Enhancement #5831
[UAT3-9 - UAT_093] - Promotion > Business Meeting
Status: | Closed - End of life cycle | Start date: | December 13, 2015 | |
---|---|---|---|---|
Priority: | Normal | Due date: | December 13, 2015 | |
Assignee: | Norhaidah Md Dasuki | % Done: | 100% | |
Category: | KIV_Phase2 | Spent time: | - | |
Target version: | - |
Description
Company address for buyer should be same format with Malaysian company. Follow Malaysian Company format.
Please refer attachment for reference.
History
#1 Updated by Siti Norahayu Mohd Desa almost 9 years ago
- Assignee changed from Stephanie Sufrapto to Tan Jeng Wei
#2 Updated by Tan Jeng Wei almost 9 years ago
- Status changed from New - Begin Life Cycle to Internal Testing
- % Done changed from 0 to 90
#3 Updated by Tan Jeng Wei almost 9 years ago
- Assignee changed from Tan Jeng Wei to Siti Norahayu Mohd Desa
Hi ayu
Company address for buyer should be same format with Malaysian company. Follow Malaysian Company format.----> fixed.
Change Task also not yet deployed into TPMS system. Please test after deployed.... Thanks alot.
#4 Updated by Siti Norahayu Mohd Desa almost 9 years ago
- Tracker changed from Change to Enhancement
- Project changed from TPMS_M3-M9: UAT to MATRADE - TPMS UAT Conditional Sign-off
- Subject changed from [UAT3-9/093] - Promotion > Business Meeting to [UAT3-9 - UAT_093] - Promotion > Business Meeting
- Category deleted (
tpms_uat)
#5 Updated by Norhaidah Md Dasuki almost 9 years ago
- Category set to KIV_Phase2
#6 Updated by Siti Norahayu Mohd Desa over 8 years ago
- Status changed from Internal Testing to User Acceptance Test
- % Done changed from 90 to 100
18/1/2016
Hi Aditya,
Please remove compulsory at Address 2 & 3 and Postcode.
#7 Updated by Siti Norahayu Mohd Desa over 8 years ago
- Status changed from User Acceptance Test to Development / Work In Progress
- Assignee changed from Siti Norahayu Mohd Desa to Aditya Prathama
#8 Updated by Aditya Prathama over 8 years ago
- Status changed from Development / Work In Progress to Internal Testing
- Assignee changed from Aditya Prathama to Siti Norahayu Mohd Desa
Validation removed, please retest
#9 Updated by Tan Lee Yong over 8 years ago
- Assignee changed from Siti Norahayu Mohd Desa to Lim Leonard
#10 Updated by Lim Leonard over 8 years ago
- File Enhancement#5831_Test Result-TPMS_UAT_093.docx added
- Status changed from Internal Testing to User Acceptance Test
- Assignee changed from Lim Leonard to Norhaidah Md Dasuki
attached is the test result
thank you
#11 Updated by Norhaidah Md Dasuki over 8 years ago
15/2/16 - forward to IT for retest
#12 Updated by Norhaidah Md Dasuki over 8 years ago
5/4/2016 - Send for SIT/UAT via email dated Wed, Feb 15, 2016. Resend for retest.
#13 Updated by Norhaidah Md Dasuki over 8 years ago
- Status changed from User Acceptance Test to Pending Prod Deployment
8/4/2016 [Azliza] - already test.
Pending for Prod. Deployment.
#14 Updated by Norhaidah Md Dasuki over 8 years ago
- Status changed from Pending Prod Deployment to Closed - End of life cycle
13/5/2016 - Successfully deployed to Production
Migration Ver:029