November 29, 2022
- 11:16 Support #13334 (System Integration Test): [SCP ID :##6525##] : FRIA-i Campaign - add new Fria-i p...
- Delivered the patch to Bank on 29/11/2022
November 26, 2022
- 23:25 Support #13339 (Work Completed-End life cycle): [SCP ID :##6528##] : IB REPORT - header issue
- Hi,
Kindly attend below request:-
Header for 3rd party report display insufficient information (total successful ...
November 24, 2022
- 10:22 Support #13334 (System Integration Test): [SCP ID :##6525##] : FRIA-i Campaign - add new Fria-i p...
- Hi,
Kindly attend below request:-
Agrobank will add new Fria-i product as part of AGROBANK FRIA-i campaign. produ...
November 22, 2022
- 17:28 Support #13326 (System Integration Test): [SCP ID :##6521##] : takaful bulk payment issue
- Finding:
The required field for the HOST report is not being sent to HOST.
Solution:
Send the required field to ... - 17:02 Support #13328 (Work Completed-End life cycle): [SCP ID :##6523##] : no annual fee deduction on a...
- Hi,
Kindly attend below request:-
please help to check, no annual fee deduction for company below.
Company Nam... - 12:33 Support #13326 (Development / Work In Progress): [SCP ID :##6521##] : takaful bulk payment issue
- 12:11 Support #13324 (System Integration Test): [SCP ID :##6519##] : Change of Takaful Provider TI to S...
- Update the Takaful PDS content as requested by Bank
- 09:23 Support #13324 (Development / Work In Progress): [SCP ID :##6519##] : Change of Takaful Provider ...
November 21, 2022
- 15:15 Support #13326 (Work Completed-End life cycle): [SCP ID :##6521##] : takaful bulk payment issue
- Hi,
Kindly attend below request:-
We notice currently takaful bulk payment send insufficient data to host (filler...
November 17, 2022
- 14:34 Support #12919: [SCP ID :##6244##] : ERROR :DECODE_VALUE_TOO_ SHORT
- Help to close the ticket. Thank you
- 14:34 Support #12919 (Work Completed-End life cycle): [SCP ID :##6244##] : ERROR :DECODE_VALUE_TOO_ SHORT
- Patch already migrated to production on 21/07/2022.
Can close this ticket - 14:30 Support #13269 (System Integration Test): [SCP ID :##6470##] : IBAM ID dormant issue
- #Finding issue/Root cause:
The last login date and date last used at cua is not updated when user access to IBAM via... - 13:59 Support #13324 (Work Completed-End life cycle): [SCP ID :##6519##] : Change of Takaful Provider T...
- Hi,
Kindly attend below request:-
As per my email on 16/11/2022, user raised new CR to change takaful provider. B... - 10:34 Support #13323 (Work Completed-End life cycle): [SCP ID :##6518##] : Request to configure x-forwa...
- Hi,
Kindly attend below request:-
Request for your kind assistance to configure x-forwarded for FPX HA servers.
...
November 07, 2022
- 09:56 Support #13237 (System Integration Test): [SCP ID :##6441##] : API Gateway not responding (24092022)
- Development done, proceed with internal testing
November 03, 2022
- 14:07 Support #12897 (Closed - End of life cycle): [SCP ID :##6227##] : SMS PIN Agronetbiz not received...
- 01/04/22
As per our joint findings, the issue is due to the path in IBAM AppConfig pointing to Java KeyStore was di... - 14:05 Support #12885 (Closed - End of life cycle): [SCP ID :##6215##] : implement the RSA Encryption at...
- deployed to PROD on 14/04/2022