Task #598
AirAsia: Assist Task 584 - front end development
Status: | Work Completed-End life cycle | Start date: | October 27, 2010 | |
---|---|---|---|---|
Priority: | Normal | Due date: | November 01, 2010 | |
Assignee: | Ngoh Chee Ping | % Done: | 100% | |
Category: | - | Spent time: | 14.00 hours | |
Target version: | - |
Description
To assist to complete the front end development first.
History
#1 Updated by Ngoh Chee Ping almost 14 years ago
- Status changed from New - Begin Life Cycle to Development / Work In Progress
- % Done changed from 0 to 40
Now i help do the generate paper that part, now i already finish do the add paper, and add questions to the paper. For export paper out into difference formats havent finish.
#2 Updated by Ngoh Chee Ping almost 14 years ago
- % Done changed from 40 to 80
#3 Updated by Ngoh Chee Ping almost 14 years ago
- Status changed from Development / Work In Progress to Work Completed-End life cycle
- % Done changed from 80 to 100