Activity
From August 12, 2020 to September 10, 2020
September 10, 2020
- 19:18 CR20004 - FPX Bug #11239 (User Acceptance Test): Expected result error code 13 - AgronetBiz B2B1
- done deploy to uat and testing
- 19:17 CR20004 - FPX Bug #11238 (User Acceptance Test): Expected result error code 13 - Agronet B2C
- done deploy to UAT
- 17:47 0. CDB_Change Request Task #11100: [CR19003] : [MOBILE IOS] To Add New EPF Payment Type (Late Payment & Dividen)
- Hi Adit,
EPF Other Payment can successfully approved via iOS.
However still missing a few field:
1. Details Pa... - 17:39 0. CDB_Change Request Task #11101 (Development / Work In Progress): [CR19003] : [MOBILE ANDROID] To Add New EPF Payment...
- Hi Daren,
EPF Other Payment can successfully displayed and approved in ANDROID.
However, please remove below fiel... - 16:37 CR20004 - FPX Bug #11238 (Pending SIT Deployment): Expected result error code 13 - Agronet B2C
- 14:41 CR20004 - FPX Bug #11239: Expected result error code 13 - AgronetBiz B2B1
- correction on the title
- 14:40 CR20004 - FPX Bug #11239 (Work Completed-End life cycle): Expected result error code 13 - AgronetBiz B2B1
- Balqis will add return error code 13 when IB exceeds the maximum limit.
Email: Expected result error code 13 - 14:39 CR20004 - FPX Bug #11238 (Work Completed-End life cycle): Expected result error code 13 - Agronet B2C
- Hi Hazirah, please return error code 13 when IB exceeds the maximum limit.
Email: Expected result error code 13
September 09, 2020
- 12:21 CR20004 - FPX Task #11228 (Development / Work In Progress): [DEV] B2B2 Fees
- FPX New Request 08/09/20
Email: RE: Discussion on Online Refund Fee Handling
Redmine:
https://hub.penril.net/re... - 12:20 CR20004 - FPX Task #11227 (Development / Work In Progress): [DEV] B2B2 TokenType
- FPX New Request 08/09/20
Email: RE: Discussion on Online Refund Fee Handling
Redmine:
https://hub.penril.net/re...
September 08, 2020
- 20:39 CR20004 - FPX Task #11228: [DEV] B2B2 Fees
- Requirement is in email:
RE: Discussion on Online Refund Fee Handling - 20:38 CR20004 - FPX Task #11227: [DEV] B2B2 TokenType
- Requirement is in email:
RE: Discussion on Online Refund Fee Handling - 19:53 CR20004 - FPX Task #11228 (Development / Work In Progress): [DEV] B2B2 Fees
- Add fee 1 and fee 2 fields.
- 19:51 CR20004 - FPX Task #11227 (Development / Work In Progress): [DEV] B2B2 TokenType
- Add below fields:
TokenType = O is FPX Payment - use b2b1 service info
TokenType = OX is FPX Refund - use online ... - 12:25 0. CDB_Change Request Task #11100 (Development / Work In Progress): [CR19003] : [MOBILE IOS] To Add New EPF Payment Typ...
- Hi Adit,
Issue has been tested and failed. Refer below for issue happened:
1. Details at iOS Approval Details p... - 12:12 0. CDB_Change Request Bug #11191 (Work Completed-End life cycle): [CDB] Details at Approver & Verifier Result Page is n...
- Tested and Passed
September 04, 2020
- 20:14 KFH Change Request Task #10915: 5370:BNM Requirement to address the SMS OTP TAC fraud - Password Complexity
- SSAO login and navigation pending test
- 10:05 1. CDB_Phase 2 & 3 Development Task #10424: [P1_Extended] IOS - CDB_Push Notification for authorization
- IOS source code developement complete. restful source code developemnt complete. to proceed to sit test BSN need prov...
- 10:00 0. CDB_Change Request Task #11100 (Internal Testing): [CR19003] : [MOBILE IOS] To Add New EPF Payment Type (Late Paymen...
- @Erni Please proceed to internal testing
- 10:00 0. CDB_Change Request Task #11100 (Development / Work In Progress): [CR19003] : [MOBILE IOS] To Add New EPF Payment Typ...
- IOS updated to version 3.2.1 build 84. Restful deployed
September 03, 2020
- 18:39 0. CDB_Change Request Bug #11191 (Internal Testing): [CDB] Details at Approver & Verifier Result Page is not complete
- Hi Erni,
approver result page details epf other payment has been updated. Kindly retest. - 12:54 0. CDB_Change Request Bug #11191 (Finished Development): [CDB] Details at Approver & Verifier Result Page is not complete
September 02, 2020
- 18:24 Industry Fraud Bug #11202 (Internal Testing): [MULE Account Enquiry] : Create Bulk Record > Negative Testing
- Hi Akmal,
Error message changed, please try again.
Thank you - 17:55 Industry Fraud Bug #11202 (Pending Fixes): [MULE Account Enquiry] : Create Bulk Record > Negative Testing
- 17:55 Industry Fraud Bug #11202: [MULE Account Enquiry] : Create Bulk Record > Negative Testing
- Pls help update as below.
Scenario 2:
Expected (FSD):
Total number of record not match. Please check your fil... - 16:52 Industry Fraud Bug #11202 (Pending Review): [MULE Account Enquiry] : Create Bulk Record > Negative Testing
- Hi Amy,
Kindly advise.
Thank you. - 16:38 Industry Fraud Bug #11202: [MULE Account Enquiry] : Create Bulk Record > Negative Testing
- Hi Akmal,
Please help to check with Amy on this error message in FSD whether updated or not, due to newest request... - 16:36 Industry Fraud Bug #11205 (Internal Testing): [MULE Account Enquiry] : Create Single Record > Negative Testing
- Hi Akmal,
Issue for scenario 1 and 2 had been fixed, please try again.
Thank you - 16:35 Industry Fraud Bug #11205 (Development / Work In Progress): [MULE Account Enquiry] : Create Single Record > Nega...
