Activity

From May 14, 2020 to June 12, 2020

June 12, 2020

18:14 Phase 2 Enhancement Bug #10869 (Development / Work In Progress): [MERCHANT MAINTENANCE] : Maker unable to delete group
Tested and Successfully delete group. However, request to remove error message,seems like system display error messag... Nurul Akmal
Avatar?id=1966&size=24 17:42 Phase 2 Enhancement Bug #10864 (Internal Testing): [MERCHANT] Authorization > Pending & Approval : Delete Merchant Gr...
Hi Ayu,
Issue had been fixed, please try again.
Thank you
Ngoh Chee Onn
Avatar?id=1966&size=24 17:42 Phase 2 Enhancement Bug #10864 (Development / Work In Progress): [MERCHANT] Authorization > Pending & Approval : Dele...
Ngoh Chee Onn
Avatar?id=1966&size=24 17:14 Phase 2 Enhancement Bug #10874 (Internal Testing): [MERCHANT MAINTENANCE] : To standardize error message
Hi Akmal,
Fixed done, please test after deployment done by today.
Thank you
Ngoh Chee Onn
Avatar?id=1966&size=24 17:13 Phase 2 Enhancement Bug #10874 (Development / Work In Progress): [MERCHANT MAINTENANCE] : To standardize error message
Ngoh Chee Onn
Avatar?id=1966&size=24 17:08 Phase 2 Enhancement Bug #10873 (Internal Testing): Merchant User Maintenance - User List : Column display wrong value
Hi Ayu,
Fixed had been done, please test after deployment done by today.
Thank you
Ngoh Chee Onn
17:06 Phase 2 Enhancement Bug #10828 (Work Completed-End life cycle): [ADMIN>Content Management] Create Category: Unable to...
Tested and passed. Thank you. Nurul Akmal
Avatar?id=1966&size=24 17:01 Phase 2 Enhancement Bug #10873 (Development / Work In Progress): Merchant User Maintenance - User List : Column displ...
Ngoh Chee Onn
15:56 Phase 2 Enhancement Bug #10828 (Internal Testing): [ADMIN>Content Management] Create Category: Unable to edit sub-cat...
i tested already have no error Bramantyo Pujo Wiyono
15:50 Phase 2 Enhancement Bug #10855 (Internal Testing): [MERCHANT] : Unable to view Merchant Maintenance sub navigation
Merchant Maker not supposed to have access to Pending Application, only for Participant & PayNet Admin.
Please upda...
Chuah Kar Yan
12:49 Phase 2 Enhancement Bug #10874 (Work Completed-End life cycle): [MERCHANT MAINTENANCE] : To standardize error message
*Merchant User Maintenance > Create User*
Key in other than numeric to Official Contact No field.
*Error displa...
Nurul Akmal
11:50 Phase 2 Enhancement Bug #10873 (Work Completed-End life cycle): Merchant User Maintenance - User List : Column displa...
Merchant User Maintenance List display wrong value for Merchant User ID & Merchant Username. Please refer attached.
...
Siti Norahayu Mohd Desa
Avatar?id=1966&size=24 11:21 Phase 2 Enhancement Bug #10869 (Internal Testing): [MERCHANT MAINTENANCE] : Maker unable to delete group
Hi Akmal,
There was old data with the same sequence id with the check maker activity you created by click on the c...
Ngoh Chee Onn
10:26 Phase 2 Enhancement Bug #10869: [MERCHANT MAINTENANCE] : Maker unable to delete group
Hi Chee Onn,
Merchant group name: _festivallazada_
This morning, i created another 5 new groups. only 2 groups (_...
Nurul Akmal
Avatar?id=1966&size=24 10:07 Phase 2 Enhancement Bug #10867 (Internal Testing): [MERCHANT] : Authorization > Approval : Edit Merchant Group
Hi Ayu,
Activity log wrongly log into bank audit log table, please try again after deployment done by today.
Th...
Ngoh Chee Onn
Avatar?id=1966&size=24 10:06 Phase 2 Enhancement Bug #10865 (Internal Testing): [MERCHANT] Authorization > Authorizer Log : Activity Name & Reason...
Hi Ayu,
Please refer *below*.
Activity Name & Reason value not display ----> Activity Name still not display at...
Ngoh Chee Onn

