Activity

From April 27, 2017 to May 26, 2017

May 26, 2017

15:23 Support #7474 (Internal Testing): [TPMS_GL087] - Post Event > Edit Button
Issue:
Post-event follow-up for event INSP INTRADE 2016 shows error page.
Cause:
Follow-up not available for INS...
Najmi Pasarudin

May 25, 2017

14:10 Support #7474 (Development / Work In Progress): [TPMS_GL087] - Post Event > Edit Button
Najmi Pasarudin
11:34 Support #7474 (Work Completed-End life cycle): [TPMS_GL087] - Post Event > Edit Button
Case ID : TPMS/17-0018
Untuk Post Event-> INSP INTRADE 2016
Bila klik button EDIT untuk Follow up Month 3, erro...
Siti Norahayu Mohd Desa

May 22, 2017

17:10 Support #6785 (Pending Customer Feedback): [TPMS_GL066] - Publication > Email Marketing
Siti Norahayu Mohd Desa

May 19, 2017

16:27 Change #6427: [TPMS_GL023] - Group Management
Hi Amy,
Below is code changes need to be made. Estimate need like 7-10 days including UAT.
A. Update Admin Grou...
Najmi Pasarudin
10:41 Support #7424 (Pending Prod Deployment): [TPMS_GL086] - Promotion > Event Setup > Committee
Siti Norahayu Mohd Desa
10:40 Support #7417 (User Acceptance Test): [TPMS_GL085] - Post Event Report for TIM
Dear Pn.Azliza,
This is because server issue. I already restart TPMS UAT server. Please try again.
Thank you.
Siti Norahayu Mohd Desa
10:39 Support #7417 (Development / Work In Progress): [TPMS_GL085] - Post Event Report for TIM
Dear Ayu,
Have tested but failed to display result.
Regards,
Azliza Husain
Application Unit
Information T...
Siti Norahayu Mohd Desa
10:30 Support #7424: [TPMS_GL086] - Promotion > Event Setup > Committee
19May 2017 10:12 AM
Dear Ayu,
Have tested and the list of users are loaded.

Regards,
Azliza Husain...
Siti Norahayu Mohd Desa
10:29 Support #7408: [TPMS_GL082] - Post Event > Feedback Form
TPMS UAT server has been restart. Please try again. In addition, Trade Fair feedback is with the FOC non-CR, please t... Siti Norahayu Mohd Desa
10:28 Support #7408: [TPMS_GL082] - Post Event > Feedback Form
19 May 2017 9:59 AM
Dear Ayu,
Have tested but the feedback form failed to submit.
(See attached file: Feedb...
Siti Norahayu Mohd Desa
09:50 Support #6785 (Internal Testing): [TPMS_GL066] - Publication > Email Marketing
Issue has been deployed in migration ID0018, TPMS version 47 on 25 November 2016. There is no test scenario since thi... Najmi Pasarudin

May 18, 2017

18:12 Change #6427: [TPMS_GL023] - Group Management
Hi Amy,
Kindly assist on both quotation.
Siti Norahayu Mohd Desa
11:55 Support #6968 (User Acceptance Test): [TPMS_GL071] - Feedback Form
Send for user testing Siti Norahayu Mohd Desa
11:50 Support #7424 (User Acceptance Test): [TPMS_GL086] - Promotion > Event Setup > Committee
Send for user testing Siti Norahayu Mohd Desa
11:47 Support #7417 (User Acceptance Test): [TPMS_GL085] - Post Event Report for TIM
Send for user testing Siti Norahayu Mohd Desa
11:43 Support #7408 (User Acceptance Test): [TPMS_GL082] - Post Event > Feedback Form
Send for user testing Siti Norahayu Mohd Desa
11:36 Support #6968 (Internal Testing): [TPMS_GL071] - Feedback Form
Please try again with the following scenario:
Test scenario 1:
# Login to TPMS.
# Access Post-Event Programmes.
...
Najmi Pasarudin

May 16, 2017

15:57 Support #7412 (Development / Work In Progress): [TPMS_GL084] - ARAB HEALTH 2017 (REPORT SALES)
Najmi Pasarudin

May 15, 2017

12:28 Support #7408 (Internal Testing): [TPMS_GL082] - Post Event > Feedback Form
Issue:
When new company access to TPMS feedback form link for the first time, the page always fail to load css.
...
Najmi Pasarudin
10:00 Task #7394 (Pending Customer Feedback): TPMS non-CR FOC task
Najmi Pasarudin

