15:59 Task #5495 (Closed - End of life cycle): Penambahan Biller PLN
SIT - Aug 3 - Sept 11
UAT - Oct 19 - Oct 30
Live - Nov 14
Tan Lee Yong
15:57 Task #5494 (Closed - End of life cycle): Fraud Mitigation Development
SIT - Oct 14 - Oct 20
UAT - Oct 14 - Oct 27
Live - Nov 6
Tan Lee Yong
15:55 Task #5493 (Closed - End of life cycle): FCR New Transfer Rules
SIT - Oct 14 - Oct 20
UAT - Oct 14 - Oct 27
Live - Nov 6
Tan Lee Yong
15:53 Enhancement #5492 (Closed - End of life cycle): SKN BI NG Development
SIT - Sept 25 - Oct 8
UAT - Oct 9 - Oct 22
Live - Oct 25
Tan Lee Yong
08:26 Enhancement #5460: Virtual Account
Dear Gabby,
Kindly provide the credentials to login to RIB,
for me to test the page flow before I push the codes....
Yap Kah Yan

September 15, 2015

Avatar?id=2607&size=24 17:19 Enhancement #5460: Virtual Account
Dear Kah Yan,
Kindly push the changes to mercurial. Leave the integration for a while, because connection is still...
Rayvandy Gabbytian

September 14, 2015

15:25 Enhancement #5460: Virtual Account
finish transfer part of the module.
Pending on how to enquire on own Virtual Account (to appear in dropdown list)
Yap Kah Yan

September 09, 2015

16:57 Enhancement #5460 (Development / Work In Progress): Virtual Account
Set up VPN Connection to bii
Complete hibernate mapping & table design
Yap Kah Yan

September 07, 2015

Avatar?id=2607&size=24 18:59 Enhancement #5460: Virtual Account
Kahyan,
VA Test Data as attached.
Thank you.
Rayvandy Gabbytian
Avatar?id=2607&size=24 18:55 Enhancement #5460: Virtual Account
Dear Kah Yan,
Integration doc as attached. Use ESBPostpaid service (shall be similar to utility, or mobile postpai...
Rayvandy Gabbytian

September 04, 2015

10:02 Enhancement #5460: Virtual Account
no SI for this service Yap Kah Yan

September 03, 2015

11:59 Enhancement #5460: Virtual Account
Please advice on the scope of work. Thank you. Yap Kah Yan

September 01, 2015

Avatar?id=2607&size=24 19:39 Enhancement #5460: Virtual Account
Dear Kah Yan,
Requirement as per attached. For technical document (mapping to backend) will be sent later. Please ...
Rayvandy Gabbytian
Avatar?id=2607&size=24 18:12 Enhancement #5461 (Development / Work In Progress): Credit Card via SKN
Rayvandy Gabbytian
18:08 Enhancement #5461 (Closed - End of life cycle): Credit Card via SKN
Tan Lee Yong
18:08 Enhancement #5460 (Closed - End of life cycle): Virtual Account
Tan Lee Yong
 

Also available in: Atom