October 22, 2013
- 09:47 Task #3591 (Finished Development): Migration Fall back - to add switch at the client application
- 09:46 Task #3571 (Finished Development): Application (CCPP, online ticketing, im2u sg integration) Cus...
- 09:45 Task #3420 (Finished Development): modification of M2U (jdk 1.4)
October 09, 2013
- 10:44 Task #3739 (Closed - End of life cycle): Cover MaybankFacadeImpl in the integration test
- Recently we have experienced quite a few regressions, which we could have identified and rectified them much earlier ...
October 05, 2013
- 23:55 Task #3646 (Pending UAT Deployment): Improve the performance of authentication operation in UPass
- The performance graph attached shows the performance improvement achieved by reducing DB-to-App round-trips, as well ...
- 14:40 Task #3418 (System Integration Test): modify upass to support end to end encription (jdk 1.4)
October 02, 2013
- 11:09 Task #3642 (Finished Development): Implement LDAP updates for user creation in UPass
- UPASS will add/update user record in LDAP during user creation.
September 30, 2013
- 12:13 Task #3646 (Work Completed-End life cycle): Improve the performance of authentication operation i...
- Currently our "internal stress test":https://staging.penril.net/jenkins/view/j%20M2U%20UPass%20Coverage/job/z%20m2u-u...
- 11:59 Task #3644 (Closed - End of life cycle): Convert the project for UPass Pre-population to EJB
- Having done so, we'll be able to trigger the operation simply using @WebService annotations; or schedule them using @...
- 11:46 Task #3642 (Work Completed-End life cycle): Implement LDAP updates for user creation in UPass
- In order to support fail back during migration period.
- 08:00 Task #3637 (Finished Development): Application (Online ticketing) Customization
- I have completed the implementation last Friday and already passed them the changes. Will wait them to deploy and test.
September 29, 2013
- 11:53 Task #3571: Application (CCPP, online ticketing, im2u sg integration) Customization
- Hazrul will handle for Online ticketing.
- 11:51 Task #3637 (Work Completed-End life cycle): Application (Online ticketing) Customization
- assist Bernard on the Online ticketing application customization.
September 27, 2013
- 17:26 Task #3621 (Finished Development): Application (im2u sg integration) Customization
- All the changes have been tested locally by pointing to SIT Upass webservice. Everything works fine. Now we have to w...