June 11, 2020

00:22 Phase 2 Enhancement Bug #10855 (Development / Work In Progress): [MERCHANT] : Unable to view Merchant Maintenance sub...
Hi Chee Ping,
Error still persist
Siti Norahayu Mohd Desa
00:15 Phase 2 Enhancement Bug #10862 (Work Completed-End life cycle): Merchant User Maintenance - Create New Merchant : Bro...
Tested & Passed Tq Siti Norahayu Mohd Desa
00:09 Phase 2 Enhancement Bug #10865 (Development / Work In Progress): [MERCHANT] Authorization > Authorizer Log : Activity...
Hi Chee Onn,
Please refer below test result.
> # Activity Name & Reason value not display ----> *Activity Name ...
Siti Norahayu Mohd Desa
23:54 Phase 2 Enhancement Bug #10866 (Development / Work In Progress): [MERCHANT] Merchant Audit Trail
Hi Amy, Please assist to update on below request as well. TQ
*Audit Trail List*
# Activity not display any value ...
Siti Norahayu Mohd Desa
23:48 Phase 2 Enhancement Bug #10867 (Development / Work In Progress): [MERCHANT] : Authorization > Approval : Edit Merchan...
Tested & passed.
But after approved the request, the activity not listed in Authorizer Log
Siti Norahayu Mohd Desa
23:40 Phase 2 Enhancement Bug #10868 (Work Completed-End life cycle): [MERCHANT MAINTENANCE] : Maker unable to create merch...
Tested & Passed. TQ Siti Norahayu Mohd Desa
22:16 5. Training Compilation Issue Task #10679 (Finished Development): Video Demo CDB - Review
Muhammad Haziq Mohd Ibrahim
Avatar?id=1966&size=24 19:38 Phase 2 Enhancement Bug #10865 (Internal Testing): [MERCHANT] Authorization > Authorizer Log : Activity Name & Reason...
Hi Ayu,
Fixed had been done, please test after deployment done by tonight.
Thank you
Ngoh Chee Onn
Avatar?id=1966&size=24 19:37 Phase 2 Enhancement Bug #10865 (Development / Work In Progress): [MERCHANT] Authorization > Authorizer Log : Activity...
Ngoh Chee Onn
18:09 Phase 2 Enhancement Bug #10855 (Internal Testing): [MERCHANT] : Unable to view Merchant Maintenance sub navigation
Issue No 1 is fixed. please retest after deployed Ngoh Chee Ping
Avatar?id=1966&size=24 14:49 Phase 2 Enhancement Bug #10869 (Development / Work In Progress): [MERCHANT MAINTENANCE] : Maker unable to delete group
Hi Akmal,
I able to user the LazMaker@lazada.com to delete merchant group created by administrator. Please let me ...
Ngoh Chee Onn
Avatar?id=1966&size=24 14:35 Phase 2 Enhancement Bug #10867 (Internal Testing): [MERCHANT] : Authorization > Approval : Edit Merchant Group
Hi Ayu,
There was error to insert audit log after successful approved the pending item. Please try again after dep...
Ngoh Chee Onn
Avatar?id=1966&size=24 14:34 Phase 2 Enhancement Bug #10867 (Development / Work In Progress): [MERCHANT] : Authorization > Approval : Edit Merchan...
Ngoh Chee Onn
Avatar?id=1966&size=24 14:07 Phase 2 Enhancement Bug #10868 (Internal Testing): [MERCHANT MAINTENANCE] : Maker unable to create merchant group
Hi Akmal,
There was incorrect validation for merchant user, please try again after deployment tonight.
Thank you
Ngoh Chee Onn
Avatar?id=1966&size=24 14:05 Phase 2 Enhancement Bug #10868 (Development / Work In Progress): [MERCHANT MAINTENANCE] : Maker unable to create merc...
Ngoh Chee Onn
13:32 Phase 2 Enhancement Bug #10869 (Work Completed-End life cycle): [MERCHANT MAINTENANCE] : Maker unable to delete group
*Steps:*
# Login as: LazMaker@lazada.com/A@aa11.
# Go to Merchant Group Maintenance
# Click on Search button to ...
Nurul Akmal
13:25 Phase 2 Enhancement Bug #10868 (Work Completed-End life cycle): [MERCHANT MAINTENANCE] : Maker unable to create merch...
*Steps:*
# Login as: LazMaker@lazada.com/A@aa11.
# Enter all required fields at 'Merchant Group Maintenance - Cre...
Nurul Akmal

June 10, 2020

21:51 Phase 2 Enhancement Bug #10841 (Pending Review): [MERCHANT MAINT] Merchant User Maintenance > Create : Browser Compat...
Existing bugs - affects Safari only.
When the right panel on the page is longer than the left panel, will not have t...
Chuah Kar Yan
19:19 Phase 2 Enhancement Bug #10867 (Work Completed-End life cycle): [MERCHANT] : Authorization > Approval : Edit Merchant...
# Login as Checker (LazChecker / Aaaa!111)
# Approve the Edit Merchant Group action with reason
*Actual Result*
...
Siti Norahayu Mohd Desa
18:19 Phase 2 Enhancement Bug #10851 (Pending Review): [MERCHANT MAINT] Merchant Group Maintenance - Create : Browser Compa...
Existing bugs - affected Safari only.
When the right panel on the page is longer than the left panel, will not have ...
Chuah Kar Yan
18:15 Phase 2 Enhancement Bug #10862 (Internal Testing): Merchant User Maintenance - Create New Merchant : Browser Compatib...
Able to create the user.
See attached doc.
Chuah Kar Yan
17:57 Phase 2 Enhancement Bug #10866 (Internal Testing): [MERCHANT] Merchant Audit Trail
wrong function assignment, already updated the code.
Please retest
Chuah Kar Yan
17:19 Phase 2 Enhancement Bug #10866 (Closed - End of life cycle): [MERCHANT] Merchant Audit Trail
1. Reason not display
2. Unable to view audit trail details.
# Login as Merchant Admin Maker
# Click on Merchan...
Siti Norahayu Mohd Desa
16:56 Phase 2 Enhancement Bug #10865 (Work Completed-End life cycle): [MERCHANT] Authorization > Authorizer Log : Activity ...
# Activity Name & Reason value not display
# Delete Merchant Group value not display
# Click on eye button to displ...
Siti Norahayu Mohd Desa
16:03 Phase 2 Enhancement Bug #10863 (Work Completed-End life cycle): [MERCHANT] : Merchant User Maintenance > Create : Una...
Tested & Passed. Siti Norahayu Mohd Desa
Avatar?id=1966&size=24 15:58 Phase 2 Enhancement Bug #10863 (Internal Testing): [MERCHANT] : Merchant User Maintenance > Create : Unable to create...
Hi Ayu,
Please try again, check user access function had been remove by ken this morning.
Thank you
Ngoh Chee Onn
Avatar?id=1966&size=24 15:57 Phase 2 Enhancement Bug #10863 (Development / Work In Progress): [MERCHANT] : Merchant User Maintenance > Create : Un...
Ngoh Chee Onn
11:37 Phase 2 Enhancement Bug #10864 (Work Completed-End life cycle): [MERCHANT] Authorization > Pending & Approval : Delet...
# Login as LazMaker@lazada.com
# Delete Merchant Group
# Click on Authorization Navigation > Pending & Approval
...
Siti Norahayu Mohd Desa
10:54 Phase 2 Enhancement Bug #10863: [MERCHANT] : Merchant User Maintenance > Create : Unable to create user
*Unable to create new user*
# Login as Merchant (LazMaker@lazada.com)
# Click on Create button
*Actual Result*...
Siti Norahayu Mohd Desa
10:51 0. CDB_Change Request Enhancement #10112 (System Integration Test): [CR19001] : To add "Collection Receivable" function...
(BSNeBiz process)
1. Register New Company at CDB and only Collection (Success all screen)
2. Dowload PDF (Success, ...
Nurul Athira Abdul Rahim
10:47 Phase 2 Enhancement Bug #10863 (Work Completed-End life cycle): [MERCHANT] : Merchant User Maintenance > Create : Una...
Siti Norahayu Mohd Desa
10:00 Phase 2 Enhancement Bug #10858 (Work Completed-End life cycle): [MERCHANT] : Authorization > Pending.
Tested & Passed. TQ Siti Norahayu Mohd Desa
09:58 Phase 2 Enhancement Bug #10854 (Work Completed-End life cycle): [MERCHANT MAINT] Merchant Group Maintenance - Edit : ...
Reported issue tested & passed. Siti Norahayu Mohd Desa

