Activity

From August 20, 2016 to September 18, 2016

September 15, 2016

12:10 Support #6574 (Work Completed-End life cycle): [TPMS_GL053] -]Unable to generate report (blank re...
Case ID : TPMS/16-0053
We are unable to generate report for Planning module i.e. Report -> Budget Report -> JPKA-...
Anonymous

September 08, 2016

14:48 Support #6340 (Work Completed-End life cycle): [TPMS_GL006] - Post EVENT > JPPPA Report > Fast Fact
Email to Inteksoft on 16 Jun 16 to get feedback from user. But no reply. Issue closed .
Salam Anis,
?
Based on ...
Siti Norahayu Mohd Desa
14:38 Support #6545 (User Acceptance Test): [TPMS_GL048] - Publication >> Email Marketing
Tested & Passed. Page will look fine after run the script given.
Send for user testing & verification.
Siti Norahayu Mohd Desa
14:29 Support #6560 (User Acceptance Test): [TPMS_GL052] - Promotion >> Promotion Report >> Company De...
Tested & Passed. All value display accordingly.
Send for user testing & verification.
Siti Norahayu Mohd Desa

September 07, 2016

12:19 Support #6520 (Pending Prod Deployment): [TPMS_GL043] - Promotion >> Event Setup >> Product and S...
7 Sept 2016 12:02 PM
Dear Ayu,
Done verified on 18 August 2016.
Regards,
Azliza Husain
Application ...
Siti Norahayu Mohd Desa
12:12 Change #6559 (Pending Customer Feedback): [TPMS_GL051] - Promotion >> Business Meeting >> Busines...
Waiting reply from Teo. Siti Norahayu Mohd Desa
12:07 Change #6427: [TPMS_GL023] - Group Management
Hi Chee Ping,
Kindly assist on both quotation.
Siti Norahayu Mohd Desa
12:06 Change #6427 (Documentation): [TPMS_GL023] - Group Management
*+22 July 2016+*
Salam En. Rizal,
Below is summary on this issue:
1. TPMS module permission for view, crea...
Siti Norahayu Mohd Desa
11:58 Support #6370 (Work Completed-End life cycle): [TPMS_GL010] - Publication >> Company Profile Writ...
Najmi Pasarudin
11:28 Support #6560 (Internal Testing): [TPMS_GL052] - Promotion >> Promotion Report >> Company Detali...
Issue:
For Promotion Report, Company Detalis - Foreign Buyer(No of Buyers By product/service, order by Foreign Buyer...
Najmi Pasarudin
11:01 Support #6560 (Development / Work In Progress): [TPMS_GL052] - Promotion >> Promotion Report >> ...
Najmi Pasarudin

September 06, 2016

14:39 Support #6560 (Work Completed-End life cycle): [TPMS_GL052] - Promotion >> Promotion Report >> C...
Inteksoft Case ID : TPMS/16-0052
The total of Foreign Buyer for each products / services is not correct. (refer to...
Siti Norahayu Mohd Desa
14:08 Support #6545 (Internal Testing): [TPMS_GL048] - Publication >> Email Marketing
Issue:
Cannot edit email marketing draft for event EXPORT ACCELERATION MISSION (EAM) IN CONJUNCTION WITH MALAYSIA IN...
Najmi Pasarudin

September 05, 2016

10:17 Change #6559 (Dropped-End of life cycle): [TPMS_GL051] - Promotion >> Business Meeting >> Busines...
Users can not proceed with business match setup cause of mandatory fields(Lunch Break Time).
Business meeting sta...
Siti Norahayu Mohd Desa

September 02, 2016

12:35 Support #6544 (Pending Prod Deployment): [TPMS_GL025] - Administration >> Template Manager >> Not...
2/9/2016 12.13pm
Dear Ayu,
Done verified.

Regards,
Azliza Husain
Application Unit
Information ...
Siti Norahayu Mohd Desa
11:47 Support #6544 (User Acceptance Test): [TPMS_GL025] - Administration >> Template Manager >> Notifi...
Issue tested & passed. Send for user testing & verification. Siti Norahayu Mohd Desa

September 01, 2016

15:17 Support #6505 (Work Completed-End life cycle): [TPMS_GL037] - Promotion >> Event Setup >> Committee
Migration ID: TPMS_ID0014
War File: TPMS_v043
Planed Deployment date: 29/08/2016
Actual Deployent date: 30/08/2016
Najmi Pasarudin
15:16 Support #6532 (Work Completed-End life cycle): [TPMS_GL046] - MATRADE Portal >> List Of Participa...
Najmi Pasarudin
15:16 Support #6532: [TPMS_GL046] - MATRADE Portal >> List Of Participant >> View Write-Up
Migration ID: TPMS_ID0014
War File: TPMS_v043
Planed Deployment date: 29/08/2016
Actual Deployent date: 30/08/2016
Najmi Pasarudin
15:15 Support #6534 (Work Completed-End life cycle): [TPMS_GL047] - Planning >> Budget >> Activity Budg...
Migration ID: TPMS_ID0014
War File: TPMS_v043
Planed Deployment date: 29/08/2016
Actual Deployent date: 30/08/2016
Najmi Pasarudin
14:53 Support #6544 (Internal Testing): [TPMS_GL025] - Administration >> Template Manager >> Notificati...
Issue:
Meeting date is not showing in No Meeting email notification.
Cause:
Meeting date in No Meeting email is ...
Najmi Pasarudin
10:18 Support #6544 (Development / Work In Progress): [TPMS_GL025] - Administration >> Template Manager...
Najmi Pasarudin