- 16:02 0. CDB_Change Request Enhancement #10112 (Work Completed-End life cycle): [CR19001] : To add "Collection Receivable" fu...
- 11:30 Industry Fraud Bug #11205 (Work Completed-End life cycle): [MULE Account Enquiry] : Create Single Record > Negat...
- *Scenario 1*: Leave blank all fields
*Result*: Hit error: "MULE Report already exist."
*Expected*:
* Proxy Type i... - 10:49 Industry Fraud Bug #11202 (Work Completed-End life cycle): [MULE Account Enquiry] : Create Bulk Record > Negati...
- To amend error message as per in FSD for followings scenarios:
+Scenario 1:+
Bulk file unique ID already exist in... - 10:35 CR19006 - Takaful Kasih Plus (TKP) Task #11142 (Development / Work In Progress): [DOC] FSD Takaful Kasih Plus
- 10:35 CR20013 - Change SOCSO Host Transaction Code Task #11153 (Finished Development): [DEV] CR20013 - Change SOCSO Host Transaction Code
- Done development. Waiting for update to be deploy to SIT / UAT.
September 01, 2020
- 19:17 KFH Change Request Task #10915: 5370:BNM Requirement to address the SMS OTP TAC fraud - Password Complexity
- testing upass and integration with IB, removing existing validation to allow regex to validate password.
- 14:47 Industry Fraud Bug #11178 (Work Completed-End life cycle): [Committee User Maintenance] : Suspend user using che...
- Tested and passed.
Thank you. - 14:46 Industry Fraud Bug #11194 (Work Completed-End life cycle): [MULE Account Enquiry] : MULE Account list
- Tested and passed.
Thank you. - 14:46 Industry Fraud Bug #11193 (Work Completed-End life cycle): [MULE Account Enquiry] : Delete record
- Tested and passed.
Thank you. - 14:46 Industry Fraud Bug #11195 (Work Completed-End life cycle): [MULE Account Enquiry] : Industry Fraud Audit Trail -...
- Tested and passed.
Thank you. - 11:36 Industry Fraud Bug #11193 (Internal Testing): [MULE Account Enquiry] : Delete record
- Hi Akmal,
Issue fixed, please try again.
Thank you - 11:36 Industry Fraud Bug #11193 (Development / Work In Progress): [MULE Account Enquiry] : Delete record
- 11:36 Industry Fraud Bug #11194 (Internal Testing): [MULE Account Enquiry] : MULE Account list
- Hi Akmal,
Issue fixed, please try again.
Thank you - 11:35 Industry Fraud Bug #11194 (Development / Work In Progress): [MULE Account Enquiry] : MULE Account list
- 11:35 Industry Fraud Bug #11195 (Internal Testing): [MULE Account Enquiry] : Industry Fraud Audit Trail - Create Bulk ...
- Hi Akmal,
Issue fixed, please try again.
Thank you - 11:34 Industry Fraud Bug #11195 (Development / Work In Progress): [MULE Account Enquiry] : Industry Fraud Audit Trail ...
August 28, 2020
- 18:19 0. CDB_Change Request Task #11101 (Finished Development): [CR19003] : [MOBILE ANDROID] To Add New EPF Payment Type (Lat...
- Finished development. Added EPF/Other Payment to display at Approval Listing. Please test
SIT https://drive.google... - 18:17 KFH Change Request Task #10915: 5370:BNM Requirement to address the SMS OTP TAC fraud - Password Complexity
- Corus password management testing and debugging finished.
Started foundations for multi platform support (IB,BIB,C... - 12:16 2. Inhouse Task (Development & QA) Bug #11086 (Pending Review): [Mozilla Firefox] CDB : System does not remove the deleted file format
- 12:14 1. CDB_Phase 2 & 3 Development Bug #11072 (Closed - End of life cycle): [LHDNSIT_018] Organization code not appear in service an...
- 12:13 1. CDB_Phase 2 & 3 Development Bug #11073 (Closed - End of life cycle): [LHDNSIT_020] : Employer no in LHDN history screen displ...
- 10:42 Industry Fraud Bug #11195 (Work Completed-End life cycle): [MULE Account Enquiry] : Industry Fraud Audit Trail -...
- Status in Audit Trail and transaction not standardize.
*Steps:*
# Perform Upload bulk record.
# Get result Succ... - 10:10 Industry Fraud Bug #11194 (Work Completed-End life cycle): [MULE Account Enquiry] : MULE Account list
- Contact Number column display empty data for all records.
Kindly assist to check. - 10:07 Industry Fraud Bug #11193 (Work Completed-End life cycle): [MULE Account Enquiry] : Delete record
- To give permission to delete record to below role
- Paynet Admin
- Fraud Committee User
Currently there are on...
August 27, 2020
- 17:43 0. CDB_Change Request Bug #11191 (Work Completed-End life cycle): [CDB] Details at Approver & Verifier Result Page is n...
- Bug:
1. Does not include "Print Receipt" button
2. Does not contain below details:
>1. Payment Type (Late Payment/... - 17:38 0. CDB_Change Request Bug #11182 (Work Completed-End life cycle): [CDB] Payment Type at CDB displaye value "L"/"D" at R...
- Tested and passed
Thanks Nieza - 17:37 0. CDB_Change Request Bug #11181 (Work Completed-End life cycle): [CDB] Result status after Approver approved display "...
- Tested and passed.
Result status can successfully display status "Accepted" after approved
Thanks Nieza - 17:35 0. CDB_Change Request Bug #11180 (Work Completed-End life cycle): [CDB] System unable to display appropriate error message
- Tested and passed
Thanks Nieza - 17:13 0. CDB_Change Request Bug #11180 (Internal Testing): [CDB] System unable to display appropriate error message
- Hi Erni,
validation error message has been updated. Kindly retest. - 17:12 0. CDB_Change Request Bug #11182 (Internal Testing): [CDB] Payment Type at CDB displaye value "L"/"D" at Receipt
- Hi Erni,
payment type display in receipt has been updated. Kindly retest. - 17:11 0. CDB_Change Request Bug #11181 (Internal Testing): [CDB] Result status after Approver approved display "Successful"
- Hi Erni,
result status for approver approved has been updated. Kindly retest. - 11:27 0. CDB_Change Request Bug #11181 (Finished Development): [CDB] Result status after Approver approved display "Successful"
- 11:13 0. CDB_Change Request Bug #11181 (Development / Work In Progress): [CDB] Result status after Approver approved display ...
