SIT - Aug 3 - Sept 11
UAT - Oct 19 - Oct 30
Live - Nov 14
History
#1 Updated by Rayvandy Gabbytian over 8 years ago
- Status changed from New - Begin Life Cycle to User Acceptance Test
On going certification. Not sure when to complete.
#2 Updated by Rayvandy Gabbytian almost 8 years ago
- Status changed from User Acceptance Test to Closed - End of life cycle
- % Done changed from 0 to 100
Dear all,
This enahancement has deployed to production.