July 18, 2013
- 16:52 Revision 11:05e3b9ae1a68 (m2u-upass-ws): Add more test cases
- 16:52 Revision 10:ecafeb8a1e00 (m2u-upass-ws): Add some comments on TODO items
July 17, 2013
- 10:46 UPASS CORE Task #3208 (Development / Work In Progress): M2U UPASS CORE: Create Unit Test Using SoupUI
- Have added several test cases to cover most of the WS functions except token & security code related functions.
Ne... - 10:20 Revision 9:2146df0cdcf0 (m2u-upass-ws): Add several test case to cover most of the functions exce...
- 09:50 Task #3240 (Dropped-End of life cycle): Make sure existing code can run on Java 1.5
- Dropped in response to previous comment.
July 15, 2013
- 15:51 UPASS Admin Task #3206 (Development / Work In Progress): M2U UPASS Admin: Revamp Agrobank IBAM L&F to Maybank...
- Chee Onn, I've finally pushed my changesets for the initial code. You may now proceed with this task.
- 15:34 Revision 1:5b08c0dcf148 (m2u-upass-admin): Removed a dependency on proxool.
- 10:38 UPASS Admin Task #3207 (Development / Work In Progress): M2U UPASS Admin: DB Conversion - MSSQL to Oracle
- Managed to migrate Agro DB to Oracle. Still need some work to remove the unnecessary tables.
- 10:25 Revision 8:abffa427217b (m2u-upass-ws): Temporarily set the project output to Java 1.6 .
July 12, 2013
- 16:55 Revision 0:ea666cc7880e (m2u-upass-admin): Forked from agro-admin r:642, stripped away as much cl...
- 12:03 UPASS Admin Task #3206: M2U UPASS Admin: Revamp Agrobank IBAM L&F to Maybank MSS L&F
- Let me create the initial code base, and make it runnable, then assign this task back to you.
July 11, 2013
- 10:48 Task #3240: Make sure existing code can run on Java 1.5
- So sorry to update you that based on yesterday discussion with Mr. Lee, his decision will not upgrade BV to use JDK1....
- 10:34 Task #3240 (Dropped-End of life cycle): Make sure existing code can run on Java 1.5
July 10, 2013
- 13:42 Revision 4:ab707df86eff (m2u-upass-core): Updated dependencies.
- 12:53 Revision 7:2f54c7e7d21f (m2u-upass-ws): Minor change.
- 12:32 Revision 6:30274aa4b906 (m2u-upass-ws): Minor change.
- 11:31 Revision 5:beb9556af15a (m2u-upass-ws): Backported to Java 1.5
- 09:42 Revision 3:ad4da989a1d3 (m2u-upass-core): Updated dependencies.
- 09:07 Revision 2:dcd717e1bcae (m2u-upass-core): Backported the source code to Java 1.5
July 09, 2013
- 00:24 Revision 4:6929b881e172 (m2u-upass-ws): Updated the dependencies.
- 00:00 Revision 3:84fa6720f031 (m2u-upass-ws): Updated the dependencies.
- 22:06 Revision 2:8013c4c9233f (m2u-upass-ws): Changed the URLs in SoapUI.
- 18:01 M2U UPASS Initial Stage Task #3217: M2U: Syste Design and Requirement Document
- I put the FSD doc "M2U UPASS FSD 20130709.docx" and "FSD Diagrams.vsd" inside Alfresco "M2U UPASS Project->Document L...
- 17:45 Revision 1:de3237f0578f (m2u-upass-ws): Renamed the artifact.
- 17:31 Revision 1:422937082a3a (m2u-upass-core): Renamed the artifact.
- 16:45 Revision 0:53910be9bd5d (m2u-upass-ws): Forked from agro-upass-ws r:47
- 16:42 M2U UPASS Initial Stage Task #3217 (Dropped-End of life cycle): M2U: Syste Design and Requirement Document
- To create the M2U UPASS Architecture Design Document. Please work closely with and Hadi on this doc. Also can segrega...
- 16:41 Revision 0:02300db8682b (m2u-upass-core): Forked from agro-upass r:108
- 15:10 UPASS CORE Task #3208 (Work Completed-End life cycle): M2U UPASS CORE: Create Unit Test Using SoupUI
- To create more unit test for reach higher percentage of code test coverage
- 15:03 UPASS Admin Task #3207 (Work Completed-End life cycle): M2U UPASS Admin: DB Conversion - MSSQL to Oracle
- Convert Agrobank IBAM database to Oracle. Due to Hadi had made some modification on the UPASS tables, please discussi...
- 15:00 UPASS Admin Task #3206 (Work Completed-End life cycle): M2U UPASS Admin: Revamp Agrobank IBAM L&F to Maybank ...
- Take Agrobank IBAM as base and then revamp the look & feel to Maybank MSS look & feel using Maybank MSS's CSS.
Funct...
July 03, 2013
- 14:03 M2U UPASS Initial Stage Task #3121 (Development / Work In Progress): M2U: Project Plan
- I have done the first draft of the project plan and submitted to customer on July 2nd 2013
- 13:56 M2U UPASS Initial Stage Task #3124 (Work Completed-End life cycle): M2U: UPASS Admin Console BRS
- To compile the UPASS administration console requirement document
- 13:55 M2U UPASS Initial Stage Task #3123 (Dropped-End of life cycle): M2U: Development Environment Doc
- Creating the development environment document.
- 12:22 M2U UPASS Initial Stage Task #3121 (Work Completed-End life cycle): M2U: Project Plan
- Project plan creation and finalization with customer