June 09, 2020

23:09 Phase 2 Enhancement Bug #10862 (Work Completed-End life cycle): Merchant User Maintenance - Create New Merchant : Bro...
*SAFARI*
Below is the step to reproduce:
1. Click on Create button and click on Next button.
2. System displa...
Siti Norahayu Mohd Desa
22:59 Phase 2 Enhancement Bug #10842 (Work Completed-End life cycle): [MERCHANT MAINT] Merchant User Maintenance : Create N...
Issue reported above tested & passed.
Siti Norahayu Mohd Desa
22:22 Phase 2 Enhancement Bug #10858: [MERCHANT] : Authorization > Pending.
Unable to test. This issue is related with Bug #10854
Siti Norahayu Mohd Desa
14:52 Phase 2 Enhancement Bug #10845 (Work Completed-End life cycle): [MERCHANT] : New Merchant User Login
Tested & Passed. Siti Norahayu Mohd Desa
14:49 Phase 2 Enhancement Bug #10836 (Work Completed-End life cycle): [MERCHANT MAINT] Merchant Enquiry - Terminate status
Tested & Passed. Siti Norahayu Mohd Desa
Avatar?id=1966&size=24 14:44 Phase 2 Enhancement Bug #10854 (Internal Testing): [MERCHANT MAINT] Merchant Group Maintenance - Edit : Unable to edi...
Hi Ayu,
For existing group it already insert a invalid navigation access id to database. I had remove those invali...
Ngoh Chee Onn
14:11 Phase 2 Enhancement Bug #10850 (Work Completed-End life cycle): [MERCHANT MAINT] Merchant User Maintenance - View Mer...
Tested & Passed. Siti Norahayu Mohd Desa
14:05 Phase 2 Enhancement Bug #10854 (Development / Work In Progress): [MERCHANT MAINT] Merchant Group Maintenance - Edit :...
Hi Chee Onn,
Error still persist. Page die after click on Confirm button
Siti Norahayu Mohd Desa
13:55 Phase 2 Enhancement Bug #10855 (Development / Work In Progress): [MERCHANT] : Unable to view Merchant Maintenance sub...
Hi Chee Onn,
Noted.
Issue have been tested & passed.
Hi Chee Ping / Ken
Please fix on issue no. 1. TQ
Siti Norahayu Mohd Desa
13:50 Phase 2 Enhancement Bug #10828 (Development / Work In Progress): [ADMIN>Content Management] Create Category: Unable t...
Issue reported fixed. System already view edit screen when click on Pencil icon. However, error when click on Update ... Nurul Akmal
13:45 Phase 2 Enhancement Bug #10849 (Development / Work In Progress): [ADMIN>Content Management] Create Content: Error pag...
Hi Bram,
Error still persist. Kindly assist to check. Thank you
Nurul Akmal
13:43 Phase 2 Enhancement Bug #10826 (Work Completed-End life cycle): [ADMIN>Content Management] Create Content: Unsuccessf...
Successfully save content. Nurul Akmal
13:42 Phase 2 Enhancement Bug #10848 (Work Completed-End life cycle): [ADMIN>Content Management] Create Content: Error whil...
Successfully create content. Nurul Akmal

