Bug #6092
Planning >> Activities List
Status: | Work Completed-End life cycle | Start date: | March 17, 2016 | |
---|---|---|---|---|
Priority: | Normal | Due date: | ||
Assignee: | Norhaidah Md Dasuki | % Done: | 100% | |
Category: | CR_Phase1 | Spent time: | - | |
Target version: | - |
Description
Dear Adit,
Kindly assist to fix on the "blue screen" error. (THE SYSTEM HAS ENCOUNTERED AN ERROR. PLEASE CONTACT SYSTEM ADMINISTRATOR.)
Step to replicate:- Click on TPMS>Planning>Activities List
- Click on Add Activity
Current Result:
System throw "THE SYSTEM HAS ENCOUNTERED AN ERROR. PLEASE CONTACT SYSTEM ADMINISTRATOR." screen
Expected Result:
Should display the add activity screen.
Related issues
History
#1 Updated by Norhaidah Md Dasuki over 8 years ago
- Category set to CR_Phase1
#2 Updated by Aditya Prathama over 8 years ago
- Assignee changed from Aditya Prathama to Lizahwati Basirun
- % Done changed from 0 to 100
Finding: found null pointer on controller
Solution : fix null pointer to escape null pointer exception
#3 Updated by Norhaidah Md Dasuki over 8 years ago
- Status changed from New - Begin Life Cycle to Internal Testing
- Assignee changed from Lizahwati Basirun to Lim Leonard
Leo please test.
#4 Updated by Lim Leonard over 8 years ago
- File Bug#6092_Test Result.docx added
- Status changed from Internal Testing to Pending Review
- Assignee changed from Lim Leonard to Norhaidah Md Dasuki
test result attached
#5 Updated by Norhaidah Md Dasuki over 8 years ago
- Status changed from Pending Review to Work Completed-End life cycle