- 11:13 0. CDB_Change Request Bug #11182 (Finished Development): [CDB] Payment Type at CDB displaye value "L"/"D" at Receipt
- 10:59 0. CDB_Change Request Change #11157 (Work Completed-End life cycle): [CDB] Change "EPF No" field
- Tested and passed
1. Employer EPF No can successfully displayed as default field at CDB:
- Data Entry
- EPF Other ... - 09:59 0. CDB_Change Request Bug #11182 (Development / Work In Progress): [CDB] Payment Type at CDB displaye value "L"/"D" at ...
August 26, 2020
- 18:14 Industry Fraud Bug #11178 (Internal Testing): [Committee User Maintenance] : Suspend user using checker maker role
- Hi Akmal,
Issue fixed, please try again.
Thank you - 18:13 Industry Fraud Bug #11178 (Development / Work In Progress): [Committee User Maintenance] : Suspend user using ch...
- 17:14 0. CDB_Change Request Bug #11180 (Finished Development): [CDB] System unable to display appropriate error message
- 17:01 0. CDB_Change Request Bug #11182 (Work Completed-End life cycle): [CDB] Payment Type at CDB displaye value "L"/"D" at R...
- Bug: Payment Type at CDB displaye value "L"/"D" at Receipt
Expected Result:
Should display below value for Paymen... - 16:34 Phase 2 Enhancement Bug #11170 (Internal Testing): [RPPBOP2_SIT126]: Merchant Audit Trail
- Hi Ayu,
Found issue in superadmin or maker user create or edit product. Issues fixed, please try again after deplo... - 16:32 Phase 2 Enhancement Bug #11170 (Development / Work In Progress): [RPPBOP2_SIT126]: Merchant Audit Trail
- 16:32 Phase 2 Enhancement Bug #11169 (Internal Testing): [RPPBOP2_SIT124]: Merchant Registration > Email notification
- Hi Ayu,
Merchant Id added only at last step of paynet user approved, due to not able to get the merchant id before... - 16:30 Phase 2 Enhancement Bug #11169 (Development / Work In Progress): [RPPBOP2_SIT124]: Merchant Registration > Email noti...
- 16:10 0. CDB_Change Request Bug #11181 (Work Completed-End life cycle): [CDB] Result status after Approver approved display "...
- Bug: Result status after Approver approved display "Successful". (Should be "Accepted", same result status for single...
- 15:46 0. CDB_Change Request Bug #11180 (Development / Work In Progress): [CDB] System unable to display appropriate error mes...
- 15:37 0. CDB_Change Request Bug #11180 (Work Completed-End life cycle): [CDB] System unable to display appropriate error message
- Bug: System displayed error "Service is currently unavailable" instead of appropriate error message
Scenario:
1. ... - 15:15 Industry Fraud Bug #11178 (Work Completed-End life cycle): [Committee User Maintenance] : Suspend user using che...
- User status remain *Normal* after admin checker successfully approved Suspend user.
- 13:38 Phase 2 Enhancement Bug #11167 (Internal Testing): [RPPBOP2_SIT121]: Merchant Maintenance > Merchant Enquiry > Produc...
- Hi Ayu,
Second level authentication added to create new merchant product, please try again after deployment done.
... - 13:38 Phase 2 Enhancement Bug #11167 (Development / Work In Progress): [RPPBOP2_SIT121]: Merchant Maintenance > Merchant En...
- 13:37 Phase 2 Enhancement Bug #11168 (Internal Testing): [RPPBOP2_SIT122]: Merchant Maintenance > Merchant Enquiry > Produc...
- Hi Ayu,
Second level authentication added to suspend, activate and terminate action and effective date will update... - 13:36 Phase 2 Enhancement Bug #11168 (Development / Work In Progress): [RPPBOP2_SIT122]: Merchant Maintenance > Merchant En...
- 11:04 Phase 2 Enhancement Bug #11163 (Internal Testing): [RPPBOP2_SIT117]: Merchant Maintenance > Pending Application
- Hi Ayu,
Issue fixed, please try again after deployment done by today.
Thank you - 11:04 Phase 2 Enhancement Bug #11163 (Development / Work In Progress): [RPPBOP2_SIT117]: Merchant Maintenance > Pending App...
- 11:03 Phase 2 Enhancement Bug #11166 (Internal Testing): [RPPBOP2_SIT120]: Merchant Maintenance > Merchant Enquiry > Produc...
- Hi Ayu,
Issue fixed, please try again after deployment done by today.
Thank you - 11:03 Phase 2 Enhancement Bug #11166 (Development / Work In Progress): [RPPBOP2_SIT120]: Merchant Maintenance > Merchant En...
- 10:40 Phase 2 Enhancement Bug #11165 (Development / Work In Progress): [RPPBOP2_SIT119]: Merchant Maintenance > Merchant En...
- Hi Ayu,
I'm not able to replicate this issue here. According to the log, there is no matched merchant for that use... - 10:30 Phase 2 Enhancement Bug #11164: [RPPBOP2_SIT118]: Merchant Maintenance > Merchant User Maintenance
- Hi Ayu,
Not clear on which step and module for this issue, please provide the step.
Thank you - 10:00 Industry Fraud Bug #11149 (Work Completed-End life cycle): [PARTICIPANTS] : Participant Enquiry > Fraud Email Di...
- Tested and passed.
Thank you.
