July 15, 2010

17:45 Task #178 (Development / Work In Progress): Code Review
Normal transaction - done.
Pending for SI transaction which executed from scheduler.
Chang Grace

July 14, 2010

14:16 Task #237 (Closed - End of life cycle): Migration & Testing to Staging
All migration completed last week as there has been no new changes since. However UAT has been push back to August, s... Wong Bernard
14:01 Task #262 (Work Completed-End life cycle): UAT Monitoring for SMS Notification
Monitor internal/external UAT until UAT sign off
UAT 2/8 - 13/8
UAT Signoff 20/
Tan Lee Yong
14:00 Task #242: Migration Plan for SMS Notification & Remittance Application Form
Pre migration 23/8 - 27/8
GO LIVE 28/8
Tan Lee Yong
13:58 Task #178: Code Review
Please update this task on the plan Tan Lee Yong

July 07, 2010

16:25 Task #259 (Development / Work In Progress): SMS Notification Support for SI
# Created new methods to support SMS Notification for SI
# Updated SI JSP
# Updated SI ResultServices
# Require te...
Wong Bernard
16:23 Task #259 (Closed - End of life cycle): SMS Notification Support for SI
Create method and coding for SMS Notification to function with SI transactions Wong Bernard
16:04 Feature #258 (Closed - End of life cycle): Muliple GL Account Support
SMS Charges for SMS Notification gets charged to branch GL accounts based on the From Account Wong Bernard
12:31 Test_Script_for_SMS_Notification_v1.8.xls
Tan Lee Yong
12:31 Document: SMS Notification Test Script
Tan Lee Yong

July 06, 2010

16:13 Task #237: Migration & Testing to Staging
# Updated migration to include Billers changes from Vince Wong Bernard
09:26 Task #242 (Work Completed-End life cycle): Migration Plan for SMS Notification & Remittance Appli...
Prepare the PRODUCTION migration plan, scripts and files including table schema, BVMC related, class files, resource ... Tan Lee Yong

July 02, 2010

18:59 Task #82 (Closed - End of life cycle): Testing SMS Notification Coding
Wong Bernard
18:58 Task #228 (Closed - End of life cycle): Update BVMC and CIB User Guide
# Updated BVMC User Guide for IB Service Info
# No CIB User Guide
Wong Bernard
18:51 Task #237 (Development / Work In Progress): Migration & Testing to Staging
Wong Bernard
18:49 Task #237 (Closed - End of life cycle): Migration & Testing to Staging
Migration & Testing to Staging in KFH for SMS Notification Wong Bernard
18:47 Task #82: Testing SMS Notification Coding
# Fixed bug where SMS is charged even when transaction has failed. Wong Bernard
17:57 Task #182 (Work Completed-End life cycle): Internal Test for report
Nandong Frank
17:07 Task #228 (Closed - End of life cycle): Update BVMC and CIB User Guide
Update the BVMC User Guide and Consumer Banking User Guide Tan Lee Yong
16:58 Task #182: Internal Test for report
Please update status Tan Lee Yong
16:57 Task #82: Testing SMS Notification Coding
Please update status Tan Lee Yong
16:57 Task #178: Code Review
Please update status Tan Lee Yong
16:55 Task #179 (Closed - End of life cycle): Code Review
Completed Tan Lee Yong
13:43 Bug #202 (Work Completed-End life cycle): Record Other1 need to remove from TAC Issuance Report ,...
Removed the "Other1" field Tan Lee Yong
12:17 Bug #201 (Closed - End of life cycle): In BRS_SMS_Notification doc didn’t listed the Grant Tota...
This is the new section added during development. I found that it is needed and I added it. Please keep this behaviou... Tan Lee Yong

July 01, 2010

18:47 Task #179 (Development / Work In Progress): Code Review
Completed both SMS and TAC report review and fixed some issue to display sender and beneficiary section when no recor... Tan Lee Yong
18:13 Bug #202 (Closed - End of life cycle): Record Other1 need to remove from TAC Issuance Report , In...
Record Other1 need to remove from TAC Issuance Report , In BRS not listed.
Actual Result:
Other1 have in TAC Issu...
Nandong Frank
16:13 Bug #201 (Closed - End of life cycle): In BRS_SMS_Notification doc didn’t listed the Grant Tota...
In BRS_SMS_Notification doc didn’t listed the Grant Total Record, Grant Total Successful Record, Grand Total Ussucc... Nandong Frank

