Activity

From June 03, 2010 to July 02, 2010

July 02, 2010

18:59 Task #82 (Closed - End of life cycle): Testing SMS Notification Coding
Wong Bernard
18:58 Task #228 (Closed - End of life cycle): Update BVMC and CIB User Guide
# Updated BVMC User Guide for IB Service Info
# No CIB User Guide
Wong Bernard
18:51 Task #237 (Development / Work In Progress): Migration & Testing to Staging
Wong Bernard
18:49 Task #237 (Closed - End of life cycle): Migration & Testing to Staging
Migration & Testing to Staging in KFH for SMS Notification Wong Bernard
18:47 Task #82: Testing SMS Notification Coding
# Fixed bug where SMS is charged even when transaction has failed. Wong Bernard
17:57 Task #182 (Work Completed-End life cycle): Internal Test for report
Nandong Frank
17:07 Task #228 (Closed - End of life cycle): Update BVMC and CIB User Guide
Update the BVMC User Guide and Consumer Banking User Guide Tan Lee Yong
16:58 Task #182: Internal Test for report
Please update status Tan Lee Yong
16:57 Task #82: Testing SMS Notification Coding
Please update status Tan Lee Yong
16:57 Task #178: Code Review
Please update status Tan Lee Yong
16:55 Task #179 (Closed - End of life cycle): Code Review
Completed Tan Lee Yong
13:43 Bug #202 (Work Completed-End life cycle): Record Other1 need to remove from TAC Issuance Report ,...
Removed the "Other1" field Tan Lee Yong
12:17 Bug #201 (Closed - End of life cycle): In BRS_SMS_Notification doc didn’t listed the Grant Tota...
This is the new section added during development. I found that it is needed and I added it. Please keep this behaviou... Tan Lee Yong

July 01, 2010

18:47 Task #179 (Development / Work In Progress): Code Review
Completed both SMS and TAC report review and fixed some issue to display sender and beneficiary section when no recor... Tan Lee Yong
18:13 Bug #202 (Closed - End of life cycle): Record Other1 need to remove from TAC Issuance Report , In...
Record Other1 need to remove from TAC Issuance Report , In BRS not listed.
Actual Result:
Other1 have in TAC Issu...
Nandong Frank
16:13 Bug #201 (Closed - End of life cycle): In BRS_SMS_Notification doc didn’t listed the Grant Tota...
In BRS_SMS_Notification doc didn’t listed the Grant Total Record, Grant Total Successful Record, Grand Total Ussucc... Nandong Frank

June 30, 2010

16:48 Task #180: Test Script for report
New Update. Nandong Frank
16:14 Task #180: Test Script for report
New update for Testscript SMS Notification. Nandong Frank
12:53 Task #180: Test Script for report
Wrong update. Nandong Frank
12:38 Task #180 (Work Completed-End life cycle): Test Script for report
Include Testscript, will verify the Demand Draft and Banker's Cheque Report fields. Nandong Frank

June 29, 2010

18:31 Task #182 (Closed - End of life cycle): Internal Test for report
Perform internal test for SMS Report, TAC report and Consolidated report for monthly and daily. Tan Lee Yong
18:28 Task #180 (Closed - End of life cycle): Test Script for report
Please create test script for the report. See the report format from the BRS. Tan Lee Yong
18:27 Task #179 (Closed - End of life cycle): Code Review
Code review for IBUtils Tan Lee Yong
18:24 Task #178 (Closed - End of life cycle): Code Review
Code Review. For any issue, please open a new issue for the stakeholder to fix the problem and have QA to test it. Tan Lee Yong
13:24 Task #82: Testing SMS Notification Coding
# TAC not able to test in Developement
# SI not tested as not rolled out to Production
Wong Bernard
10:58 Task #18 (Closed - End of life cycle): Updating Demo Pages
Wong Bernard
10:57 Task #32 (Closed - End of life cycle): Study CIB for Development
Wong Bernard
10:55 Task #33 (Closed - End of life cycle): Development
Wong Bernard
10:53 Task #17 (Closed - End of life cycle): Updating BRS Document
BRS signed off, considered completed. Wong Bernard
10:51 Task #113 (Closed - End of life cycle): Coding for Inserting SMS Notification Data
Wong Bernard
10:50 Bug #105 (Closed - End of life cycle): Create Test Script
Wong Bernard
10:49 Task #117 (Closed - End of life cycle): TAC & SMS Issuance Report
Wong Bernard
10:47 Task #119 (Closed - End of life cycle): Daily & Monthly Consolidated Transaction IB Report Modifi...
Wong Bernard
10:45 Task #134 (Closed - End of life cycle): Testing & Enhancement
Wong Bernard
10:44 Bug #157 (Work Completed-End life cycle): Validation Failed when Select the Yes radio button for ...
Wong Bernard
10:42 Bug #158 (Work Completed-End life cycle): Validate Local Phone Number with alphanumeric failed in...
Wong Bernard
10:40 Bug #159 (Work Completed-End life cycle): Validate International Phone Number with alphanumeric F...
Wong Bernard
10:17 Task #134: Testing & Enhancement
# Small code changes to SMSServices.java Wong Bernard
10:13 Bug #158: Validate Local Phone Number with alphanumeric failed in 3rd Party Account Transfer.
# Fixed error in validation.xml Wong Bernard
10:08 Bug #159: Validate International Phone Number with alphanumeric Failed in 3rd Party Account Trans...
# Fixed error in validation.xml Wong Bernard

