Hi,
Kindly attend below request:-
CDB Transmittal Report display STOPPED but in IBAM File Processing, transaction display PENDING PROCESSING.
Upon checking in DB, status in consolidate bulk is not tally with auto credit main. Currently, EOD Program will fix this status
Request to fix CDB Status
History
#1 Updated by Nurul Athira Abdul Rahim over 3 years ago
- Due date set to May 06, 2021
- Assignee changed from Nurul Athira Abdul Rahim to Najmi Pasarudin
- Priority changed from Normal to High
#2 Updated by Nurul Athira Abdul Rahim over 3 years ago
- Assignee changed from Najmi Pasarudin to Nurul Hasnieza Bt Mohd Zamri
#3 Updated by Nurul Hasnieza Bt Mohd Zamri over 3 years ago
- Status changed from New - Begin Life Cycle to Development / Work In Progress
#4 Updated by Nurul Hasnieza Bt Mohd Zamri over 3 years ago
- Status changed from Development / Work In Progress to Finished Development
- % Done changed from 0 to 80
Upon checking, the status display in IBAM and CDB is called from 2 different table(BibConsolidateBulk, BibAutoCreditMain).
As for bulk payment, the initial status is set to Stopped to prevent double posting when involved large data.
When the process is done, the status will update to Pending Approval or Pending Processing.
Initial status Stopped has been updated for BibConsolidateBulk and status in CDB has been updated as in IBAM status.
#5 Updated by Nurul Hasnieza Bt Mohd Zamri over 3 years ago
- Status changed from Finished Development to Internal Testing
- Assignee changed from Nurul Hasnieza Bt Mohd Zamri to Nurul Athira Abdul Rahim
Hi Athira,
file process status in cdb has been updated. Kindly retest and please make sure the status is tally with IBAM.
#6 Updated by Nurul Athira Abdul Rahim over 3 years ago
- File 11741-Transaction status in IBAM.docx added
- Status changed from Internal Testing to Development / Work In Progress
- Assignee changed from Nurul Athira Abdul Rahim to Nurul Hasnieza Bt Mohd Zamri
Tested and failed
System display wrong status at both transmittal report, History Listing and file processing.
Current : Pending Approval
Expected : Successful / Accepted
Refer BSNeBiz transaction enquiry, system display successful.
Find attachment for reference
#7 Updated by Nurul Hasnieza Bt Mohd Zamri over 3 years ago
- Status changed from Development / Work In Progress to Finished Development
For file processing, when approval approved, the transaction status that display accepted/successful will update the file processing status
to Pending Processing for auto credit and Pending Enter Amount for auto credit without account.
#8 Updated by Nurul Hasnieza Bt Mohd Zamri over 3 years ago
- Status changed from Finished Development to Internal Testing
- Assignee changed from Nurul Hasnieza Bt Mohd Zamri to Nurul Athira Abdul Rahim
Athira, auto credit approval status has been updated. Kindly retest.
#9 Updated by Nurul Athira Abdul Rahim over 3 years ago
- File 11741-Transaction status in IBAM - Updated 080621.pdf added
- Status changed from Internal Testing to System Integration Test
Tested and passed for module
Bulk Payment
EPF
LHDN
#10 Updated by Nurul Athira Abdul Rahim about 3 years ago
- Status changed from System Integration Test to Pending UAT Deployment
- Assignee changed from Nurul Athira Abdul Rahim to Najmi Pasarudin
Tested and passed by azyan on 28/06/21
Please prepare for UAt development.
#11 Updated by Najmi Pasarudin about 3 years ago
- Status changed from Pending UAT Deployment to Code Review
#12 Updated by Najmi Pasarudin about 3 years ago
- Status changed from Code Review to Development / Work In Progress
#13 Updated by Najmi Pasarudin about 3 years ago
- Status changed from Development / Work In Progress to User Acceptance Test
- Assignee changed from Najmi Pasarudin to Nurul Athira Abdul Rahim
UAT deployed on 15/07/2021
#14 Updated by Nurul Athira Abdul Rahim about 3 years ago
- Status changed from User Acceptance Test to Pending Prod Deployment
- Assignee changed from Nurul Athira Abdul Rahim to Najmi Pasarudin
Tested and passed by Mazni on 2/8/21
Please prepare for Pre-prod deployment
TArget to go live on 6/8/21
#15 Updated by Nurul Athira Abdul Rahim about 3 years ago
- % Done changed from 80 to 90
#16 Updated by Najmi Pasarudin about 3 years ago
- Status changed from Pending Prod Deployment to Pending Review
- Assignee changed from Najmi Pasarudin to Nurul Athira Abdul Rahim
- % Done changed from 90 to 100
Prod deployed on 11/08/2021
#17 Updated by Nurul Athira Abdul Rahim about 3 years ago
- Status changed from Pending Review to Work Completed-End life cycle
- Assignee changed from Nurul Athira Abdul Rahim to Zahir Abd Latif
Migration ID0038