June 30, 2010

16:48 Task #180: Test Script for report
New Update. Nandong Frank
16:14 Task #180: Test Script for report
New update for Testscript SMS Notification. Nandong Frank
12:53 Task #180: Test Script for report
Wrong update. Nandong Frank
12:38 Task #180 (Work Completed-End life cycle): Test Script for report
Include Testscript, will verify the Demand Draft and Banker's Cheque Report fields. Nandong Frank

June 29, 2010

18:31 Task #182 (Closed - End of life cycle): Internal Test for report
Perform internal test for SMS Report, TAC report and Consolidated report for monthly and daily. Tan Lee Yong
18:28 Task #180 (Closed - End of life cycle): Test Script for report
Please create test script for the report. See the report format from the BRS. Tan Lee Yong
18:27 Task #179 (Closed - End of life cycle): Code Review
Code review for IBUtils Tan Lee Yong
18:24 Task #178 (Closed - End of life cycle): Code Review
Code Review. For any issue, please open a new issue for the stakeholder to fix the problem and have QA to test it. Tan Lee Yong
13:24 Task #82: Testing SMS Notification Coding
# TAC not able to test in Developement
# SI not tested as not rolled out to Production
Wong Bernard
10:58 Task #18 (Closed - End of life cycle): Updating Demo Pages
Wong Bernard
10:57 Task #32 (Closed - End of life cycle): Study CIB for Development
Wong Bernard
10:55 Task #33 (Closed - End of life cycle): Development
Wong Bernard
10:53 Task #17 (Closed - End of life cycle): Updating BRS Document
BRS signed off, considered completed. Wong Bernard
10:51 Task #113 (Closed - End of life cycle): Coding for Inserting SMS Notification Data
Wong Bernard
10:50 Bug #105 (Closed - End of life cycle): Create Test Script
Wong Bernard
10:49 Task #117 (Closed - End of life cycle): TAC & SMS Issuance Report
Wong Bernard
10:47 Task #119 (Closed - End of life cycle): Daily & Monthly Consolidated Transaction IB Report Modifi...
Wong Bernard
10:45 Task #134 (Closed - End of life cycle): Testing & Enhancement
Wong Bernard
10:44 Bug #157 (Work Completed-End life cycle): Validation Failed when Select the Yes radio button for ...
Wong Bernard
10:42 Bug #158 (Work Completed-End life cycle): Validate Local Phone Number with alphanumeric failed in...
Wong Bernard
10:40 Bug #159 (Work Completed-End life cycle): Validate International Phone Number with alphanumeric F...
Wong Bernard
10:17 Task #134: Testing & Enhancement
# Small code changes to SMSServices.java Wong Bernard
10:13 Bug #158: Validate Local Phone Number with alphanumeric failed in 3rd Party Account Transfer.
# Fixed error in validation.xml Wong Bernard
10:08 Bug #159: Validate International Phone Number with alphanumeric Failed in 3rd Party Account Trans...
# Fixed error in validation.xml Wong Bernard

June 25, 2010

13:01 Task #134: Testing & Enhancement
# Moved logging coding to LogTables
# Minor changes to coding
Wong Bernard
12:59 Task #119: Daily & Monthly Consolidated Transaction IB Report Modification for SMS & TAC
# Completed coding for Daily & Monthly Consolidated Transaction IB Report Wong Bernard
12:58 Task #117: TAC & SMS Issuance Report
# Completed coding for TAC & SMS Reports Wong Bernard
10:40 Bug #157: Validation Failed when Select the Yes radio button for "Send SMS to beneficiary?" In 3r...
# Uncomment validation rule that will resolve this bug Wong Bernard
10:13 Bug #159 (Closed - End of life cycle): Validate International Phone Number with alphanumeric Fail...
Validate International Phone Number with alphanumeric Failed in 3rd Party Account Transfer.
Actual Result:
Go to ...
Nandong Frank
10:10 Bug #158 (Closed - End of life cycle): Validate Local Phone Number with alphanumeric failed in 3r...
Validate Local Phone Number with alphanumeric failed in 3rd Party Account Transfer.
Actual Result:
Go to "Confirm...
Nandong Frank
10:02 Bug #157 (Closed - End of life cycle): Validation Failed when Select the Yes radio button for "Se...
Validation Failed when Select the Yes radio button for "Send SMS to beneficiary?" In 3rd Party Transfer Account.
T...
Nandong Frank
 

Also available in: Atom