July 25, 2012
- 09:56 Task #1593 (Development / Work In Progress): SupportCenter Plus Installation project
- *Done so far:*
a) Installed new OS on the new machine
b) SugarCRM managed to moved after +several+ upgrade
c) Supp... - 09:38 Task #1593 (Closed - End of life cycle): SupportCenter Plus Installation project
- *Project*: To install Manageengine SupportCenter Plus software as another method to support Penril's client
*Scena... - 09:19 Task #660 (Work Completed-End life cycle): AgroBank POC