June 08, 2020

22:51 Phase 2 Enhancement Bug #10826 (Internal Testing): [ADMIN>Content Management] Create Content: Unsuccessful save content
Bramantyo Pujo Wiyono
22:51 Phase 2 Enhancement Bug #10849 (Internal Testing): [ADMIN>Content Management] Create Content: Error page during custo...
Bramantyo Pujo Wiyono
22:50 Phase 2 Enhancement Bug #10848 (Internal Testing): [ADMIN>Content Management] Create Content: Error while Admin Maker...
Bramantyo Pujo Wiyono
22:50 Phase 2 Enhancement Bug #10828 (Internal Testing): [ADMIN>Content Management] Create Category: Unable to edit sub-cat...
Bramantyo Pujo Wiyono
Avatar?id=1966&size=24 22:28 Phase 2 Enhancement Bug #10858 (Internal Testing): [MERCHANT] : Authorization > Pending.
Hi Ayu,
There was invalid group access display when create merchant group. Please test again with create new merch...
Ngoh Chee Onn
Avatar?id=1966&size=24 22:26 Phase 2 Enhancement Bug #10858 (Development / Work In Progress): [MERCHANT] : Authorization > Pending.
Ngoh Chee Onn
Avatar?id=1966&size=24 21:51 Phase 2 Enhancement Bug #10852: [MERCHANT MAINT] Merchant User Maintenance - Edit : Unable to view and edit User Access
Hi Ayu,
Not able to replicate this issue, please provide user id to test it.
Thank you
Ngoh Chee Onn
Avatar?id=1966&size=24 21:51 Phase 2 Enhancement Bug #10852 (Development / Work In Progress): [MERCHANT MAINT] Merchant User Maintenance - Edit : ...
Ngoh Chee Onn
Avatar?id=1966&size=24 21:47 Phase 2 Enhancement Bug #10836 (Internal Testing): [MERCHANT MAINT] Merchant Enquiry - Terminate status
Hi Ayu,
The status select had been disable and not allow to edit, please try again after deployment done tomorrow ...
Ngoh Chee Onn
Avatar?id=1966&size=24 21:35 Phase 2 Enhancement Bug #10845 (Internal Testing): [MERCHANT] : New Merchant User Login
Hi Ayu,
Please check again on the group access for that merchant user. I found only the group access empty will sh...
Ngoh Chee Onn
Avatar?id=1966&size=24 21:34 Phase 2 Enhancement Bug #10845 (Development / Work In Progress): [MERCHANT] : New Merchant User Login
Ngoh Chee Onn
Avatar?id=1966&size=24 21:34 Phase 2 Enhancement Bug #10842 (Internal Testing): [MERCHANT MAINT] Merchant User Maintenance : Create New Merchant
Hi Ayu,
Please refer below for my reply.
1. Change Merchant User Id error message to Merchant User ID
- Change...
Ngoh Chee Onn
Avatar?id=1966&size=24 21:31 Phase 2 Enhancement Bug #10842 (Development / Work In Progress): [MERCHANT MAINT] Merchant User Maintenance : Create ...
Ngoh Chee Onn

June 06, 2020

11:36 Phase 2 Enhancement Bug #10858 (Work Completed-End life cycle): [MERCHANT] : Authorization > Pending.
Merchant able to see Admin Pending item.
Cross check with Group user access. There is NO Admin Pending list there t...
Siti Norahayu Mohd Desa

