Task #13675
Change #13556: [CR23001] : Enhancement of New Registration Process for BSNeBiz
Task #13558: [CR23001] - SOW02&03 - Enhancement on existing IBAM - CDB Application & Related Module
New creation for CA
Status: | Work Completed-End life cycle | Start date: | October 06, 2023 | ||
---|---|---|---|---|---|
Priority: | Normal | Due date: | |||
Assignee: | Binti Marobi Athirah Umairah | % Done: | 80% | ||
Category: | - | Spent time: | - | ||
Target version: | - |
Description
To apply same process as new application (generate temporary password) for creation additional new CA
History
#1 Updated by Nurul Hasnieza Bt Mohd Zamri 12 months ago
- Status changed from New - Begin Life Cycle to Finished Development
- % Done changed from 0 to 80
#2 Updated by Nurul Hasnieza Bt Mohd Zamri 12 months ago
- Status changed from Finished Development to Pending SIT Deployment
#3 Updated by Nurul Hasnieza Bt Mohd Zamri 12 months ago
- Status changed from Pending SIT Deployment to Internal Testing
- Assignee changed from Nurul Hasnieza Bt Mohd Zamri to Binti Marobi Athirah Umairah
Salam Umai,
SIT deploy on 09/10/2023. Please retest.
#4 Updated by Binti Marobi Athirah Umairah 12 months ago
tested and passed.
#5 Updated by Binti Marobi Athirah Umairah 12 months ago
- Status changed from Internal Testing to User Acceptance Test
#6 Updated by Binti Marobi Athirah Umairah 11 months ago
- Status changed from User Acceptance Test to Development / Work In Progress
- Assignee changed from Binti Marobi Athirah Umairah to Nurul Hasnieza Bt Mohd Zamri
#7 Updated by Nurul Hasnieza Bt Mohd Zamri 11 months ago
- Status changed from Development / Work In Progress to Internal Testing
- Assignee changed from Nurul Hasnieza Bt Mohd Zamri to Binti Marobi Athirah Umairah
#8 Updated by Binti Marobi Athirah Umairah 11 months ago
- Status changed from Internal Testing to Work Completed-End life cycle