August 01, 2013
- 17:00 ePay_Internal Testing Task #3376: [Test Script] - ePrepaid Top Up for RIB
- Hi Elham, Kindly assist.
- 16:57 ePay_Internal Testing Task #3376 (Work Completed-End life cycle): [Test Script] - ePrepaid Top Up for RIB
- To create test scrip for ePrepaid Top Up based on BRS.
July 26, 2013
- 15:25 Task #3360 (Development / Work In Progress): Integration module for ePay
- 15:14 Task #3363 (Work Completed-End life cycle): Mobile Reload Report
- * Create ePrepaid top up Report.
* Modify the report header for all reports - 15:11 Task #3362 (Work Completed-End life cycle): RIB: Mobile Reload Limit
- * Create a maintenance module to set maximum reload limit.
- 15:05 Task #3361 (Work Completed-End life cycle): RIB: Mobile Report Module
- * Create two separate modules: Pinless and Pin Based. Each module divided into a few steps allowing the customers to ...
- 14:57 Task #3360 (Work Completed-End life cycle): Integration module for ePay
- * Create interface to integrate with Host. Composing of request message and send to host. Capture the response from h...
- 14:54 Task #3359 (Work Completed-End life cycle): Create Navigation and Products
- * Create new navigation menu for Mobile Reload
> > Pinless Reload
> > Pin Based Reload
> > Others: Reload Limit
... - 14:49 Task #3358 (Work Completed-End life cycle): Create Database table and Data Layer
- * Create new tables for Mobile Reload module.
* Create application interface and mapping file.
* Create methods to ...