- 15:22 Task #7717 (Pending SIT Deployment): FSD : Penambahan Layanan Pembayaran PLN
- Reviewed
- 15:21 Task #7751 (Pending SIT Deployment): Main Menu : Move "Investment and Insurance" Menu under "Acco...
- Updated document, please download again from Alfresco
- 15:21 Task #7740 (Pending SIT Deployment): PLN : Label Changes
- Updated document, please download again from Alfresco
- 14:49 Task #7731 (Pending SIT Deployment): PLN Prepaid - Advice Menu
- Updated document, please download again from Alfresco
August 15, 2017
- 13:14 Task #7751 (Pending Review): Main Menu : Move "Investment and Insurance" Menu under "Accounts" Menu
- Test script updated,
https://hub.penril.net/share/page/site/maybank-bii-internet-banking/document-details?nodeRef=... - 13:13 Task #7731: PLN Prepaid - Advice Menu
- Test script
https://hub.penril.net/share/page/site/maybank-bii-internet-banking/document-details?nodeRef=workspac...
August 14, 2017
- 20:28 Task #7740 (Pending Review): PLN : Label Changes
- Amy please check
https://hub.penril.net/share/page/site/maybank-bii-internet-banking/document-details?nodeRef=wor... - 19:10 Task #7731 (Pending Review): PLN Prepaid - Advice Menu
- Already tested, attached screenshot
- 19:05 Task #7751 (Internal Testing): Main Menu : Move "Investment and Insurance" Menu under "Accounts" ...
- *Hi Chee Onn,*
Thank you.
*Hi Tommy,*
Please retest and furnish the test result.
Thank you. - 17:30 Task #7751 (Finished Development): Main Menu : Move "Investment and Insurance" Menu under "Accoun...
- Hi Gabby,
Changes had been done, please refer email for the new adapter, apk and ipa i send out.
Thank you. - 13:42 Task #7731 (Internal Testing): PLN Prepaid - Advice Menu
- Hi Tommy,
I have installed the restful in SIT, you just have to test it after Chee Onn sent the apk and ipa packag... - 13:40 Task #7740 (Internal Testing): PLN : Label Changes
- *Hi Chee Onn,*
Thanks for the help.
*Hi Tommy,*
Please retest this enhancement after Chee Onn sent apk and ipa.
August 13, 2017
- 13:02 Task #7751 (Closed - End of life cycle): Main Menu : Move "Investment and Insurance" Menu under "...
- Hi Chee Onn,
As per subject. Please attend this request.
Screen cap is inside FSD last page: https://hub.penril...
August 11, 2017
- 17:30 Task #7731 (Finished Development): PLN Prepaid - Advice Menu
- Hi Gabby,
Please pull middle services and restful and deploy into development server. Please check email for the n... - 17:28 Task #7740 (Finished Development): PLN : Label Changes
- Hi Gabby,
Please refer *below* and check email for the new apk and ipa for this changes.
2. PLN POSTPAID:
Open... - 14:13 Task #7740 (Closed - End of life cycle): PLN : Label Changes
- Hi Ken,
Please attend below request:
*2. PLN POSTPAID:
Open PLN Postpaid Step 3 (Confirmation):*
- Change lab... - 14:06 Task #7717: FSD : Penambahan Layanan Pembayaran PLN
- Amy,
I updated document based on review by user.
Changes are stated in comment section. Please review.
https:/...
August 10, 2017
- 15:25 Task #7731: PLN Prepaid - Advice Menu
- Hi Chee Onn,
Please attend below request:
*Issue:*
- In RMBP, upon payment of PLN Prepaid, if host returns 68,... - 14:45 Task #7731 (Closed - End of life cycle): PLN Prepaid - Advice Menu
August 09, 2017
- 14:16 Task #7717 (Work Completed-End life cycle): FSD : Penambahan Layanan Pembayaran PLN
- Dear Amy,
I have summarized the feedback from bank. Need your information and decision if certain task shall not b...