Calendar should display year based on existing data. Apply to all screen and report parameter

Enhancement#5449_Test Result-TPMS_UAT_088.docx (1.88 MB) Lim Leonard, January 29, 2016 12:11


Related issues

Related to MATRADE_TPMS Support - Enhancement #6035: [TPMS_Prod017 & 018] - Planning JPPPA - Report Closed - End of life cycle March 04, 2016

History

#1 Updated by Siti Norahayu Mohd Desa almost 9 years ago

  • Assignee changed from Najmi Pasarudin to Norhaidah Md Dasuki

Hi Iman,
Kindly assist

#2 Updated by Siti Norahayu Mohd Desa almost 9 years ago

  • Assignee changed from Norhaidah Md Dasuki to Shahidan Syahirman

#3 Updated by Norhaidah Md Dasuki almost 9 years ago

  • Project changed from Development & Internal Test (M1&2) to MATRADE - TPMS UAT Conditional Sign-off
  • Subject changed from [TPMS_UAT_088] - Search Filter >> Date Range to [UAT1&2 - UAT_088] - Search Filter >> Date Range
  • Due date changed from August 31, 2015 to December 30, 2015
  • Category changed from TPMS_UAT to KIV_Phase1
  • Start date changed from August 27, 2015 to December 23, 2015

To fix as below:

i. The year dropdown list in search function on JPPPA activities list will only have years that in database.
ii. The year dropdown list JPPPA report will only have years that in database.

#4 Updated by Shahidan Syahirman almost 9 years ago

  • Status changed from New - Begin Life Cycle to Internal Testing
  • Assignee changed from Shahidan Syahirman to Siti Norahayu Mohd Desa

hi akak,

enhancement done. please check

thank you

#5 Updated by Siti Norahayu Mohd Desa over 8 years ago

  • Status changed from Internal Testing to Development / Work In Progress
  • Assignee changed from Siti Norahayu Mohd Desa to Aditya Prathama

unable to view year in http://172.25.96.136/matrade-tpms/ for Planning JPPPA

#6 Updated by Aditya Prathama over 8 years ago

  • Assignee changed from Aditya Prathama to Siti Norahayu Mohd Desa
  • % Done changed from 0 to 100

Finding: Invalid path for retrieve year list from server

Solution: Put correct path to retrieve year list

#7 Updated by Siti Norahayu Mohd Desa over 8 years ago

  • Assignee changed from Siti Norahayu Mohd Desa to Lim Leonard

#8 Updated by Lim Leonard over 8 years ago

  • Assignee changed from Lim Leonard to Aditya Prathama

Hi Adit

Please Assist on this issue

the year for Date Range, still showing the year that dont have existing data,

Thank You

#9 Updated by Aditya Prathama over 8 years ago

  • Status changed from Development / Work In Progress to Internal Testing
  • Assignee changed from Aditya Prathama to Lim Leonard

fixed please retest

#10 Updated by Lim Leonard over 8 years ago

  • Assignee changed from Lim Leonard to Aditya Prathama

the issue is still exist,
you can try by comparing the result in date range by year,
there are the year that's not shown in the date range by year,
but for the date range by date range the year selection is shown.

please kindly fix this

#11 Updated by Aditya Prathama over 8 years ago

  • Assignee changed from Aditya Prathama to Lim Leonard

fixed. retest

#12 Updated by Lim Leonard over 8 years ago

  • Assignee changed from Lim Leonard to Aditya Prathama

hi Adit,

I rechecked it,
and the issue is still exist
it seems that you only fixed few of the date range, from all of the search filter,

please kindly help
thank you

#13 Updated by Aditya Prathama over 8 years ago

  • Assignee changed from Aditya Prathama to Lim Leonard

Please retest,
if found any issue please provide me page url and expected requirement.
thanks

#14 Updated by Lim Leonard over 8 years ago

  • Status changed from Internal Testing to Development / Work In Progress
  • Assignee changed from Lim Leonard to Aditya Prathama

Hi Adit,

Please check on :
Planning > Reports > Budget Report -> Yearly
Planning > Reports > Planning Report -> Monthly
Execution -> Date Range
Post Event > JPPPA Programme -> Date Range

Thank You

#15 Updated by Aditya Prathama over 8 years ago

  • Assignee changed from Aditya Prathama to Lim Leonard

updated please retest at http://172.25.96.136/matrade-tpms
thanks

#16 Updated by Lim Leonard over 8 years ago

attached is the test result for this issue

#17 Updated by Norhaidah Md Dasuki over 8 years ago

  • Status changed from Pending Prod Deployment to User Acceptance Test

#18 Updated by Norhaidah Md Dasuki over 8 years ago

  • Status changed from User Acceptance Test to Development / Work In Progress
  • Assignee changed from Norhaidah Md Dasuki to Aditya Prathama

Based on further discussion with En. Rizal and SD (Najmie), TPMS will display detail search based on fixed starting year 2002 for Planning – Activities List and 2013 for Planning JPPPA. As for ending year it will be current year plus 5 years onward.

Adit to fix.

#19 Updated by Siti Norahayu Mohd Desa over 8 years ago

  • Assignee changed from Aditya Prathama to Ngoh Chee Onn

Hi Chee Onn,

Kindly assist.

TPMS will display detail search based below:
For Planning starting year 2002
For Planning JPPPA starting year 2013

#20 Avatar?id=1966&size=24 Updated by Ngoh Chee Onn over 8 years ago

  • Status changed from Development / Work In Progress to Internal Testing
  • Assignee changed from Ngoh Chee Onn to Siti Norahayu Mohd Desa
  • % Done changed from 0 to 100

Hi Ayu,

Search filter change according to user request, please test on SIT enhancement environment as URL below.
http://172.25.96.136/matrade-tpms-enhancement/login

Thank you.

#21 Updated by Siti Norahayu Mohd Desa over 8 years ago

  • Status changed from Internal Testing to Development / Work In Progress
  • Assignee changed from Siti Norahayu Mohd Desa to Aditya Prathama

New Request :

TPMS will display detail search based on fixed starting year 2002 for Planning and Planning JPPPA.

Hi Adit,
Kindly assist.

#22 Updated by Aditya Prathama over 8 years ago

  • Status changed from Development / Work In Progress to Internal Testing
  • Assignee changed from Aditya Prathama to Siti Norahayu Mohd Desa

For this changes, already apply since last enhancement branch testing. current version already has this changes

#23 Updated by Siti Norahayu Mohd Desa over 8 years ago

  • Assignee changed from Siti Norahayu Mohd Desa to Lim Leonard

HI Leo,

Kindly assist to prepare the test result. TQ

#24 Updated by Lim Leonard over 8 years ago

  • Status changed from Internal Testing to Development / Work In Progress
  • Assignee changed from Lim Leonard to Aditya Prathama

Hi Adit,

Execution > Report > Date range - starts from 2006
Post Event > JPPPA Programmes - starts from 2013
Post Event > JPPPA Report - Starts from 2013

Please fix this

#25 Updated by Aditya Prathama over 8 years ago

  • Status changed from Development / Work In Progress to Internal Testing
  • Assignee changed from Aditya Prathama to Lim Leonard

date bug fixed, please retest

#26 Updated by Norhaidah Md Dasuki over 8 years ago

  • Status changed from Internal Testing to Pending Prod Deployment

11/4/2016 [Fadzilah] - Successfully tested and Closed
Pending Pro Deployment

#27 Updated by Norhaidah Md Dasuki over 8 years ago

  • Status changed from Pending Prod Deployment to Closed - End of life cycle

13/5/2016 - Successfully deployed to Production
Migration Ver:029