Activity

From September 30, 2013 to October 29, 2013

October 28, 2013

Avatar?id=2560&size=24 12:10 Task #3739 (Closed - End of life cycle): Cover MaybankFacadeImpl in the integration test
Ahmadi Hadi

October 22, 2013

09:47 Task #3591 (Finished Development): Migration Fall back - to add switch at the client application
Wong Bernard
09:46 Task #3571 (Finished Development): Application (CCPP, online ticketing, im2u sg integration) Cus...
Wong Bernard
09:45 Task #3420 (Finished Development): modification of M2U (jdk 1.4)
Wong Bernard

October 09, 2013

Avatar?id=2560&size=24 10:44 Task #3739 (Closed - End of life cycle): Cover MaybankFacadeImpl in the integration test
Recently we have experienced quite a few regressions, which we could have identified and rectified them much earlier ... Ahmadi Hadi

October 05, 2013

Avatar?id=2560&size=24 23:55 Task #3646 (Pending UAT Deployment): Improve the performance of authentication operation in UPass
The performance graph attached shows the performance improvement achieved by reducing DB-to-App round-trips, as well ... Ahmadi Hadi
Avatar?id=2560&size=24 14:40 Task #3418 (System Integration Test): modify upass to support end to end encription (jdk 1.4)
Ahmadi Hadi

October 02, 2013

Avatar?id=1835&size=24 11:09 Task #3642 (Finished Development): Implement LDAP updates for user creation in UPass
UPASS will add/update user record in LDAP during user creation. Mohd Hashim Mohd Hadzrul

September 30, 2013

Avatar?id=2560&size=24 12:13 Task #3646 (Work Completed-End life cycle): Improve the performance of authentication operation i...
Currently our "internal stress test":https://staging.penril.net/jenkins/view/j%20M2U%20UPass%20Coverage/job/z%20m2u-u... Ahmadi Hadi
Avatar?id=2560&size=24 11:59 Task #3644 (Closed - End of life cycle): Convert the project for UPass Pre-population to EJB
Having done so, we'll be able to trigger the operation simply using @WebService annotations; or schedule them using @... Ahmadi Hadi
Avatar?id=2560&size=24 11:46 Task #3642 (Work Completed-End life cycle): Implement LDAP updates for user creation in UPass
In order to support fail back during migration period. Ahmadi Hadi
Avatar?id=1835&size=24 08:00 Task #3637 (Finished Development): Application (Online ticketing) Customization
I have completed the implementation last Friday and already passed them the changes. Will wait them to deploy and test. Mohd Hashim Mohd Hadzrul
 

Also available in: Atom