Change #5056
Task #5061: JomPAY UAT Tracking
CR-00020: UAT-RIB001_New & Fav JomPAY - Report HOST (DDI300P & ON US)
Status: | Closed - End of life cycle | Start date: | December 15, 2014 | |
---|---|---|---|---|
Priority: | Normal | Due date: | ||
Assignee: | Nurul Akmal | % Done: | 100% | |
Category: | NBPS UAT | Spent time: | 11.00 hours | |
Target version: | - |
Description
Hi Ton,
Kindly assist on below request.
Front end did not sent Filler04 and there is no filler04 field in wsdl's middleware.
Once Beans provide wsdl file, kindly update for our side.
Actual Result:
Report HOST (DDI300P & ON US) did not display On Us Tranx
Expected Result:
On Us Tranx should display in HOST Report (DDI300P & ON US)
Thank you.
Related issues
History
#1 Updated by Norhaidah Md Dasuki almost 10 years ago
- Subject changed from CR-00020: IE0000078C - New & Fav JomPAY - Report HOST (DDI300P & ON US) to CR-00020: UAT-RIB001_New & Fav JomPAY - Report HOST (DDI300P & ON US)
#2 Updated by Norhaidah Md Dasuki almost 10 years ago
- Category set to 232
#3 Updated by Norhaidah Md Dasuki almost 10 years ago
- Category changed from 232 to NBPS UAT
- Parent task set to #5061
#4 Updated by Wijaya Kartono almost 10 years ago
- Status changed from New - Begin Life Cycle to Internal Testing
- Assignee changed from Wijaya Kartono to Nurul Akmal
- % Done changed from 0 to 70
Hi kak Akmal,
Filler04 had been mapped into request message as per requirement. Kindly test and make sure IB send correct details to the HOST. Thank you.
#5 Updated by Wijaya Kartono over 9 years ago
Changes:
- Updated filler04 spec for both RIB and BIB Bill Payment (refer attached doc).
- Updated NBPS integration for both RIB and BIB Bill Payment (filler04).
#6 Updated by Tan Lee Yong over 9 years ago
Hi Akmal, any update?
#7 Updated by Nurul Akmal over 9 years ago
Has been tested and IT checked that Front End sent Filler 04 as per BEANS spec. But when compared to Silverlake spec, BEANS spec has missed some fields. And currently we are working on to add those missed part.
#8 Updated by Nurul Akmal over 9 years ago
- Status changed from Internal Testing to Closed - End of life cycle
- % Done changed from 70 to 100
Deployed to production on 03/03/2015.