Activity

From June 19, 2021 to July 18, 2021

July 15, 2021

12:09 Change #12056 (Work Completed-End life cycle): Participant Maintenance > Edit : To enable field f...
Tested & Passed. TQ Siti Norahayu Mohd Desa

July 13, 2021

01:21 Change #12056 (Internal Testing): Participant Maintenance > Edit : To enable field for edit.
deployed on VIT Bramantyo Pujo Wiyono
11:42 Change #12056 (Development / Work In Progress): Participant Maintenance > Edit : To enable field ...
1. To add asterisk for mandatory fields.
2. Error message for Telephone No. display Office No. is required. Change t...
Siti Norahayu Mohd Desa

July 02, 2021

15:24 Change #12056 (Internal Testing): Participant Maintenance > Edit : To enable field for edit.
Fixed and deployed to server. Please retest. Ngoh Chee Ping
10:19 Change #12056 (Work Completed-End life cycle): Participant Maintenance > Edit : To enable field f...
Hi CP,
As per discuss, please enable below field for Edit Participant Maintenance purpose.
* Participant Desc...
Siti Norahayu Mohd Desa

July 01, 2021

11:31 Bug #11848 (Closed - End of life cycle): [MOD301 : 1.20.2 Create Dispute Transaction
Already tested and passed. Zahir Abd Latif
10:55 Bug #11945 (Work Completed-End life cycle): [MOD034: Admin Report] RPT015 - TC047 TC048 Report - ...
Tested & Passed. Siti Norahayu Mohd Desa

June 30, 2021

18:27 Bug #11790 (Work Completed-End life cycle): [MOD022: Participant User Maintenance > Edit]: Email ...
Nurul Akmal
18:26 Bug #11844 (Work Completed-End life cycle): MOD023 :Participant User Access Control > Rewording E...
Nurul Akmal
18:25 Bug #11799 (Work Completed-End life cycle): [MOD026: PARTICIPANT > AUDIT TRAIL]: Before/After state
Nurul Akmal

June 28, 2021

16:12 Bug #12038 (Work Completed-End life cycle): Add new checking for Resend Email function in approval
Tested & Passed.
System Display "Invalid participant user status to resend email, please reject this activity."
...
Siti Norahayu Mohd Desa
Avatar?id=1966&size=24 16:02 Bug #12038 (Internal Testing): Add new checking for Resend Email function in approval
Hi Ayu,
Issue had been fixed with added error message while checker approve the resend email activity, when user s...
Ngoh Chee Onn
14:05 Bug #12038 (Work Completed-End life cycle): Add new checking for Resend Email function in approval
Hi Chee Onn,
As per subject, below is the step to reproduce the issue.
+Step 1+
# Login as Maker
# Select u...
Siti Norahayu Mohd Desa

June 25, 2021

15:59 Bug #11977 (Work Completed-End life cycle): [MOD017: Participant Maintenance] FUNC_055 - Particip...
Issue have been closed due to Participant User unable to edit their Participant details. Only Host able to edit. Siti Norahayu Mohd Desa
14:47 Bug #12002 (Work Completed-End life cycle): [TG2020_02 - 924] : Authorize Participant User update
Tested & Passed. TQ Siti Norahayu Mohd Desa
14:40 Bug #11978 (Work Completed-End life cycle): Participant Access Control > FTL
Tested & Passed. Siti Norahayu Mohd Desa

June 24, 2021

12:15 Bug #11977 (Internal Testing): [MOD017: Participant Maintenance] FUNC_055 - Participant Enquiry f...
Bramantyo Pujo Wiyono

June 21, 2021

Avatar?id=1966&size=24 11:14 Bug #11978 (Internal Testing): Participant Access Control > FTL
Hi ayu,
Fixed done and deployed into Penril Server, Fixed will deploy to Ptap server at release beta 11.
Thank you
Ngoh Chee Onn
 

Also available in: Atom