August 25, 2020
- 01:02 Phase 2 Enhancement Bug #11170 (Closed - End of life cycle): [RPPBOP2_SIT126]: Merchant Audit Trail
- Creating product audit does not capture all the info.
Where is the info for Crediting agent, account no, account typ... - 01:00 Phase 2 Enhancement Bug #11169 (Closed - End of life cycle): [RPPBOP2_SIT124]: Merchant Registration > Email notifica...
- "Could we add 1 more field Merchant Id in the email content?
Because merchant id is auto generated, they may not awa... - 00:55 Phase 2 Enhancement Bug #11168 (Closed - End of life cycle): [RPPBOP2_SIT122]: Merchant Maintenance > Merchant Enquir...
- "Suspend / Activiate/ Terminate currently does not route to bank for approval (like item above 121)
Question
If I... - 00:52 Phase 2 Enhancement Bug #11167 (Closed - End of life cycle): [RPPBOP2_SIT121]: Merchant Maintenance > Merchant Enquir...
- "Based on FSD page 104 - For every new product the merchant wants to add into their listing, the product must be appr...
- 00:45 Phase 2 Enhancement Bug #11166 (Closed - End of life cycle): [RPPBOP2_SIT120]: Merchant Maintenance > Merchant Enquir...
- Failed to approve the product on the same day it is created.
Login as Merchant User checker.
Refer attachment. - 00:32 Phase 2 Enhancement Bug #11165 (Closed - End of life cycle): [RPPBOP2_SIT119]: Merchant Maintenance > Merchant Enquir...
- Click on merchant product management and hit error.
2020/08/24 22:26:28:187 ERROR enterprise.services.ss113_mercha... - 00:28 Phase 2 Enhancement Bug #11164 (Closed - End of life cycle): [RPPBOP2_SIT118]: Merchant Maintenance > Merchant User M...
- Re-activate to send out email activation.
The description is not complete.
Login as Administrator - 00:14 Phase 2 Enhancement Bug #11163 (Closed - End of life cycle): [RPPBOP2_SIT117]: Merchant Maintenance > Pending Applica...
- The pagination is not same as current one.
And why is it shown since it has only 2 records?
Login as Paynet Che... - 19:44 Industry Fraud Bug #11149 (Internal Testing): [PARTICIPANTS] : Participant Enquiry > Fraud Email Distribution > ...
- *Step to reproduce:*
1. Login as Admin maker.
2. Create fraud email, get result pending approval.
3. Create fraud ... - 18:36 Industry Fraud Bug #11148 (Work Completed-End life cycle): [Committee User Maintenance] : Email activation not r...
- Tested and passed.
Thank you. - 18:34 Industry Fraud Bug #11161 (Work Completed-End life cycle): [Committee User Maintenance] : Edit > To Add field va...
- Tested and passed.
Thank you. - 18:32 Industry Fraud Bug #11158 (Work Completed-End life cycle): [PARTICIPANTS] : Participant Enquiry > Fraud Email Di...
- Tested and passed.
Thank you. - 18:31 Industry Fraud Bug #11149 (Development / Work In Progress): [PARTICIPANTS] : Participant Enquiry > Fraud Email D...
- Successfully tested via administrator role.
Error while testing via maker checker role.
*Step to reproduce:*
... - 18:15 Industry Fraud Bug #11161 (Internal Testing): [Committee User Maintenance] : Edit > To Add field validation
- Hi Akmal,
Validation issues fixed, please try again.
Thank you - 18:14 Industry Fraud Bug #11161 (Development / Work In Progress): [Committee User Maintenance] : Edit > To Add field v...
- 17:51 0. CDB_Change Request Change #11157 (Internal Testing): [CDB] Change "EPF No" field
- Hi Erni,
the issue has been fixed. Kindly retest. - 17:35 Industry Fraud Bug #11149: [PARTICIPANTS] : Participant Enquiry > Fraud Email Distribution > Create
- changed assignee to Nurul Akmal
- 17:33 Industry Fraud Bug #11158 (Internal Testing): [PARTICIPANTS] : Participant Enquiry > Fraud Email Distribution > ...
- Fixed issue where successfully created email did not displayed in the table.
- 14:59 Industry Fraud Bug #11161 (Work Completed-End life cycle): [Committee User Maintenance] : Edit > To Add field va...
- Below fields have no validation during edit. Able to enter any character.
* Name
* Office No.
* Mobile No.
* Em... - 13:00 0. CDB_Change Request Bug #11155 (Work Completed-End life cycle): [IBAM>Content] Unable to offline content
- Tested and passed
Thanks nieza - 12:42 0. CDB_Change Request Change #11157 (Development / Work In Progress): [CDB] Change "EPF No" field
- Hi Nieza,
Employer EPF No field can successfully displayed as a default field.
However, after click on "Next" but... - 12:37 0. CDB_Change Request Bug #11155 (Internal Testing): [IBAM>Content] Unable to offline content
- Hi Erni,
the issue has been fixed. Kindly retest. - 12:36 0. CDB_Change Request Change #11157 (Internal Testing): [CDB] Change "EPF No" field
- Hi Erni, the epf employer no. field has been updated. kindly retest.
- 10:12 Industry Fraud Bug #11148 (Internal Testing): [Committee User Maintenance] : Email activation not received
- Hi Akmal,
Send email issue fixed, please try again.
Thank you - 09:46 Phase 2 Enhancement Bug #11000 (Work Completed-End life cycle): [MERCHANT MAINTENANCE] : Merchant Audit Trail > Advan...
- 09:45 Industry Fraud Bug #11146 (Work Completed-End life cycle): [MULE Account Enquiry] : Advance search
- Tested and passed. Thank you.
- 09:44 Industry Fraud Bug #11151 (Work Completed-End life cycle): [MULE Account Enquiry] : Create > Confirm page
- Tested and passed. Thank you.
- 09:44 Industry Fraud Bug #11159 (Work Completed-End life cycle): [Committee User Maintenance] : Spelling error for wor...
- Tested and passed. Thank you.