August 30, 2016

16:14 Support #6463 (Work Completed-End life cycle): [TPMS_GL029] - Post Event >> Programmes >> Feedbac...
Siti Norahayu Mohd Desa
16:07 Support #6463 (User Acceptance Test): [TPMS_GL029] - Post Event >> Programmes >> Feedback - Updat...
30/8/2016 2:43 PM
Cik Siti Norahayu,
As of today, i have not received new report from users this issues occ...
Siti Norahayu Mohd Desa
10:12 Support #6545 (Development / Work In Progress): [TPMS_GL048] - Publication >> Email Marketing
Najmi Pasarudin

August 29, 2016

17:44 Support #6545 (Work Completed-End life cycle): [TPMS_GL048] - Publication >> Email Marketing
Case ID : TPMS/16-0048
There is an error when click Edit Button.
please refer attachment.
Siti Norahayu Mohd Desa
16:15 Support #6544 (Work Completed-End life cycle): [TPMS_GL025] - Administration >> Template Manager ...
Case ID : TPMS/16-0025
Secretariat for INSP KOIMA had send email notification No Meeting to Malaysian companies wh...
Siti Norahayu Mohd Desa

August 25, 2016

15:15 Support #6463 (Pending Customer Feedback): [TPMS_GL029] - Post Event >> Programmes >> Feedback - ...
I have email to Helmi to monitor on this issue. if no other issue until end of August this issue will automatically c... Siti Norahayu Mohd Desa
15:10 Support #6505 (Pending Prod Deployment): [TPMS_GL037] - Promotion >> Event Setup >> Committee
25/08/2016 2:50 PM
Dear Ayu,
Done testing last week but forgot to send email.
Sorry for the late feedback...
Siti Norahayu Mohd Desa

August 23, 2016

17:47 Support #6463 (Internal Testing): [TPMS_GL029] - Post Event >> Programmes >> Feedback - Update co...
For this issue, cannot replicate in UAT. Update has been deployed to production. Required Matrade IT member to monito... Najmi Pasarudin
17:41 Change #6427 (Pending Customer Feedback): [TPMS_GL023] - Group Management
Siti Norahayu Mohd Desa
16:17 Support #6370: [TPMS_GL010] - Publication >> Company Profile Write Up
This issue can be closed since company has been able to upload images for company profile write-up up until now. Najmi Pasarudin
16:09 Support #6534 (Pending Prod Deployment): [TPMS_GL047] - Planning >> Budget >> Activity Budget All...
23/8/2016 2:49 PM
Dear Ayu,
Done verified.

Regards,
Azliza Husain
Application Unit
Information...
Siti Norahayu Mohd Desa
16:08 Support #6532 (Pending Prod Deployment): [TPMS_GL046] - MATRADE Portal >> List Of Participant >> ...
23/8/2016 2:46 PM
Dear Ayu,
Done verified.

Regards,
Azliza Husain
Application Unit
Information T...
Siti Norahayu Mohd Desa
16:04 Support #6534 (User Acceptance Test): [TPMS_GL047] - Planning >> Budget >> Activity Budget Alloca...
Testing & Passed. Send for user testing & verification. Siti Norahayu Mohd Desa
12:39 Support #6534 (Internal Testing): [TPMS_GL047] - Planning >> Budget >> Activity Budget Allocation
Note: This issue only happens in Production.
Issue:
For GITEX event, received error page in Budget Activity Alloc...
Najmi Pasarudin
12:31 Support #6534 (Development / Work In Progress): [TPMS_GL047] - Planning >> Budget >> Activity Bud...
Najmi Pasarudin
12:30 Support #6534 (Work Completed-End life cycle): [TPMS_GL047] - Planning >> Budget >> Activity Budg...
There is an error (blue screen) when click button Activity Allocation for event GITEX 2016. Siti Norahayu Mohd Desa
12:00 Support #6532 (User Acceptance Test): [TPMS_GL046] - MATRADE Portal >> List Of Participant >> Vie...
Testing & Passed. Send for user testing & verification. Siti Norahayu Mohd Desa

August 22, 2016

15:01 Support #6532 (Internal Testing): [TPMS_GL046] - MATRADE Portal >> List Of Participant >> View Wr...
Issue:
Label mistake for programme type Export Acceleration Mission, image table is labeled as product/service inste...
Najmi Pasarudin
13:37 Support #6532 (Development / Work In Progress): [TPMS_GL046] - MATRADE Portal >> List Of Particip...
Najmi Pasarudin
11:42 Support #6532 (Work Completed-End life cycle): [TPMS_GL046] - MATRADE Portal >> List Of Participa...
There is an error when click View Write-up in MATRADE portal. If programme type is Export Acceleration Mission, the w... Siti Norahayu Mohd Desa
09:53 Support #6527 (Work Completed-End life cycle): [TPMS_GL045] - Planning >> Budget >> Annual Alloca...
Migration ID: TPMS_ID0013
War File: TPMS_v042
Deployed date: 19/08/2016
Najmi Pasarudin
09:52 Support #6526 (Work Completed-End life cycle): [TPMS_GL044] - Planning >> Activities List >> Add ...
Migration ID: TPMS_ID0013
War File: TPMS_v042
Deployed date: 19/08/2016
Najmi Pasarudin
 

Also available in: Atom