June 05, 2020

Avatar?id=1966&size=24 18:34 Phase 2 Enhancement Bug #10850 (Internal Testing): [MERCHANT MAINT] Merchant User Maintenance - View Merchant : Unabl...
Hi Ayu,
Please try again after deployment done tonight.
Thank you
Ngoh Chee Onn
Avatar?id=1966&size=24 18:33 Phase 2 Enhancement Bug #10850 (Development / Work In Progress): [MERCHANT MAINT] Merchant User Maintenance - View Me...
Ngoh Chee Onn
Avatar?id=1966&size=24 18:33 Phase 2 Enhancement Bug #10854 (Internal Testing): [MERCHANT MAINT] Merchant Group Maintenance - Edit : Unable to edi...
Hi Ayu,
Please try again after deployment tonight.
Root Cause:
- Wrong access object checking in result page...
Ngoh Chee Onn
Avatar?id=1966&size=24 18:30 Phase 2 Enhancement Bug #10854 (Development / Work In Progress): [MERCHANT MAINT] Merchant Group Maintenance - Edit :...
Ngoh Chee Onn
Avatar?id=1966&size=24 18:30 Phase 2 Enhancement Bug #10855 (Internal Testing): [MERCHANT] : Unable to view Merchant Maintenance sub navigation
Ngoh Chee Onn
Avatar?id=1966&size=24 18:29 Phase 2 Enhancement Bug #10855: [MERCHANT] : Unable to view Merchant Maintenance sub navigation
Hi Ayu,
For Item no.2 and No.3, you may test again after ken deployment done.
For Item No.1 will be fix by Ken or...
Ngoh Chee Onn
Avatar?id=1966&size=24 18:21 Phase 2 Enhancement Bug #10855 (Development / Work In Progress): [MERCHANT] : Unable to view Merchant Maintenance sub...
Ngoh Chee Onn
17:49 Phase 2 Enhancement Bug #10857: [ADMIN>System Maintenance] : System did not display all tab
Nurul Akmal wrote:
> Login as Admin Maker (makerlilyp2/P@$$w0rd). This user already given all access. Click on Syste...
Nurul Akmal
17:47 Phase 2 Enhancement Bug #10826 (Development / Work In Progress): [ADMIN>Content Management] Create Content: Unsuccess...
Tested.Content successfully save without session expired. However, unable to trace back saved item/content.
Kindly a...
Nurul Akmal
17:39 Phase 2 Enhancement Bug #10857 (Work Completed-End life cycle): [ADMIN>System Maintenance] : System did not display a...
Login as Admin Maker (lilymakerp2/P@$$w0rd). This user already given all access. Click on System Maintenance navigati... Nurul Akmal
17:08 Phase 2 Enhancement Bug #10855 (Work Completed-End life cycle): [MERCHANT] : Unable to view Merchant Maintenance sub ...
Login as Merchant Maker
LazMaker / A@aa1111
# Click on Pending Application sub navigation - System display "Er...
Siti Norahayu Mohd Desa
16:58 Phase 2 Enhancement Bug #10854 (Work Completed-End life cycle): [MERCHANT MAINT] Merchant Group Maintenance - Edit : ...
*Unable to edit Group Access*
Login as Administrator
At Edit Group Page
- Edit Group Access for Merchant Check...
Siti Norahayu Mohd Desa
13:15 Phase 2 Enhancement Bug #10836: [MERCHANT MAINT] Merchant Enquiry - Terminate status
Hi Chee Onn,
Issue report still persist.
Below is the step to reproduce the issue reported.
# Login as Admi...
Siti Norahayu Mohd Desa
12:51 1. CDB_Phase 2 & 3 Development Task #10840: [P2_New] : RFP Sect 1.6.1 - To develop Statutory Board Payment - LHDN
Please test screen at IBAM:
# Application
# Submission
# Org Setup > Account Services
# Authorization
Najmi Pasarudin
12:28 Phase 2 Enhancement Bug #10852 (Work Completed-End life cycle): [MERCHANT MAINT] Merchant User Maintenance - Edit : U...
*Unable to view and edit User Access*
+Step to re-produce+
# Edit User
# Change User Role from Admin to User
...
Siti Norahayu Mohd Desa
11:45 Phase 2 Enhancement Bug #10851 (Closed - End of life cycle): [MERCHANT MAINT] Merchant Group Maintenance - Create : B...
*SAFARI*
1. Leave empty field and click on Next button. System stuck unable to scroll up or down after validation.
Siti Norahayu Mohd Desa
11:30 Phase 2 Enhancement Bug #10850 (Work Completed-End life cycle): [MERCHANT MAINT] Merchant User Maintenance - View Mer...
*Unable to view new created user*
+Step to reproduce :+
# Login new user (LazMaker/A@aa1111)
# Click on Mercha...
Siti Norahayu Mohd Desa
11:23 Phase 2 Enhancement Bug #10844 (Work Completed-End life cycle): [MERCHANT MAINT] Merchant User Maintenance - Edit Mer...
Noted.
Tested & Passed. TQ
Siti Norahayu Mohd Desa
11:05 Phase 2 Enhancement Bug #10849 (Work Completed-End life cycle): [ADMIN>Content Management] Create Content: Error page...
At create content details page, click on merchant button to customize target audience.
Screen displayed as in screen...
Nurul Akmal
10:50 Phase 2 Enhancement Bug #10848 (Work Completed-End life cycle): [ADMIN>Content Management] Create Content: Error whil...
+Step to reproduce:+
# Login as Admin Maker
# Click on Content Management.
# Select Content>DOCUMENT
# Select Cat...
Nurul Akmal
10:43 Phase 2 Enhancement Bug #10838 (Work Completed-End life cycle): [ADMIN>System Maintenance] Config Parameters - Create
Successfully tested. Nurul Akmal
10:36 0. CDB_Change Request Enhancement #10112 (Internal Testing): [CR19001] : To add "Collection Receivable" function to ser...
Please redo testing.
Cannot replicate issue in Submission, Collection Receivable not selected and Online Payment se...
Najmi Pasarudin
Avatar?id=1966&size=24 09:38 Phase 2 Enhancement Bug #10844 (Internal Testing): [MERCHANT MAINT] Merchant User Maintenance - Edit Merchant : Unabl...
Hi Ayu,
Please refer below for the root cause and resolution, please test again after deployment by end of today.
...
Ngoh Chee Onn
Avatar?id=1966&size=24 09:36 Phase 2 Enhancement Bug #10844 (Development / Work In Progress): [MERCHANT MAINT] Merchant User Maintenance - Edit Me...
Ngoh Chee Onn

