April 30, 2015
- 14:18 Agrobank Change Request Task #4757 (Rejected - End of life cycle): CR-00035: [RIB/BIB] Enhancement for IBG and Transactio...
- since cr already expired. a new cr is required and new task will create in different folder for tracking. will procee...
- 14:16 Agrobank Change Request Task #4780 (Rejected - End of life cycle): CR-00033_Bulk Payment
- User did not finalize the requirement and it may not proceed. a new folder created for tracking those cr in differen...
- 14:13 Agrobank Change Request Task #4756 (Rejected - End of life cycle): CR-00029: [BIB] Zakat Payment at BIB
- since the cr already expired and user did not put this in thier priority list. proceed for cancellation.
- 14:12 Agrobank Change Request Task #4755 (Rejected - End of life cycle): CR-00030 : [IBAM] Set Limit by Company per day
- since cr already expired. a new cr will be issue to user and new redmine task to be created. will proceed cancel this...
- 14:11 Agrobank Change Request Task #4378 (Rejected - End of life cycle): CR-00025 : IBAM Dynamic Report
- since CR already expired and it may take another yr for user to confirm. will proceed to cancel it.
April 29, 2015
- 16:11 Task #4944: Patch: Upgrade SMSCron to support active-active cluster [related to Request ID :##248...
- Hi Kartono,
please update us on the testing status for this case. TQ.
If you needed Akmal help for testing, please ... - 11:07 Agrobank Change Request Task #5187 (Work Completed-End life cycle): CR-00027_GST- New and Favorite eIBFT to add * on char...
- Dear Kak Haida,
Please find attached the test result for eIBFT.
_Notes:
Unable to test for Favourite eIBFT du...
April 28, 2015
- 18:25 Agrobank Change Request Task #5060 (Pending Prod Deployment): CR-00027_RIB & BIB Demo for GST Implementation Screen
- Test results reviewed and pending for deployment to Production.
- 18:22 Agrobank Change Request Task #4755 (Pending Customer Feedback): CR-00030 : [IBAM] Set Limit by Company per day
- 28/4/15 - CR expired. SOW send to IT on 11/09/2014. Need to follow up with USER/IT.
- 18:20 Agrobank Change Request Task #4756 (Pending Customer Feedback): CR-00029: [BIB] Zakat Payment at BIB
- 28/4/15 - CR expired. SOW send to IT on 12/08/2014. Need to follow up with USER/IT.
- 18:18 Agrobank Change Request Task #4757 (Pending Customer Feedback): CR-00035: [RIB/BIB] Enhancement for IBG and Transaction H...
- 28/4/15 - CR expired. SOW send to IT on 11/09/2014. Need to follow up with User/IT.
- 18:16 Agrobank Change Request Task #4523 (Dropped-End of life cycle): CR-00025 : IBAM Dynamic Report [Statistic Report]
- Dropped. Requirement study needed. refer #4378
- 18:15 Agrobank Change Request Task #4780: CR-00033_Bulk Payment
- 28/4/15 - Requirement Study and New Timeline setup for Bulk Payment
- 18:08 Agrobank Change Request Task #4437 (Work Completed-End life cycle): CR-00020 : IE0000078C - National Bill Payment Scheme ...
- Issue fixed and successfully migrated to Production on 4/3/2015
- 18:06 Agrobank Change Request Task #4378 (Pending Customer Feedback): CR-00025 : IBAM Dynamic Report
- 24/4/15 - CR already expired. Need to follow-up with user on the request details.
- 17:35 Agrobank Change Request Task #3449 (Dropped-End of life cycle): CR-0009 - BIB_Filter
- Dropped this CR as NO feedback from User. Refer attachment on the follow-up from last email by IT on 26/12/13 . Anoth...
- 17:34 Agrobank Change Request Task #3448 (Dropped-End of life cycle): CR-0008 - RIB User Status Maintenance
- Dropped this CR as NO feedback from User. Refer attachment on the follow-up from last email by IT on 26/12/13 . Anoth...
- 17:32 Agrobank Change Request Task #3447 (Dropped-End of life cycle): CR-0007 - Special Daily Limit
- Dropped this CR as NO feedback from User. Refer attachment on the follow-up from last email by IT on 26/12/13 . Anoth...
- 17:23 Agrobank Change Request Task #5061 (Work Completed-End life cycle): JomPAY UAT Tracking
- CR Completed. Successfully migrated to production on 4/3/2015
- 17:18 Agrobank Change Request Bug #5189 (Work Completed-End life cycle): CR-00027_GST testing defect 239: Error while approving...
- Internal Test RESULTS reviewed.
Successfully deployed to production on 31/3/2015. - 17:17 Agrobank Change Request Bug #5235 (Work Completed-End life cycle): CR-00027_GST- RIB eIBFT: Receipt do not printed with G...
- Internal Test RESULTS reviewed.
Successfully deployed to production on 31/3/2015. - 17:16 Agrobank Change Request Task #5236 (Work Completed-End life cycle): CR-00027_GST- eIBFT: change label from IBG Charges to...
- Internal Test RESULTS reviewed.
Successfully deployed to production on 31/3/2015. - 17:11 Agrobank Change Request Bug #5237 (Work Completed-End life cycle): CR-00027_GST- Defect : IBAM - RIB Transaction History ...
- Internal Test results reviewed.
Successfully deployed to production on 31/3/2015. - 15:54 Agrobank Change Request Bug #5077 (Closed - End of life cycle): CR-00020:UAT-RIB004_ RIB>Account & Banking>Transaction Hi...
- Deployed to production on 03/03/2014.
- 15:52 Agrobank Change Request Bug #5079 (Closed - End of life cycle): CR-00020: UAT-RIB006_New & Fav JomPAY - GL Report
- 15:46 Agrobank Change Request Bug #5079: CR-00020: UAT-RIB006_New & Fav JomPAY - GL Report
- Deployed to production on 03/03/2015.
- 15:45 Agrobank Change Request Change #5056 (Closed - End of life cycle): CR-00020: UAT-RIB001_New & Fav JomPAY - Report HOST (D...
- Deployed to production on 03/03/2015.
April 23, 2015
- 13:00 Agrobank Change Request Task #5180 (Work Completed-End life cycle): CR-00027_GST- change of GST calculator formula
- Migrated to production on 21/03/2015
April 22, 2015
- 17:52 Agrobank Change Request Task #4730 (Work Completed-End life cycle): CR-00027 : [RIB/BIB] GST
- Migrated to production on 21/03/2015
- 17:51 Agrobank Change Request Task #5094 (Work Completed-End life cycle): CR-00027_GST Integration for RIB and BIB
- Migrated to production on 21/03/2015
April 20, 2015
- 15:51 Agrobank Change Request Bug #5192 (Closed - End of life cycle): CR-00027_GST testing defect 244: Agronet Transaction Hist...
- completed. GST migrated to production on 15 March.
April 10, 2015
- 11:10 Task #4944: Patch: Upgrade SMSCron to support active-active cluster [related to Request ID :##248...
- Hi Kartono,
please retest and if error found, then please assist fix the issue.
April 09, 2015
- 16:05 Agrobank Change Request Task #5094: CR-00027_GST Integration for RIB and BIB
- Hi Liza,
Kindly review the test result documentation. Thank you.