June 25, 2010

13:01 Task #134: Testing & Enhancement
# Moved logging coding to LogTables
# Minor changes to coding
Wong Bernard
12:59 Task #119: Daily & Monthly Consolidated Transaction IB Report Modification for SMS & TAC
# Completed coding for Daily & Monthly Consolidated Transaction IB Report Wong Bernard
12:58 Task #117: TAC & SMS Issuance Report
# Completed coding for TAC & SMS Reports Wong Bernard
10:40 Bug #157: Validation Failed when Select the Yes radio button for "Send SMS to beneficiary?" In 3r...
# Uncomment validation rule that will resolve this bug Wong Bernard
10:13 Bug #159 (Closed - End of life cycle): Validate International Phone Number with alphanumeric Fail...
Validate International Phone Number with alphanumeric Failed in 3rd Party Account Transfer.
Actual Result:
Go to ...
Nandong Frank
10:10 Bug #158 (Closed - End of life cycle): Validate Local Phone Number with alphanumeric failed in 3r...
Validate Local Phone Number with alphanumeric failed in 3rd Party Account Transfer.
Actual Result:
Go to "Confirm...
Nandong Frank
10:02 Bug #157 (Closed - End of life cycle): Validation Failed when Select the Yes radio button for "Se...
Validation Failed when Select the Yes radio button for "Send SMS to beneficiary?" In 3rd Party Transfer Account.
T...
Nandong Frank

June 21, 2010

16:42 Task #134: Testing & Enhancement
# Added formatAmountValue method to SMSServices
# Changed ResultServices classes to use new method
# Added method t...
Wong Bernard
14:54 Bug #105: Create Test Script
New Update For Test Script... Nandong Frank

June 18, 2010

17:23 Task #134: Testing & Enhancement
# Improved SMSServices coding for better usage with SI and maintainability
# Code clean up for better readability
...
Wong Bernard
09:16 Task #134: Testing & Enhancement
# Improved sendSMS method implementation
# Added more columns to IB_SMS_NOTIFICATION table
# Tested all modules, re...
Wong Bernard
09:12 Task #134 (Closed - End of life cycle): Testing & Enhancement
Testing of SMS Notification with all modules & changes to implementation if required Wong Bernard
09:08 Task #113: Coding for Inserting SMS Notification Data
# Done, new task for enchancing SMS Notification table insert Wong Bernard

June 17, 2010

19:06 Bug #105: Create Test Script
New Update for testscript for version 3.........Continuing enhance it Nandong Frank

June 16, 2010

11:56 Bug #105: Create Test Script
new update for testscript Nandong Frank
11:14 Task #82 (Development / Work In Progress): Testing SMS Notification Coding
Tan Lee Yong

June 15, 2010

18:20 Bug #105 (Development / Work In Progress): Create Test Script
Tan Lee Yong
18:17 Task #119 (Closed - End of life cycle): Daily & Monthly Consolidated Transaction IB Report Modifi...
Add two more rows for TAC and SMS statistic Tan Lee Yong
18:16 Task #117 (Closed - End of life cycle): TAC & SMS Issuance Report
Create TAC & SMS Issuance Report Tan Lee Yong
16:38 Task #113 (Closed - End of life cycle): Coding for Inserting SMS Notification Data
Several data for SMS Notification Reports required to be saved in DB. This task is to cater for this req.uirement Wong Bernard
16:32 Task #17: Updating BRS Document
# Updated Reports section (Section 2.7) Wong Bernard
11:51 Bug #105: Create Test Script
revamp again Nandong Frank

June 11, 2010

19:38 Task #17 (Development / Work In Progress): Updating BRS Document
Tan Lee Yong
19:37 Task #18 (Development / Work In Progress): Updating Demo Pages
Tan Lee Yong
18:44 Task #82: Testing SMS Notification Coding
# Fixed small bugs with migrating SMS Notification coding to latest version in Mercurial
# Improved SMS message temp...
Wong Bernard
14:31 Bug #105 (Closed - End of life cycle): Create Test Script
Create test script for SMS Notification Tan Lee Yong
14:09 Task #32 (Development / Work In Progress): Study CIB for Development
Tan Lee Yong
14:08 Task #33 (Development / Work In Progress): Development
Tan Lee Yong
14:07 Task #80 (Closed - End of life cycle): Updating BRS Document
Tan Lee Yong

June 09, 2010

10:01 Task #82: Testing SMS Notification Coding
# Need to test GL payment and SMS sending (log to SMS Table) Wong Bernard

June 07, 2010

12:15 Task #82 (Closed - End of life cycle): Testing SMS Notification Coding
Testing and debugging of coding for SMS Notification. Performed at KFH site only. Wong Bernard
12:13 Task #17: Updating BRS Document
# Updated screenshots
# Updated content
# Changed SMS templates
Wong Bernard
11:59 Task #80: Updating BRS Document
# Updated screenshots
# Updated content
# Changed SMS templates
Wong Bernard
11:58 Task #80 (Closed - End of life cycle): Updating BRS Document
Update SMS Notification BRS document to include changes discussed from meeting with clients on 3rd June 2010 Wong Bernard
 

Also available in: Atom