- 18:32 Support #5206 (Closed - End of life cycle): [SCP ID :##2600##] : MSS RMBP : Cant approve user re...
- Hi Gabby
Please attend below issue:...
February 24, 2015
- 15:38 Task #5197 (System Integration Test): [SCP ID :##2590##] : Reconcile CityNet_BillPayment Offline
- Sent to Pak Wahyu for internal test.
Re: [Request ID :##2590##] : Reconcile CityNet_BillPayment Offline - 15:36 Task #5197 (Development / Work In Progress): [SCP ID :##2590##] : Reconcile CityNet_BillPayment ...
- 15:34 Task #5197: [SCP ID :##2590##] : Reconcile CityNet_BillPayment Offline
- Here is the summary of the issue:
Root Cause:
- Previous biller reconciliation program was not introduced with ne...
February 23, 2015
- 18:37 Task #5197 (Closed - End of life cycle): [SCP ID :##2590##] : Reconcile CityNet_BillPayment Offline
- Hi Gabby
Kindly attend below issue:...