May 09, 2017

15:12 Support #7417 (Development / Work In Progress): [TPMS_GL085] - Post Event Report for TIM
Najmi Pasarudin

May 05, 2017

15:09 Support #7424 (Internal Testing): [TPMS_GL086] - Promotion > Event Setup > Committee
Issue:
Promotion Committee edit does not load user list and user cannot be assigned in event committee.
Cause:
W...
Najmi Pasarudin
14:58 Support #7424 (Development / Work In Progress): [TPMS_GL086] - Promotion > Event Setup > Committee
Najmi Pasarudin
12:13 Support #7424 (Work Completed-End life cycle): [TPMS_GL086] - Promotion > Event Setup > Committee
Case ID : TPMS/17-0016
Mohon untuk semak samada terdapat bugs atau tidak pada modul Promotion -> Event Setup-> Com...
Siti Norahayu Mohd Desa

May 03, 2017

10:41 Support #7417 (Work Completed-End life cycle): [TPMS_GL085] - Post Event Report for TIM
Case ID : TPMS/17-0015
There is an error in te Post Event Report for Trade and Investment Mission To Japan and Kor...
Siti Norahayu Mohd Desa

May 02, 2017

12:46 Support #7411 (User Acceptance Test): [TPMS_GL083] - Event Participating Company
Send for user testing Siti Norahayu Mohd Desa
11:15 Support #7408 (Development / Work In Progress): [TPMS_GL082] - Post Event > Feedback Form
Najmi Pasarudin
11:14 Support #7411 (Internal Testing): [TPMS_GL083] - Event Participating Company
Issue:
Database contains wrong data for ec_bumi_status column in table event_participating_company.
Cause:
Wrong...
Najmi Pasarudin
11:11 Support #7411 (Development / Work In Progress): [TPMS_GL083] - Event Participating Company
Najmi Pasarudin
10:49 Support #7412 (Work Completed-End life cycle): [TPMS_GL084] - ARAB HEALTH 2017 (REPORT SALES)
Case ID : TPMS/17-0014
The sales for the above event in TPMS is not same with the manual report. To check the cu...
Siti Norahayu Mohd Desa
10:39 Support #7411 (Work Completed-End life cycle): [TPMS_GL083] - Event Participating Company
Case ID : TPMS/17-0013
We found out that the data for ec_bumi_status column in event_participating_company is w...
Siti Norahayu Mohd Desa

April 27, 2017

14:46 Support #7408 (Work Completed-End life cycle): [TPMS_GL082] - Post Event > Feedback Form
Case ID : TPMS/17-0012
When user click the link follow up feedback form from email they received, feedback form wa...
Siti Norahayu Mohd Desa
10:19 Change #6750 (Dropped-End of life cycle): [TPMS_GL064] - Promotion >> Registration - Unable to re...
Najmi Pasarudin
10:18 Support #7134 (Work Completed-End life cycle): [TPMS_GL076] - Post Event >> Feedback
Najmi Pasarudin
10:17 Change #6559 (Dropped-End of life cycle): [TPMS_GL051] - Promotion >> Business Meeting >> Busines...
This is considered CR. Matrade setup business meeting from lunch hour(1pm) as alternative for meeting that start at 2pm. Najmi Pasarudin
10:13 Support #7231 (Work Completed-End life cycle): [TPMS_GL080] - Post Event > JPPPA Report > Outcome...
Email from Arshad(Matrade IT department personnel):
> Dear Najmi,
>
> Deployment activity(Migration plan ID:0021...
Najmi Pasarudin
10:13 Support #7123 (Work Completed-End life cycle): [TPMS_GL073] - Post Event >> Report >> JPPPA
Email from Arshad(Matrade IT department personnel):
> Dear Najmi,
>
> Deployment activity(Migration plan ID:0021...
Najmi Pasarudin
10:04 Support #6968 (Development / Work In Progress): [TPMS_GL071] - Feedback Form
Salam Najmi,
Below is the feedback from user:-
+For the Test scenario 1+
*Expected result:* form is saved bu...
Siti Norahayu Mohd Desa

April 21, 2017

16:07 Support #6961 (Pending Prod Deployment): [TPMS_GL069] - Dashboard
Salam Ayu,
Tested in UAT environment, dashboard budget and programme can be access.
Thank You
Muhammad Arsh...
Siti Norahayu Mohd Desa
16:05 Support #6959 (Pending Prod Deployment): [TPMS_GL070] - Promotion>>Registration>>List Of Companies
Dear Ayu,
The format export as xls and pdf is same with format List of companies.
Regards,
Azliza Husain
...
Siti Norahayu Mohd Desa
16:03 Support #7177 (Pending Prod Deployment): [TPMS_GL078] - Post Event > Event Report
Ayu,
The result in the report and feedback is similar.
Regards,
Azliza Husain
Application Unit
Informati...
Siti Norahayu Mohd Desa

April 17, 2017

12:09 Task #7394 (Development / Work In Progress): TPMS non-CR FOC task
Najmi Pasarudin
10:13 Support #6968 (User Acceptance Test): [TPMS_GL071] - Feedback Form
Send for User Testing Siti Norahayu Mohd Desa
10:03 Support #7385 (User Acceptance Test): [TPMS_GL081] - Post Event > Feedback Form
Send for user testing Siti Norahayu Mohd Desa

April 14, 2017

15:00 Task #7394 (Closed - End of life cycle): TPMS non-CR FOC task
Najmi Pasarudin

April 13, 2017

16:22 Support #7385 (Internal Testing): [TPMS_GL081] - Post Event > Feedback Form
Issue:
Company followup input not saved when submit Follow-up form for programme type International Trade Fair. No e...
Najmi Pasarudin
16:14 Support #6968 (Internal Testing): [TPMS_GL071] - Feedback Form
Najmi Pasarudin
16:14 Support #6968: [TPMS_GL071] - Feedback Form
Issue:
Company cannot submit Follow-up form for programme type Export Acceleration Mission. Error message popup when...
Najmi Pasarudin

April 12, 2017

09:48 Support #7385 (Development / Work In Progress): [TPMS_GL081] - Post Event > Feedback Form
Najmi Pasarudin

April 11, 2017

16:58 Support #7385 (Work Completed-End life cycle): [TPMS_GL081] - Post Event > Feedback Form
Case ID : TPMS/17-0011
Referring to the attachment, please check the error because the status of feedback form for...
Siti Norahayu Mohd Desa

April 10, 2017

09:39 Support #7263 (Work Completed-End life cycle): [TPMS_GL081] - Promotion > Business Meeting > Gene...
Matrade completed deployment on 31/03/2017 5:48PM Najmi Pasarudin
09:39 Support #7191 (Work Completed-End life cycle): [TPMS_GL079] - Promotion > Business Meeting
Matrade completed deployment on 31/03/2017 5:48PM Najmi Pasarudin
 