Task #1791
CR45-To change the TAC request flow
Status: | Work Completed-End life cycle | Start date: | November 21, 2012 | |
---|---|---|---|---|
Priority: | Normal | Due date: | November 23, 2012 | |
Assignee: | - | % Done: | 100% | |
Category: | - | Estimated time: | 24.00 hours | |
Target version: | - | Spent time: | 3.00 hours |
History
#1 Updated by Ngoh Chee Ping almost 12 years ago
- Status changed from New - Begin Life Cycle to Development / Work In Progress
- Start date changed from November 20, 2012 to November 21, 2012
- % Done changed from 0 to 100
#2 Updated by Anonymous almost 12 years ago
- File CR_45.docx added
- Due date set to November 23, 2012
- Assignee set to Ngoh Chee Ping
- Estimated time set to 24.00
1. Update Program
2. Upon completion of UAT, update Demo & Manuals
#3 Updated by Anonymous almost 12 years ago
- File deleted (
CR_45.docx)
#4 Updated by Ngoh Chee Ping almost 12 years ago
- Status changed from Development / Work In Progress to Finished Development
#5 Updated by Ngoh Chee Ping almost 12 years ago
- Assignee changed from Ngoh Chee Ping to Tan Lee Yong
Delivered to LH bank on 22 November 2012
#6 Updated by Anonymous over 11 years ago
- Assignee changed from Tan Lee Yong to Man Siew Yong
Please update RIB User Manual - Refer document @ RedMine
#7 Updated by Man Siew Yong over 11 years ago
- Assignee changed from Man Siew Yong to Anonymous
#8 Updated by Anonymous over 11 years ago
- Status changed from Finished Development to Work Completed-End life cycle