May 12, 2017

12:07 Support #7417 (Internal Testing): [TPMS_GL085] - Post Event Report for TIM
Issue:
Post-Event (Trade Investment Mission)TIM report not working. Company feedback all blank.
Cause:
Post-Even...
Najmi Pasarudin

May 09, 2017

15:12 Support #7417 (Development / Work In Progress): [TPMS_GL085] - Post Event Report for TIM
Najmi Pasarudin

May 05, 2017

15:09 Support #7424 (Internal Testing): [TPMS_GL086] - Promotion > Event Setup > Committee
Issue:
Promotion Committee edit does not load user list and user cannot be assigned in event committee.
Cause:
W...
Najmi Pasarudin
14:58 Support #7424 (Development / Work In Progress): [TPMS_GL086] - Promotion > Event Setup > Committee
Najmi Pasarudin
12:13 Support #7424 (Work Completed-End life cycle): [TPMS_GL086] - Promotion > Event Setup > Committee
Case ID : TPMS/17-0016
Mohon untuk semak samada terdapat bugs atau tidak pada modul Promotion -> Event Setup-> Com...
Siti Norahayu Mohd Desa

May 03, 2017

10:41 Support #7417 (Work Completed-End life cycle): [TPMS_GL085] - Post Event Report for TIM
Case ID : TPMS/17-0015
There is an error in te Post Event Report for Trade and Investment Mission To Japan and Kor...
Siti Norahayu Mohd Desa

May 02, 2017

12:46 Support #7411 (User Acceptance Test): [TPMS_GL083] - Event Participating Company
Send for user testing Siti Norahayu Mohd Desa
11:15 Support #7408 (Development / Work In Progress): [TPMS_GL082] - Post Event > Feedback Form
Najmi Pasarudin
11:14 Support #7411 (Internal Testing): [TPMS_GL083] - Event Participating Company
Issue:
Database contains wrong data for ec_bumi_status column in table event_participating_company.
Cause:
Wrong...
Najmi Pasarudin
11:11 Support #7411 (Development / Work In Progress): [TPMS_GL083] - Event Participating Company
Najmi Pasarudin
10:49 Support #7412 (Work Completed-End life cycle): [TPMS_GL084] - ARAB HEALTH 2017 (REPORT SALES)
Case ID : TPMS/17-0014
The sales for the above event in TPMS is not same with the manual report. To check the cu...
Siti Norahayu Mohd Desa
10:39 Support #7411 (Work Completed-End life cycle): [TPMS_GL083] - Event Participating Company
Case ID : TPMS/17-0013
We found out that the data for ec_bumi_status column in event_participating_company is w...
Siti Norahayu Mohd Desa

April 27, 2017

14:46 Support #7408 (Work Completed-End life cycle): [TPMS_GL082] - Post Event > Feedback Form
Case ID : TPMS/17-0012
When user click the link follow up feedback form from email they received, feedback form wa...
Siti Norahayu Mohd Desa
10:19 Change #6750 (Dropped-End of life cycle): [TPMS_GL064] - Promotion >> Registration - Unable to re...
Najmi Pasarudin
10:18 Support #7134 (Work Completed-End life cycle): [TPMS_GL076] - Post Event >> Feedback
Najmi Pasarudin
10:17 Change #6559 (Dropped-End of life cycle): [TPMS_GL051] - Promotion >> Business Meeting >> Busines...
This is considered CR. Matrade setup business meeting from lunch hour(1pm) as alternative for meeting that start at 2pm. Najmi Pasarudin
10:13 Support #7231 (Work Completed-End life cycle): [TPMS_GL080] - Post Event > JPPPA Report > Outcome...
Email from Arshad(Matrade IT department personnel):
> Dear Najmi,
>
> Deployment activity(Migration plan ID:0021...
Najmi Pasarudin
10:13 Support #7123 (Work Completed-End life cycle): [TPMS_GL073] - Post Event >> Report >> JPPPA
Email from Arshad(Matrade IT department personnel):
> Dear Najmi,
>
> Deployment activity(Migration plan ID:0021...
Najmi Pasarudin
10:04 Support #6968 (Development / Work In Progress): [TPMS_GL071] - Feedback Form
Salam Najmi,
Below is the feedback from user:-
+For the Test scenario 1+
*Expected result:* form is saved bu...
Siti Norahayu Mohd Desa
 

Also available in: Atom