Activity

From November 25, 2017 to December 24, 2017

December 20, 2017

18:10 Task #8094 (Internal Testing): RPP > Report
Hi Athirah,
Please apply changes to the related report as per attached. TQ
Siti Norahayu Mohd Desa
17:12 Task #8094: RPP > Report
Done, except for Liquidity Status Report.
Screen Capture will be attach on email.
Anonymous

December 12, 2017

12:27 Task #8094 (Development / Work In Progress): RPP > Report
HI Athirah,
Please add on the requested report below:-
# Participant Settlement Report (same format with Financ...
Siti Norahayu Mohd Desa

December 04, 2017

18:09 Task #8094: RPP > Report
Salam Kak Ayu,
Report interface for has been done created.
- RPP Finance Settlement Report
- RPP Finance Fee...
Anonymous
17:01 Feature #7933 (Work Completed-End life cycle): RPP Demo - Login Page
Siti Norahayu Mohd Desa
17:01 Feature #7934 (Work Completed-End life cycle): RPP Demo - Forgot Password
Siti Norahayu Mohd Desa
16:28 Feature #7935 (Work Completed-End life cycle): RPP Demo - Password is about to expire
Siti Norahayu Mohd Desa
16:28 Feature #7936 (Work Completed-End life cycle): RPP Demo - Password has expired
Siti Norahayu Mohd Desa
16:27 Feature #7937 (Work Completed-End life cycle): RPP Demo - Force Change Password Page
Siti Norahayu Mohd Desa
10:38 Task #8094: RPP > Report
Salam Athirah,
Please find the below list of reports which are to be made available in RPP Back Office. (client u...
Siti Norahayu Mohd Desa
 

Also available in: Atom