Task #1791

CR45-To change the TAC request flow

Added by Anonymous almost 12 years ago. Updated over 11 years ago.

Status:Work Completed-End life cycleStart date:November 21, 2012
Priority:NormalDue date:November 23, 2012
Assignee:-% Done:

100%

Category:-Estimated time:24.00 hours
Target version:-Spent time:3.00 hours

CR_45.docx (41.6 KB) Anonymous, November 21, 2012 17:19

History

#1 Updated by Ngoh Chee Ping almost 12 years ago

  • Status changed from New - Begin Life Cycle to Development / Work In Progress
  • Start date changed from November 20, 2012 to November 21, 2012
  • % Done changed from 0 to 100

#2 Updated by Anonymous almost 12 years ago

  • File CR_45.docx added
  • Due date set to November 23, 2012
  • Assignee set to Ngoh Chee Ping
  • Estimated time set to 24.00

1. Update Program
2. Upon completion of UAT, update Demo & Manuals

#3 Updated by Anonymous almost 12 years ago

  • File deleted (CR_45.docx)

#4 Updated by Ngoh Chee Ping almost 12 years ago

  • Status changed from Development / Work In Progress to Finished Development

#5 Updated by Ngoh Chee Ping almost 12 years ago

  • Assignee changed from Ngoh Chee Ping to Tan Lee Yong

Delivered to LH bank on 22 November 2012

#6 Updated by Anonymous over 11 years ago

  • Assignee changed from Tan Lee Yong to Man Siew Yong

Please update RIB User Manual - Refer document @ RedMine

#7 Updated by Man Siew Yong over 11 years ago

  • Assignee changed from Man Siew Yong to Anonymous

#8 Updated by Anonymous over 11 years ago

  • Status changed from Finished Development to Work Completed-End life cycle