June 04, 2020

17:07 Phase 2 Enhancement Bug #10838 (Internal Testing): [ADMIN>System Maintenance] Config Parameters - Create
Bramantyo Pujo Wiyono
Avatar?id=1966&size=24 15:25 Phase 2 Enhancement Bug #10836: [MERCHANT MAINT] Merchant Enquiry - Terminate status
Hi Ayu,
Not able to replicate this issue. Currently activate and suspend button will not show if the merchant stat...
Ngoh Chee Onn
Avatar?id=1966&size=24 15:23 Phase 2 Enhancement Bug #10836 (Development / Work In Progress): [MERCHANT MAINT] Merchant Enquiry - Terminate status
Ngoh Chee Onn
15:05 Phase 2 Enhancement Bug #10823 (Work Completed-End life cycle): [ADMIN>Content Management] Create Category: Incorrect...
Successfully tested. Nurul Akmal
15:04 Phase 2 Enhancement Bug #10824 (Work Completed-End life cycle): [ADMIN>Content Management] Create Category: Able to c...
Successfully tested. Nurul Akmal
15:02 1. CDB_Phase 2 & 3 Development Task #10840 (Development / Work In Progress): [P2_New] : RFP Sect 1.6.1 - To develop Statutory Bo...
Merging LHDN to New URL Nurul Athira Abdul Rahim
15:00 Phase 2 Enhancement Bug #10827 (Work Completed-End life cycle): [ADMIN>Content Management] Edit Content: To remove ra...
Nurul Akmal
14:59 Phase 2 Enhancement Bug #10827: [ADMIN>Content Management] Edit Content: To remove random text at Confirm screen
Successfully tested. Nurul Akmal
14:59 Phase 2 Enhancement Bug #10825 (Work Completed-End life cycle): [ADMIN>Content Management] Create Content: Typo in er...
Successfully tested. Nurul Akmal
14:58 Phase 2 Enhancement Bug #10829 (Work Completed-End life cycle): [ADMIN>Content Management] Edit Content: Changes ref...
Successfully tested. Nurul Akmal
14:55 Phase 2 Enhancement Bug #10838 (Development / Work In Progress): [ADMIN>System Maintenance] Config Parameters - Create
Hi Bram,
Successfully tested for 'Create'.
But issue still persist for 'Edit'. System accept other than numeric d...
Nurul Akmal
14:52 Phase 2 Enhancement Bug #10839 (Work Completed-End life cycle): [ADMIN>System Maintenance] Archive Parameters - Edit
Successfully tested. Nurul Akmal
13:10 Phase 2 Enhancement Bug #10845 (Work Completed-End life cycle): [MERCHANT] : New Merchant User Login
+Step to Reproduce+
Create New Merchant user.
After activation, Login using created ID.
Actual Result :
Sy...
Siti Norahayu Mohd Desa
12:57 Phase 2 Enhancement Bug #10844 (Work Completed-End life cycle): [MERCHANT MAINT] Merchant User Maintenance - Edit Mer...
Login as Administrator, Click on Edit button, and edit User Access.
Actual result :
Unable to edit user access.
...
Siti Norahayu Mohd Desa
11:25 Phase 2 Enhancement Bug #10842 (Work Completed-End life cycle): [MERCHANT MAINT] Merchant User Maintenance : Create N...
1. Change Merchant User Id error message to Merchant User ID
3. Staff ID in FSD is not Mandatory but system set as m...
Siti Norahayu Mohd Desa
11:08 1. CDB_Phase 2 & 3 Development Task #10840: [P2_New] : RFP Sect 1.6.1 - To develop Statutory Board Payment - LHDN
Athira,
Make sure all related functionality capture in the document and tested.
+IBAM+**
* CDB Application & Org...
Norhaidah Md Dasuki
10:59 Phase 2 Enhancement Bug #10841 (Closed - End of life cycle): [MERCHANT MAINT] Merchant User Maintenance > Create : Br...
*SAFARI*
1. Leave empty field and click on Next button. System stuck unable to scroll up or down after validation.
Siti Norahayu Mohd Desa
10:53 1. CDB_Phase 2 & 3 Development Task #10840 (Work Completed-End life cycle): [P2_New] : RFP Sect 1.6.1 - To develop Statutory Boa...
Statutory Board Payment - LHDN
> to support payment to statutory bodies net file upload.
> to support file upload f...
Norhaidah Md Dasuki
10:20 0. CDB_Change Request Enhancement #10112 (Development / Work In Progress): [CR19001] : To add "Collection Receivable" f...
Test Process
(BSNeBiz process)
1. Register New Company at CDB and only Collection (Success all screen)
2. Dowloa...
Nurul Athira Abdul Rahim

June 03, 2020

16:47 Phase 2 Enhancement Bug #10839 (Internal Testing): [ADMIN>System Maintenance] Archive Parameters - Edit
Bramantyo Pujo Wiyono
16:44 Phase 2 Enhancement Bug #10838 (Internal Testing): [ADMIN>System Maintenance] Config Parameters - Create
Bramantyo Pujo Wiyono
16:38 Phase 2 Enhancement Bug #10829 (Internal Testing): [ADMIN>Content Management] Edit Content: Changes reflect even sta...
Bramantyo Pujo Wiyono
16:35 Phase 2 Enhancement Bug #10839 (Work Completed-End life cycle): [ADMIN>System Maintenance] Archive Parameters - Edit
Able to proceed to Confirm page when leave blank to NAD Alias (retention days) field.
*Expected:*
System display ...
Nurul Akmal
16:31 Phase 2 Enhancement Bug #10838 (Work Completed-End life cycle): [ADMIN>System Maintenance] Config Parameters - Create
System accept other than numeric (alphabet & special characters) in "Service Type Code" field.
*Expected:*
System...
Nurul Akmal
16:23 Phase 2 Enhancement Bug #10826 (Internal Testing): [ADMIN>Content Management] Create Content: Unsuccessful save content
Bramantyo Pujo Wiyono
16:07 Phase 2 Enhancement Bug #10827 (Internal Testing): [ADMIN>Content Management] Edit Content: To remove random text at ...
Bramantyo Pujo Wiyono
16:06 Phase 2 Enhancement Bug #10825 (Internal Testing): [ADMIN>Content Management] Create Content: Typo in error message
Bramantyo Pujo Wiyono
16:05 Phase 2 Enhancement Bug #10824 (Internal Testing): [ADMIN>Content Management] Create Category: Able to create categor...
Remove Parent Category field when creating new parent content (already discussed on meeting with amy and ayu) Bramantyo Pujo Wiyono
16:04 Phase 2 Enhancement Bug #10823 (Internal Testing): [ADMIN>Content Management] Create Category: Incorrect error messa...
Remove Parent Category field when creating new parent content (already discussed on meeting with amy and ayu) Bramantyo Pujo Wiyono
14:08 Phase 2 Enhancement Bug #10836 (Work Completed-End life cycle): [MERCHANT MAINT] Merchant Enquiry - Terminate status
Once merchant have been terminate, Bank / PayNet unable to re active back. Siti Norahayu Mohd Desa
12:16 0. CDB_Change Request Enhancement #10112 (Internal Testing): [CR19001] : To add "Collection Receivable" function to ser...
Fixed. Please verify.
# Remove default online payment
# Add "Collection Receivable" to email content
Najmi Pasarudin
09:53 0. CDB_Change Request Enhancement #10112 (Development / Work In Progress): [CR19001] : To add "Collection Receivable" f...
Hi Najmi, kindly fix below issue.
*Do npt default online payment*
-User select Only collection as service, system...
Nurul Athira Abdul Rahim

