Support #5902
[TPMS_Prod026] - Planning > Budget > Activity Budget Allocation
Status: | Closed - End of life cycle | Start date: | January 07, 2016 | |
---|---|---|---|---|
Priority: | Normal | Due date: | January 08, 2016 | |
Assignee: | Norhaidah Md Dasuki | % Done: | 100% | |
Category: | tpms_prod | Spent time: | - | |
Target version: | - |
Description
Finance User still not update any information in Budget but in the list have value in “Budget Approved” and “Balance Budget Approved / Revised” column for below event:-
1. SPECIALISED MARKETING MISSION (SMM) FOR CONSTRUCTION AND BUILDING MATERIALS TO SYDNEY AND PERTH, AUSTRALIA
2. SPECIALISED MARKETING MISSION ON MARITIME INDUSTRY IN CONJUNCTION WITH INTERNATIONAL MARITIME TRADE FAIR - HAMBURG
History
#1 Updated by Najmi Pasarudin over 8 years ago
- Status changed from New - Begin Life Cycle to Internal Testing
- Assignee changed from Najmi Pasarudin to Siti Norahayu Mohd Desa
- % Done changed from 0 to 90
Finding:
These data may be from migrated data. BY using TPMS, budget can not be approved without budget type.
Solution:
Budget type need to be created first and select budget type for these data.
#2 Updated by Siti Norahayu Mohd Desa over 8 years ago
- File Support#5902_Test Result-TPMS_Prod026.docx added
- Status changed from Internal Testing to Pending Prod Deployment
- Assignee changed from Siti Norahayu Mohd Desa to Norhaidah Md Dasuki
Salam Kak Haida,
The test result as per attached.
#3 Updated by Norhaidah Md Dasuki over 8 years ago
- Status changed from Pending Prod Deployment to Closed - End of life cycle
- % Done changed from 90 to 100
Data Migration -
+Findings/Root Caused (Description): +
Budget approved and Budget requested are migrated based on “budget” from source data files.
Refer to screen capture as per attached.
Resolution:
Update the Budget approved and Budget requested value for the 2 activities to null.
7/1/16 - The changes has been already reflected at TPMS Production.