- 09:43 Industry Fraud Bug #11158 (Development / Work In Progress): [PARTICIPANTS] : Participant Enquiry > Fraud Email D...
- Tested.
Found issue where successfully created email did not displayed in the table.
Kindly assist to check. Than...
August 24, 2020
- 17:53 Industry Fraud Bug #11159 (Internal Testing): [Committee User Maintenance] : Spelling error for word 'Maintenance'.
- Hi Akmal,
Spelling error fixed, please try again.
Thank you - 17:52 Industry Fraud Bug #11159 (Development / Work In Progress): [Committee User Maintenance] : Spelling error for wo...
- 17:52 Industry Fraud Bug #11151 (Internal Testing): [MULE Account Enquiry] : Create > Confirm page
- Hi Akmal,
Issue fixed, please try again.
Thank you - 17:51 Industry Fraud Bug #11146 (Internal Testing): [MULE Account Enquiry] : Advance search
- Hi Akmal,
The text had been remove, please try again.
Thank you - 16:17 Industry Fraud Bug #11158 (Internal Testing): [PARTICIPANTS] : Participant Enquiry > Fraud Email Distribution > ...
- back page flow fixed for create result page and delete result page
- 15:26 0. CDB_Change Request Change #11157 (Finished Development): [CDB] Change "EPF No" field
- 15:18 Industry Fraud Bug #11159 (Work Completed-End life cycle): [Committee User Maintenance] : Spelling error for wor...
- Kindly assist to fix the *Maintenance* spelling at below screen:
* Main screen and navigation
* User details and ... - 15:05 Industry Fraud Bug #11151 (Development / Work In Progress): [MULE Account Enquiry] : Create > Confirm page
- Tested. But found another issue as below
- Disclaimer checkbox display as *checked* if checkbox did not ticked at de... - 14:45 Industry Fraud Bug #11150 (Work Completed-End life cycle): [Committee User Maintenance] : Access to Committee User
- Successfully tested. Thank you.
- 14:42 Industry Fraud Bug #11146 (Development / Work In Progress): [MULE Account Enquiry] : Advance search
- Successfully tested.
Thank you.
Kindly assist to remove random text on screen. - 14:23 0. CDB_Change Request Change #11157 (Development / Work In Progress): [CDB] Change "EPF No" field
- 14:22 0. CDB_Change Request Bug #11155 (Finished Development): [IBAM>Content] Unable to offline content
- 13:22 Industry Fraud Bug #11158: [PARTICIPANTS] : Participant Enquiry > Fraud Email Distribution > Delete
- Please fix for create too.
*Back* button should go back to *Fraud Email Distribution* (Distribution Email Enquiry)... - 12:28 Industry Fraud Bug #11148 (Development / Work In Progress): [Committee User Maintenance] : Email activation not ...
- 12:28 Industry Fraud Bug #11146 (Internal Testing): [MULE Account Enquiry] : Advance search
- Hi Akmal,
Please refer *below* for my reply.
i) Unable to clear field Contact Number and ID Type
*- Fixed done... - 12:25 Industry Fraud Bug #11146 (Development / Work In Progress): [MULE Account Enquiry] : Advance search
- 12:25 Industry Fraud Bug #11150 (Internal Testing): [Committee User Maintenance] : Access to Committee User
- Hi Akmal,
Permission to suspend, activate, reset password had been updated for committee user, please try again. P... - 12:23 Industry Fraud Bug #11150 (Development / Work In Progress): [Committee User Maintenance] : Access to Committee User
- 12:23 Industry Fraud Bug #11151 (Internal Testing): [MULE Account Enquiry] : Create > Confirm page
- Hi Akmal,
The wording and missing checkbox in confirm had been fixed, please try again.
Thank you - 12:22 Industry Fraud Bug #11151 (Development / Work In Progress): [MULE Account Enquiry] : Create > Confirm page
- 12:13 Industry Fraud Bug #11158 (Work Completed-End life cycle): [PARTICIPANTS] : Participant Enquiry > Fraud Email Di...
- *Back* button should go back to *Fraud Email Distribution* screen after successfully deleted email.
+*Step to repr... - 12:12 0. CDB_Change Request Change #11157 (Work Completed-End life cycle): [CDB] Change "EPF No" field
- +Changes at CDB:+
1. Change "EPF No" field to be a default field (unable user to edit)
2. Rename "EPF No" to be "Em... - 11:29 Industry Fraud Bug #11149 (Internal Testing): [PARTICIPANTS] : Participant Enquiry > Fraud Email Distribution > ...
- add duplicate email validation vs db
- 09:49 Industry Fraud Bug #11149: [PARTICIPANTS] : Participant Enquiry > Fraud Email Distribution > Create
- 1. Add checking at Confirm
2. When checker approved, need to check duplicate again. - 09:33 0. CDB_Change Request Bug #11155 (Development / Work In Progress): [IBAM>Content] Unable to offline content
August 23, 2020
- 02:31 1. CDB_Phase 2 & 3 Development Task #10424: [P1_Extended] IOS - CDB_Push Notification for authorization
- Dear Aditya, kindly update the progress of this task.
- 02:30 1. CDB_Phase 2 & 3 Development Task #10425: [P1_Extended] ANDROID - CDB_Push Notification for authorization
- Dear Darren, kindly update the progress of this task.
August 21, 2020
- 17:50 0. CDB_Change Request Bug #11155 (Work Completed-End life cycle): [IBAM>Content] Unable to offline content
- Bug: EPF Other Payment module can still able to access even the status has been changed to "Offline" at IBAM > BBE > ...
- 16:29 0. CDB_Change Request Change #11003 (Internal Testing): [CR19003] : To Add New EPF Payment Type (Late Payment & Dividen)
- Hi Erni,
the deployment has been done. Kindly retest. - 16:07 CR20013 - Change SOCSO Host Transaction Code Task #11153 (Work Completed-End life cycle): [DEV] CR20013 - Change SOCSO Host Transaction Code
- Dear Stephanie,
Kindlhy help to develop this item.
