Activity
From September 02, 2014 to October 01, 2014
October 01, 2014
- 21:22 Task #4742 (Development / Work In Progress): MCI: Fixed Deposit Upliftment
- Work in local with mockup. havent test on server
- 21:21 Task #4743 (Development / Work In Progress): MCI: Fixed Deposit Management
- Working in local. havent test on server
- 18:45 Task #4613 (Development / Work In Progress): MCI: Bill Payment - Recurring Payment Maintenance
- Pending host to test.
- 18:44 Task #4612 (Development / Work In Progress): MCI: Bill Payment - Recurring Payment
- Complete page flow.
Link added in bill payment. - 12:38 Task #4617: MCI: Fund Transfer - Cardless Withdrawal
- Currently working with response from host on Open Cardless Withdrawal Placement.
September 30, 2014
- 11:51 Task #4727: Host Message
- Finished recurring payment and cardless withdrawal host message
September 26, 2014
- 15:49 Task #4749 (Work Completed-End life cycle): MCI: FTT Manage Favorite
- 15:46 Task #4748 (Work Completed-End life cycle): MCI: Foreign Telegraphic Transfer
- Open & Favorite FTT Transfer
Upon submission, required to send email to COP - 15:36 Task #4747 (Work Completed-End life cycle): MCI: Fund Transfer
- 14:02 Task #4615 (Development / Work In Progress): MCI: Fund Transfer - Interbank Maintenance Update, A...
- Finish development, but testing on the host message.
Thank you. - 14:01 Task #4614 (Development / Work In Progress): MCI: Fund Transfer - Interbank Open and Favourite Tr...
- Finish development for interbank open and favourite fund transfer, but favourite fund transfer still testing on the h...
- 12:32 Task #4744 (Development / Work In Progress): Reskin: Utilities & Account Maintenance
- Require tablet and phone view testing.
- 12:31 Task #4725 (Development / Work In Progress): Reskin: Account Maintenance
- Require tablet and phone view testing.
- 12:31 Task #4724 (Development / Work In Progress): Reskin: Transfer
- Require tablet and phone view testing.
- 12:31 Task #4723 (Development / Work In Progress): Reskin: Payment
- Require tablet and phone view testing.
- 12:30 Task #4723: Reskin: Payment
- Require tablet and phone view testing.
- 12:29 Task #4722: Reskin: Accounts & Banking
- Require tablet and phone view testing.
- 12:11 Task #4617 (Development / Work In Progress): MCI: Fund Transfer - Cardless Withdrawal
- Task done:
1.Create Open and Favourite pages (require improvement)
2.Create actions and services (require improveme... - 12:03 Task #4623 (Development / Work In Progress): MSS: Content Type - Forex
- Tasks done:
1.Add Forex table into database
2.Create pages (require improvement)
3.Create action and services (req... - 11:57 Task #4746 (Work Completed-End life cycle): MCI: Recurring Payment
- 11:55 Task #4745 (Work Completed-End life cycle): MCI: Cardless Withdrawal
- 11:44 Task #4744 (Work Completed-End life cycle): Reskin: Utilities & Account Maintenance
- Reskin existing module with responsive design
- 11:40 Task #4743 (Work Completed-End life cycle): MCI: Fixed Deposit Management
- 11:37 Task #4742 (Work Completed-End life cycle): MCI: Fixed Deposit Upliftment
- 11:32 Task #4741 (Work Completed-End life cycle): MCI: Fixed Deposit
- To complete submodule below:
Fixed Deposit Placement
Fixed Deposit Management / Upliftment
September 23, 2014
- 17:57 Task #4727: Host Message
- finished check and create the host message until check inquiry.
- 10:02 Task #4727 (Development / Work In Progress): Host Message
- done until FD upliftment.
September 20, 2014
- 18:10 Task #4727 (Work Completed-End life cycle): Host Message
- 18:07 Task #4726 (Work Completed-End life cycle): Reskin: Loan Application
- 18:07 Task #4725 (Work Completed-End life cycle): Reskin: Account Maintenance
- Update new template
- 18:05 Task #4724 (Work Completed-End life cycle): Reskin: Transfer
- Update new template
- 18:02 Task #4723 (Work Completed-End life cycle): Reskin: Payment
- Update new template
- 18:00 Task #4722 (Work Completed-End life cycle): Reskin: Accounts & Banking
- Update new template
- 17:47 Task #4721 (Work Completed-End life cycle): Existing Module - Reskin
- Update existing module - change to new responsive template
Also available in: Atom