Task #5099
Implementation Plan
Status: | Work Completed-End life cycle | Start date: | January 02, 2015 | |
---|---|---|---|---|
Priority: | Normal | Due date: | January 07, 2015 | |
Assignee: | - | % Done: | 100% | |
Category: | - | Spent time: | - | |
Target version: | - |
Description
Please prepare implementation plan
- List down all the database table to add / modify
- Prepare the data to be created / updated in DB
Target to cutover is on 24/1/2014
History
#1 Updated by Stephanie Sufrapto over 9 years ago
- Assignee changed from Stephanie Sufrapto to Anonymous
- % Done changed from 0 to 100
Done the sql script sent to chee ping to check
#2 Updated by Ngoh Chee Ping over 9 years ago
- File MCI Revamp.sql added
- Status changed from New - Begin Life Cycle to Finished Development
Already check the db script, no problem.
#3 Updated by Anonymous over 9 years ago
- Status changed from Finished Development to Work Completed-End life cycle