Requirement: https://hub.penril.net/share/s/LQOZXTFFQUywWOXf... - 14:07 0. CDB_Change Request Change #11003 (Finished Development): [CR19003] : To Add New EPF Payment Type (Late Payment & Div...
- Finished development, need to deploy to server for QA testing.
- 12:21 Industry Fraud Bug #11151: [MULE Account Enquiry] : Create > Confirm page
- pls update the text as well... should be "is" instead of "in"
The information provided *is* correct & verified. - 11:59 2. Inhouse Task (Development & QA) Bug #11085 (Work Completed-End life cycle): [Mozilla Firefox] CDB : System does not display Chall...
- Issue has been tested and successfully passed
Thanks Nieza - 11:40 2. Inhouse Task (Development & QA) Bug #11087 (Work Completed-End life cycle): [Mozilla Firefox] IBAM : Organization Code displayed ...
- Issue has been tested and successfully passed.
Thanks Nieza - 10:11 2. Inhouse Task (Development & QA) Bug #11086: [Mozilla Firefox] CDB : System does not remove the deleted file format
- File Format Content IBAM currently using File Type BSNebiz instead of CDB. Therefore, system unable to display all fo...
- 09:58 2. Inhouse Task (Development & QA) Bug #11102 (Work Completed-End life cycle): [IE] IBAM : Message Box_System display the 2nd Page a...
- Issue has been tested and successfully passed
TQ Nieza - 09:37 2. Inhouse Task (Development & QA) Bug #11095 (Work Completed-End life cycle): [IE] IBAM & CDB: Logo BSN does not display
- Logo has been successfully displayed at IBAM
Thanks Nieza. - 09:31 2. Inhouse Task (Development & QA) Bug #11096 (Work Completed-End life cycle): [IE] IBAM : Unable to click at "Home" & "Message Box...
- Issue has been tested and successfully passed
Thanks Nieza - 09:26 2. Inhouse Task (Development & QA) Bug #11103 (Work Completed-End life cycle): [IE] IBAM : Message Box > BSNeBiz Subject Maintenance...
- Issue has been tested and successfully passed
Thanks Nieza - 09:23 2. Inhouse Task (Development & QA) Bug #11097 (Work Completed-End life cycle): [IE] IBAM : Message Box_Select all Checkbox button no...
- Issue has been tested and successfully passed.
Thanks Nieza
August 20, 2020
- 14:28 Agrobank Soft Token 2020 Task #11129 (Finished Development): [DEV] AgroKey Device Pairing - Multiple Device Pairing Error ...
- Patch prepared. Will deploy in SIT environment
- 14:27 Agrobank Soft Token 2020 Task #11128 (Finished Development): [DEV] AgroKey Device Compatibility Information
- Patch prepared. Will deploy in SIT environment
August 19, 2020
- 19:04 KFH Change Request Task #10915: 5370:BNM Requirement to address the SMS OTP TAC fraud - Password Complexity
- added two more field and a page.
corus side development finished.
now starting upass side. - 18:25 Industry Fraud Bug #11151 (Work Completed-End life cycle): [MULE Account Enquiry] : Create > Confirm page
- Disclaimer checkbox missing at Confirm page.
- 18:08 Bandwidth vs Banner Ad Image Task #10936: [DEV] BIB, RIB and IBAM Banner Ad
- Done for IBAM including FTP Module, content(notice), checker maker and RIB to display image using <img src=""> instea...
- 17:48 2. Inhouse Task (Development & QA) Bug #11102 (Internal Testing): [IE] IBAM : Message Box_System display the 2nd Page after click on...
- Hi Erni,
message box pagination list select second page then select the navigation link but display second page not ... - 17:42 2. Inhouse Task (Development & QA) Bug #11103 (Internal Testing): [IE] IBAM : Message Box > BSNeBiz Subject Maintenance_ Able to del...
- Hi Erni,
message box select deselect checkbox able to delete has been updated. Kindly retest. - 17:39 2. Inhouse Task (Development & QA) Bug #11097 (Internal Testing): [IE] IBAM : Message Box_Select all Checkbox button not function
- Hi Erni,
message box select all checkbox function has been updated. Kindly retest. - 17:36 Industry Fraud Bug #11149 (Development / Work In Progress): [PARTICIPANTS] : Participant Enquiry > Fraud Email D...
- 16:50 Industry Fraud Bug #11150 (Work Completed-End life cycle): [Committee User Maintenance] : Access to Committee User
- Currently Committee User only have access to Create, Edit, Delete.
*Expected:*
To have access as per Admin.
To ... - 16:33 Industry Fraud Bug #11149 (Work Completed-End life cycle): [PARTICIPANTS] : Participant Enquiry > Fraud Email Di...
- Able to create duplicate email.
+Expected:+
Hit error
*Email Address already exist.* - 15:18 Industry Fraud Bug #11148 (Work Completed-End life cycle): [Committee User Maintenance] : Email activation not r...
- No email activation received for new created user. (yesterday still OK).
Kindly assist to check.
- 15:10 Industry Fraud Bug #11132 (Work Completed-End life cycle): [Committee User Maintenance] : User Details > To hid...
- Successfully tested. Thank you.
- 15:08 Industry Fraud Bug #11134 (Work Completed-End life cycle): [MULE Account Enquiry] : Create or Edit > Proxy Value...
- Successfully tested. Thank you.
- 15:07 Industry Fraud Bug #11135 (Work Completed-End life cycle): [MULE Account Enquiry] : Name accept all special char...
- Successfully tested. Thank you.
- 15:07 Industry Fraud Bug #11136 (Work Completed-End life cycle): [MULE Account Enquiry] : Fields not mandatory when Ot...
- Successfully tested. Thank you.
- 15:07 Industry Fraud Bug #11137 (Work Completed-End life cycle): [MULE Account Enquiry] : Unable to update record
- Successfully tested. Thank you.
- 15:06 Industry Fraud Bug #11138 (Work Completed-End life cycle): [Committee User Maintenance] : To disable maker/check...
