IBAM >IBAM : User Profile Maintenance - Unlock
Status: | Work Completed-End life cycle | Start date: | April 09, 2013 | |
---|---|---|---|---|
Priority: | Normal | Due date: | April 10, 2013 | |
Assignee: | Lizahwati Basirun | % Done: | 100% | |
Category: | IBAM - User Profile Maintnce | Estimated time: | 0.30 hour | |
Target version: | - | Spent time: | 1.70 hour |
Description
User Profile Maintenance - Unlock Confirm
1. No needs to review details in Confirmation page.
2. Add on Confirmation Message
User Profile Maintenance - Unlock Result
3. Add on User value and remove details wording at result page without Authorization Proses.
Expected Result: User gabby10 has been successfully unlocked
User Profile Maintenance - Unlock Result
4. Remove Double Colon in front of User.
Expected Result: User momoadmin has been unlock and pending for approval
Related issues
History
#1 Updated by Almasi Moein over 11 years ago
- Due date set to April 10, 2013
- % Done changed from 0 to 100
- Estimated time set to 1.00
fixed, proceed with deployment for internal testing.
#2 Updated by Tan Lee Yong over 11 years ago
- Estimated time deleted (
1.00)
#3 Updated by Tan Lee Yong over 11 years ago
- Status changed from New - Begin Life Cycle to Development / Work In Progress
#4 Updated by Tan Lee Yong over 11 years ago
- Status changed from Development / Work In Progress to Finished Development
#5 Updated by Alwi Husada over 11 years ago
- Status changed from Finished Development to Internal Testing
- Assignee changed from Alwi Husada to Siti Norahayu Mohd Desa
deployed to sit.phase2,
#6 Updated by Siti Norahayu Mohd Desa over 11 years ago
- Status changed from Internal Testing to Development / Work In Progress
- Assignee changed from Siti Norahayu Mohd Desa to Alwi Husada
- % Done changed from 100 to 80
Test Failed!
Please follow the Expected Result attached. TQ
#7 Updated by Almasi Moein over 11 years ago
- % Done changed from 80 to 100
fixed, proceed with deployment for internal testing.
#8 Updated by Alwi Husada over 11 years ago
- Status changed from Development / Work In Progress to Internal Testing
- Assignee changed from Alwi Husada to Siti Norahayu Mohd Desa
Deployed to IBAM Phase2
Thanks
#9 Updated by Siti Norahayu Mohd Desa over 11 years ago
- Status changed from Internal Testing to Development / Work In Progress
- Assignee changed from Siti Norahayu Mohd Desa to Alwi Husada
- % Done changed from 100 to 90
- Estimated time set to 0.30
User Profile Maintenance - Unlock Confirm
1. No needs to review details in Confirmation page. - Passed
2. Add on Confirmation Message - Passed
User Profile Maintenance - Unlock Result
3. Add on User value and remove details wording at result page without Authorization Proses. - Failed
Actual Result: User momoadmin have been successfully unlocked Unlocked
Expected Result: User gabby10 has been successfully unlocked
User Profile Maintenance - Unlock Result
4. Remove Double Colon in front of User. - Failed
Actual Result: User momoadmin has been pending for Unlock
Expected Result: User momoadmin has been unlock and pending for approval
Hi Alwi,
Kindly assist to change based on the expected result given. TQ
#10 Updated by Alwi Husada over 11 years ago
- Status changed from Development / Work In Progress to Internal Testing
- Assignee changed from Alwi Husada to Lizahwati Basirun
- % Done changed from 90 to 100
#11 Updated by Lizahwati Basirun over 11 years ago
- Status changed from Internal Testing to Work Completed-End life cycle
Hi,
Fixed and successfully re-tested.