Task #8166
[RPP Traceability] - PayNet Admin
Status: | Work Completed-End life cycle | Start date: | January 04, 2018 | |
---|---|---|---|---|
Priority: | Normal | Due date: | January 05, 2018 | |
Assignee: | Nurul Akmal | % Done: | 100% | |
Category: | - | Spent time: | - | |
Target version: | - |
Description
To update trace-ability matrix for PayNet Admin.
P/S: Unable to attach FSD. Please refer updated FSD at alfresco.
History
#1 Updated by Siti Norahayu Mohd Desa over 6 years ago
- File Trace-Matrix - RPP ver1.0.xlsx added
- File RPP Test Script (V1).docx added
- Description updated (diff)
#2 Updated by Nurul Akmal over 6 years ago
- % Done changed from 0 to 40
#3 Updated by Nurul Akmal almost 6 years ago
- Status changed from New - Begin Life Cycle to Work Completed-End life cycle