- Successfully tested. Thank you.
- 15:05 Industry Fraud Bug #11146 (Work Completed-End life cycle): [MULE Account Enquiry] : Advance search
- Login: lilyfraud4@mail.com/P@$$w0rd
i) Unable to clear field *Contact Number* and *ID Type*
ii) System did not ... - 14:45 2. Inhouse Task (Development & QA) Bug #11102 (Finished Development): [IE] IBAM : Message Box_System display the 2nd Page after clic...
- 14:02 Industry Fraud Bug #11138 (Internal Testing): [Committee User Maintenance] : To disable maker/checker function
- Hi Akmal,
Checker maker disabled for committee user, please try again.
Thank you - 14:01 Industry Fraud Bug #11138 (Development / Work In Progress): [Committee User Maintenance] : To disable maker/chec...
- 12:51 2. Inhouse Task (Development & QA) Bug #11097 (Finished Development): [IE] IBAM : Message Box_Select all Checkbox button not function
- 10:44 Industry Fraud Bug #11132 (Internal Testing): [Committee User Maintenance] : User Details > To hide Group and Role
- Hi Akmal,
Those field had been remove in Suspend, Delete and activate module. Please try again.
Thank you - 10:43 Industry Fraud Bug #11137 (Internal Testing): [MULE Account Enquiry] : Unable to update record
- Hi Akmal,
Incorrect access function code set in action class. Issue fixed, please try again.
Thank you - 10:42 Industry Fraud Bug #11137 (Development / Work In Progress): [MULE Account Enquiry] : Unable to update record
- 10:42 Industry Fraud Bug #11136 (Internal Testing): [MULE Account Enquiry] : Fields not mandatory when Others selected.
- Hi Akmal,
Validation updated, please try again.
Thank you - 10:41 Industry Fraud Bug #11136 (Development / Work In Progress): [MULE Account Enquiry] : Fields not mandatory when O...
- 10:41 Industry Fraud Bug #11135 (Internal Testing): [MULE Account Enquiry] : Name accept all special character and num...
- Hi Akmal,
Validation updated, please try again.
Thank you - 10:41 Industry Fraud Bug #11135 (Development / Work In Progress): [MULE Account Enquiry] : Name accept all special cha...
- 10:40 Industry Fraud Bug #11134 (Internal Testing): [MULE Account Enquiry] : Create or Edit > Proxy Value accept speci...
- Hi Akmal,
Validation updated, please try again.
Thank you - 10:40 Industry Fraud Bug #11134 (Development / Work In Progress): [MULE Account Enquiry] : Create or Edit > Proxy Valu...
- 10:21 CR19006 - Takaful Kasih Plus (TKP) Task #11144 (Work Completed-End life cycle): [DEV] Takaful Kasih Plus
- Dear Stephanie,
Kindly work on the development.
Thank you. - 10:20 CR19006 - Takaful Kasih Plus (TKP) Task #11143 (Work Completed-End life cycle): [Doc] TSD Takaful Kasih Plus
- Dear Stephanie,
Kindly work on the TSD.
Thank you. - 10:20 CR19006 - Takaful Kasih Plus (TKP) Task #11142 (Closed - End of life cycle): [DOC] FSD Takaful Kasih Plus
- Dear Stephanie,
Kindly work on the FSD.
Thank you.
August 18, 2020
- 17:59 Industry Fraud Bug #11132: [Committee User Maintenance] : User Details > To hide Group and Role
- Check for Activate as well.
- 17:56 Industry Fraud Bug #11132 (Pending Fixes): [Committee User Maintenance] : User Details > To hide Group and Role
- Pls update for Suspend & Delete view as well
Refer attached image - 17:35 2. Inhouse Task (Development & QA) Bug #11103 (Finished Development): [IE] IBAM : Message Box > BSNeBiz Subject Maintenance_ Able to...
- 16:38 Industry Fraud Bug #11138 (Work Completed-End life cycle): [Committee User Maintenance] : To disable maker/check...
- Currently when Committee user perform Committee User Maintenance, result will be "Pending for Approval".
Request to ... - 16:36 Industry Fraud Bug #11137 (Work Completed-End life cycle): [MULE Account Enquiry] : Unable to update record
- # Login as Committee User (lilyfraud4@mail.com/P@$$w0rd)
# Click on MULE Account Enquiry > Show All Pending Records... - 16:04 Industry Fraud Bug #11136 (Work Completed-End life cycle): [MULE Account Enquiry] : Fields not mandatory when Ot...
- *Steps:*
# Select *Modus Operandi* as Others
# Leave blank to *Modus Operandi - Others* field
# Select *Transactio... - 16:02 Industry Fraud Bug #11135 (Work Completed-End life cycle): [MULE Account Enquiry] : Name accept all special char...
- *Expected:*
To hit error: Name cannot include numeric and special characters except space @ ' /
- 16:01 Industry Fraud Bug #11134 (Work Completed-End life cycle): [MULE Account Enquiry] : Create or Edit > Proxy Value...
- *Expected:*
To hit error: 'Proxy Value entered is invalid' - 15:21 Industry Fraud Bug #11118 (Work Completed-End life cycle): Mule Account Enquiry - Search Result should not be cl...
- Successfully tested. Thank you.
- 15:21 Industry Fraud Bug #11117 (Work Completed-End life cycle): Mule Account Enquiry - View Details
- Successfully tested. Thank you.
- 15:20 Industry Fraud Bug #11126 (Work Completed-End life cycle): [MULE Account Enquiry] : Unable to view or edit detai...
- Successfully tested. Thank you.
- 15:20 Industry Fraud Bug #11127 (Work Completed-End life cycle): [MULE Account Enquiry] : Unable to click other naviga...
- Successfully tested. Thank you.
- 15:19 Industry Fraud Bug #11125 (Work Completed-End life cycle): [MULE Account Enquiry] : Table header missing "Action...
- Successfully tested. Thank you.
