Activity

From August 09, 2015 to September 07, 2015

September 07, 2015

10:11 KFH Labuan Change Request Change #5456: IBSCR076 - CMS Labuan FTT Straight Through Processing
To confirm:
1. validation for business registration number to accept - (eg: 001234567-P)
2. validation for country ...
Yap Kah Yan

September 03, 2015

08:21 KFH Labuan Change Request Change #5456: IBSCR076 - CMS Labuan FTT Straight Through Processing
Attached generated file from swift project Yap Kah Yan
08:19 KFH Labuan Change Request Change #5456: IBSCR076 - CMS Labuan FTT Straight Through Processing
Hafiz / Aditya,
Please help to deploy and test. Thank you.
1. Script (BIB Labuan DB)
ALTER TABLE BIB_FTT_TRA...
Yap Kah Yan

September 02, 2015

16:12 KFH Labuan Change Request Change #5456 (Development / Work In Progress): IBSCR076 - CMS Labuan FTT Straight Through Processing
- added required fields for ftt jsp
- added required fields and mapping for db
Yap Kah Yan

September 01, 2015

20:04 KFH Labuan Change Request Change #5456: IBSCR076 - CMS Labuan FTT Straight Through Processing
ITEM DESCRIPTION PLAN START DATE PLAN END DATE
------- --------------------------------------- ---------------...
Tan Lee Yong

August 28, 2015

16:17 KFH Labuan Change Request Change #5456 (Work Completed-End life cycle): IBSCR076 - CMS Labuan FTT Straight Through Processing
New Change Requirement on Foreign Telegraphic Transfer (FTT) in KFH Interbank Banking Labuan (CMS) system to use Swif... Norhaidah Md Dasuki
16:02 KFH Change Request Follow Up #5440 (Internal Testing): IBG-049 - Test Result
Hi Kak Haida,
Issue has been fixed by Hafiz.
Successfully retest.
Kindly review attached Test Result.
Nurul Akmal

August 19, 2015

18:40 KFH Change Request Task #5357: [Internal Test]Conditional Sign-off IBSCR068 & 72 - IBG Enhancement/Payment Reference
Test Result Reviewed:-
IBG-023: completed and pass with condition
IBG-035: completed and pass with condition
IBG...
Norhaidah Md Dasuki
18:30 KFH Change Request Follow Up #5440 (Work Completed-End life cycle): IBG-049 - Test Result
Hi Akmal,
Kindly check on the attached test result. There are test result that need to recheck back (refer to the ...
Norhaidah Md Dasuki
12:48 KFH Projects Task #5321: KFH SMSCron Enhancement Test
Already Deployed on STG. and still waiting for MK username password from KFH IT Aditya Prathama
12:43 KFH Projects Task #5321: KFH SMSCron Enhancement Test
Successfully tested.
Test Result attached.
Nurul Akmal
11:52 KFH Change Request Bug #5389: IBG-049: BIB EPF-Inaccurate Description
Hi Adit,
Kindly check is this task has been completed.
Norhaidah Md Dasuki

August 18, 2015

13:22 KFH Projects Task #5157: Logger Enhancement - BIB
Aditya
Please help look into this issue, i am not able to check this offside.
Ngoh Chee Ping
13:12 KFH Projects Task #5157: Logger Enhancement - BIB
Hi Chee Ping,
Thank you for your understanding and correct my mistake.
Need your help to check why data not inser...
Nurul Akmal
12:55 KFH Projects Task #5157: Logger Enhancement - BIB
Akmal
Please refer to the scenario that Haida written in this task. What you written just now "System should displ...
Ngoh Chee Ping
12:15 KFH Projects Task #5157: Logger Enhancement - BIB
Hi Chee Ping ,
Need your assistance to look into below issue.
+2nd Scenario Negative Testing+
Pending transa...
Nurul Akmal
10:14 KFH Projects Task #5321: KFH SMSCron Enhancement Test
Adit/Akmal,
What is the progress of this test? Is it complete and ready to handover to KFH IT.
Norhaidah Md Dasuki
 

Also available in: Atom