June 02, 2020

17:08 Phase 2 Enhancement Bug #10829 (Work Completed-End life cycle): [ADMIN>Content Management] Edit Content: Changes ref...
Edit Content by login as Super Admin, result shows status as Pending Approval. However the changes already reflected ... Nurul Akmal
16:40 Phase 2 Enhancement Bug #10828 (Work Completed-End life cycle): [ADMIN>Content Management] Create Category: Unable to...
*Step to reproduce:*
# Click on Content Management
# Select Content = INTERSTITIAL MESSAGES or NOTICES or DOCUMENTS...
Nurul Akmal
16:31 Phase 2 Enhancement Bug #10827 (Work Completed-End life cycle): [ADMIN>Content Management] Edit Content: To remove ra...
+Step to reproduce:+
# Click on Content Management
# Select Content = NOTICES
# Select Category
# Select Content ...
Nurul Akmal
16:15 Phase 2 Enhancement Bug #10826 (Work Completed-End life cycle): [ADMIN>Content Management] Create Content: Unsuccessf...
+Step to reproduce:+
# Click on Content Management
# Select Content = DOCUMENTS
# Select Category
# Click on Cr...
Nurul Akmal
16:09 Phase 2 Enhancement Bug #10825 (Work Completed-End life cycle): [ADMIN>Content Management] Create Content: Typo in er...
Kindly remove 's' in front of 'Document' word. (refer attachment) Nurul Akmal
16:07 Phase 2 Enhancement Bug #10824 (Work Completed-End life cycle): [ADMIN>Content Management] Create Category: Able to c...
+Step to reproduce:+
# Click on Content Management
# Select Content = DOCUMENTS
# Click on Create Category
# Lea...
Nurul Akmal
16:04 Phase 2 Enhancement Bug #10823 (Work Completed-End life cycle): [ADMIN>Content Management] Create Category: Incorrect...

+Step to reproduce:+
# Click on Content Management
# Select Content = DOCUMENTS
# Click on Create Category
# L...
Nurul Akmal

June 01, 2020

14:42 CR20005 - Remove Pop Up & Disable Right Click Function Bug #10766 (Work Completed-End life cycle): Able to right click button at TAC Popup Window
Tested and successfully passed Erni Suhaireen Zulkifli
14:40 CR20005 - Remove Pop Up & Disable Right Click Function Bug #10766 (Internal Testing): Able to right click button at TAC Popup Window
Siti Balqis Othman
14:38 CR20005 - Remove Pop Up & Disable Right Click Function Bug #10767 (Work Completed-End life cycle): Able to right click button at TAC Popup Window
Tested and successfully passed Erni Suhaireen Zulkifli
14:38 CR20005 - Remove Pop Up & Disable Right Click Function Bug #10765 (Work Completed-End life cycle): Unable to click on other function at Login page
Tested and successfully passed. Erni Suhaireen Zulkifli
14:37 CR20005 - Remove Pop Up & Disable Right Click Function Bug #10767 (Internal Testing): Able to right click button at TAC Popup Window
Siti Balqis Othman
14:32 CR20005 - Remove Pop Up & Disable Right Click Function Bug #10765 (Internal Testing): Unable to click on other function at Login page
Siti Balqis Othman

May 28, 2020

14:23 CR20005 - Remove Pop Up & Disable Right Click Function Bug #10766: Able to right click button at TAC Popup Window
Already deploy the patch, kindly retest Siti Balqis Othman
14:22 CR20005 - Remove Pop Up & Disable Right Click Function Bug #10767: Able to right click button at TAC Popup Window
Already deploy the patch, kindly retest. Siti Balqis Othman
14:09 CR20005 - Remove Pop Up & Disable Right Click Function Bug #10765: Unable to click on other function at Login page
Already deploy, kindly retest. Siti Balqis Othman
13:15 CR20001 - RPP Enhancement for IB System Bug #10707 (Work Completed-End life cycle): [BIB] Rename Favourite Interbank Transfer to be "Othe...
Item has been tested and successfully passed Erni Suhaireen Zulkifli

May 27, 2020

10:32 CR20010 - Zakat Fitrah Task #10741 (Work Completed-End life cycle): [DEV] AGRONetBIZ Zakat Fitrah
deploy to production 24 April 2020 Stephanie Sufrapto
10:28 CR20010 - Zakat Fitrah Task #10740 (Work Completed-End life cycle): [DEV] AGRONet Zakat Fitrah
deploy to production 24 April 2020 Stephanie Sufrapto

May 21, 2020

10:34 5. Training Compilation Issue Bug #10798 (Work Completed-End life cycle): CDB-Online application
Tested and passed Nurul Athira Abdul Rahim

May 20, 2020

16:43 5. Training Compilation Issue Bug #10797 (Work Completed-End life cycle): CDB-New Application-Services-SLA
Tested and passed. Nurul Athira Abdul Rahim
13:23 5. Training Compilation Issue Bug #10797 (Internal Testing): CDB-New Application-Services-SLA
Najmi Pasarudin
13:23 5. Training Compilation Issue Bug #10798 (Internal Testing): CDB-Online application
Najmi Pasarudin
12:32 5. Training Compilation Issue Bug #10797 (Development / Work In Progress): CDB-New Application-Services-SLA
Najmi Pasarudin
10:39 5. Training Compilation Issue Bug #10798 (Development / Work In Progress): CDB-Online application
Najmi Pasarudin

May 19, 2020

15:36 5. Training Compilation Issue Bug #10798 (Work Completed-End life cycle): CDB-Online application
Path : BSNeBiz > New Application
Step :
1. Insert numbers to "Organization Website"
Result : Successfuly cre...
Nurul Athira Abdul Rahim
15:27 5. Training Compilation Issue Bug #10797 (Work Completed-End life cycle): CDB-New Application-Services-SLA
Step:
1. Select only ONLINE PAYMENT at services
Result : Cannot proceed to next screen due to SLA for online pa...
Nurul Athira Abdul Rahim

May 17, 2020

15:11 1. CDB_Phase 2 & 3 Development Enhancement #10423 (Internal Testing): Mobile - Login Encryption
Tan Lee Yong

May 14, 2020

15:44 Internal Testing - CDB Bug #9757 (Work Completed-End life cycle): UAT_Error message at initiator IOS
Tested and passed Anonymous
15:43 1. CDB_Phase 2 & 3 Development Task #10362 (Work Completed-End life cycle): [P1_Extended] : IBAM - Email Notification for checker
Anonymous
15:27 Internal Testing - CDB Bug #9741 (Work Completed-End life cycle): UAT_Mobile_To change Bill Payment label (iOs)
The Biller Name stay Biller Name on Android and IOS. Anonymous
14:48 Internal Testing - IBAM Task #9051 (Work Completed-End life cycle): IBAM > BBE > Content - Service Type
Anonymous
14:21 Internal Testing - CDB Bug #9740 (Work Completed-End life cycle): UAT_File Enquiry/Stop Payment_Pagination error
Anonymous
14:19 Internal Testing - CDB Bug #9820 (Work Completed-End life cycle): Verifier-Field name amanded
Anonymous
13:29 5. Training Compilation Issue Bug #10655 (Work Completed-End life cycle): CDB_Bulk Payment_IBG
Anonymous
12:23 0. CDB_Change Request Enhancement #10421 (Work Completed-End life cycle): [CR19002] : To change word “Mobile” to “BSNeB...
Anonymous
12:23 0. CDB_Change Request Enhancement #10112 (User Acceptance Test): [CR19001] : To add "Collection Receivable" function to...
Anonymous
11:53 Internal Testing - CDB Task #8942 (Work Completed-End life cycle): [BSN_CDB-SIT] : CDB002 - Corporate Administrator
Anonymous
11:46 5. Training Compilation Issue Bug #10487 (Work Completed-End life cycle): Pre Prod - Account Summary
Anonymous
11:40 5. Training Compilation Issue Bug #10460 (Work Completed-End life cycle): Mobile IOS - Application Name
Anonymous
11:36 5. Training Compilation Issue Bug #10638 (Work Completed-End life cycle): UAT_IBAM_Admin User Manager_Access
Anonymous
11:35 5. Training Compilation Issue Change #10513 (Work Completed-End life cycle): Demo Mobile (IOS and Android)
Anonymous
11:33 Internal Testing - CDB Enhancement #10214 (Work Completed-End life cycle): [SIT_C030] [SIT_C031] - IBAM Insufficient bal...
Anonymous
11:33 5. Training Compilation Issue Bug #10024 (Work Completed-End life cycle): [BSN_Training-7] - iOS : System kick user out(with n...
Anonymous
11:32 Internal Testing - CDB Bug #10212 (Work Completed-End life cycle): CDB - Error authorization flow
Anonymous
11:30 5. Training Compilation Issue Bug #10019 (Work Completed-End life cycle): [BSN_Training-30] - CDB_Mobile Android- Transfer
Anonymous
11:30 5. Training Compilation Issue Feature #10036 (Work Completed-End life cycle): [BSN_Training-49] - Removed Inactive company (+ 7...
Anonymous
11:30 5. Training Compilation Issue Feature #10013 (Work Completed-End life cycle): [BSN_Training-12&13] - IBAM-File Processing
Anonymous
11:29 5. Training Compilation Issue Feature #10017 (Work Completed-End life cycle): [BSN_Training-25] - IBAM/CDB Transaction Enquiry
Anonymous
11:29 5. Training Compilation Issue Bug #10059 (Work Completed-End life cycle): [BSN_Training-75] - CDB - Authorization
Anonymous
11:26 Internal Testing - CDB Bug #9702 (Work Completed-End life cycle): [MOBILE > ANDROID] Fav 3rd Party Transfer > Result Pag...
Anonymous
11:26 Internal Testing - IBAM Bug #10142 (Work Completed-End life cycle): User Admin Manager - Username and group access
Anonymous
11:25 5. Training Compilation Issue Bug #10057 (Work Completed-End life cycle): [BSN_Training-73] - CDB (Mobile dekstop) - New Applic...
Anonymous
11:25 5. Training Compilation Issue Bug #10029 (Work Completed-End life cycle): [BSN_Training-45] - IBAM : The new charges added by u...
Anonymous
11:25 5. Training Compilation Issue Enhancement #10094 (Work Completed-End life cycle): [BSN_Training-81] - IBAM and CDB - Push Notif...
Anonymous
11:25 5. Training Compilation Issue Bug #10006 (Work Completed-End life cycle): [BSN_Training-05] - CDB (CA)-User Maintenance
Anonymous
 

Also available in: Atom