- 15:19 Industry Fraud Bug #11132 (Work Completed-End life cycle): [Committee User Maintenance] : User Details > To hid...
- Successfully tested. Thank you.
- 15:08 5. Training Compilation Issue Task #10578 (Work Completed-End life cycle): IOS_Add Tnc to Jompay screen
- send to athira and update status
- 15:06 5. Training Compilation Issue Bug #10528 (Work Completed-End life cycle): IOS - Approver List
- 15:02 5. Training Compilation Issue Task #10578: IOS_Add Tnc to Jompay screen
- @najmi this already deliver before first production deployment
- 15:01 5. Training Compilation Issue Bug #10528: IOS - Approver List
- @Athira this arlready deliver before first production deployment
- 14:56 1. CDB_Phase 2 & 3 Development Enhancement #9747 (Internal Testing): UAT_248 - to reposition the drop list for payment type
- @Erni, this is phase-2(to account) for ios and android already delivered to sit
- 14:54 Agrobank Soft Token 2020 Task #11112: [INFO] Need below Information
- 1. check on source code it set support 10. it parameterise can change
2. We dont have list compability Device Model ... - 14:13 Industry Fraud Bug #11117 (Internal Testing): Mule Account Enquiry - View Details
- Hi Akmal,
Issue fixed, please try again.
Thank you - 14:13 Industry Fraud Bug #11117 (Development / Work In Progress): Mule Account Enquiry - View Details
- 14:13 Industry Fraud Bug #11118 (Internal Testing): Mule Account Enquiry - Search Result should not be cleared when us...
- Hi Akmal,
Issue fixed, please try again.
Thank you - 14:12 Industry Fraud Bug #11118 (Development / Work In Progress): Mule Account Enquiry - Search Result should not be c...
- 14:12 Industry Fraud Bug #11127 (Internal Testing): [MULE Account Enquiry] : Unable to click other navigations except ...
- Hi Akmal,
Issue fixed, please try again.
Thank you - 14:12 Industry Fraud Bug #11127 (Development / Work In Progress): [MULE Account Enquiry] : Unable to click other navig...
- 14:12 Industry Fraud Bug #11126 (Internal Testing): [MULE Account Enquiry] : Unable to view or edit details of pending...
- Hi Akmal,
Issue fixed, please try again.
Thank you - 14:11 Industry Fraud Bug #11126 (Development / Work In Progress): [MULE Account Enquiry] : Unable to view or edit deta...
- 14:11 Industry Fraud Bug #11125 (Internal Testing): [MULE Account Enquiry] : Table header missing "Actions" column
- Hi Akmal,
Issue fixed, please try again.
Thank you - 14:10 Industry Fraud Bug #11125 (Development / Work In Progress): [MULE Account Enquiry] : Table header missing "Actio...
- 14:10 Industry Fraud Bug #11132 (Internal Testing): [Committee User Maintenance] : User Details > To hide Group and Role
- Hi Akmal,
Those field had been remove, please try again.
Thank you - 14:09 Industry Fraud Bug #11132 (Development / Work In Progress): [Committee User Maintenance] : User Details > To hi...
- 11:17 Industry Fraud Bug #11132 (Work Completed-End life cycle): [Committee User Maintenance] : User Details > To hid...
- Request to hide *Group* and *Role* in Committee User details as there is no Group and Role for Committee User.
- 11:05 Industry Fraud Bug #11121 (Work Completed-End life cycle): [Committee User Maintenance] : Create > Enter other t...
- Successfully tested.Thank you.
- 11:05 Industry Fraud Bug #11120 (Work Completed-End life cycle): [Committee User Maintenance] : Create > Leave blank
- Successfully tested.Thank you.
- 11:04 Industry Fraud Bug #11119 (Work Completed-End life cycle): [Committee User Maintenance] : Advance search
- Successfully tested.Thank you.
- 11:04 Industry Fraud Bug #11122 (Work Completed-End life cycle): [Committee User Maintenance] : Create > Enter numeric...
- Successfully tested.Thank you.
- 10:16 2. Inhouse Task (Development & QA) Bug #11103 (Development / Work In Progress): [IE] IBAM : Message Box > BSNeBiz Subject Maintenanc...
- 10:09 Industry Fraud Bug #11118: Mule Account Enquiry - Search Result should not be cleared when user click "Back"
- Chee Onn,
Please help with this issue. Thanks.
August 17, 2020
- 18:29 Agrobank Soft Token 2020 Task #11129 (Closed - End of life cycle): [DEV] AgroKey Device Pairing - Multiple Device Pairing ...
- Dear Stephanie,
Kindly assist to add this error message.
1. Device Pairing,
2. Key in username and password,
... - 16:36 Agrobank Soft Token 2020 Task #11128 (Closed - End of life cycle): [DEV] AgroKey Device Compatibility Information
- Dear Stephanie,
Kindly help the AgroKey device compatibility information inside BIB and RIB.
EN:
AgroKey for i... - 15:28 Agrobank Soft Token 2020 Task #11115 (System Integration Test): [DEV] AgroKey Device Pairing - Maximum License Reached Err...
- Deploy to SIT and UAT environment.
- 15:25 CR19002 - IBAM Enhancement CMS Task #10958 (Pending Prod Deployment): [DEV] Annual Fee Cron Job
- 15:18 Industry Fraud Bug #11122 (Internal Testing): [Committee User Maintenance] : Create > Enter numeric to Name
- Hi Akmal,
Issue fixed, please try again after deployment done by today.
Thank you - 15:17 Industry Fraud Bug #11122 (Development / Work In Progress): [Committee User Maintenance] : Create > Enter numeri...
- 15:03 Industry Fraud Bug #11127 (Work Completed-End life cycle): [MULE Account Enquiry] : Unable to click other naviga...
- +*Steps:*+
# Login as Participant user.
# Click on INDUSTRIAL FRAUD PORTAL > MULE Account Enquiry
# Click on "Sh... - 15:01 Industry Fraud Bug #11126 (Work Completed-End life cycle): [MULE Account Enquiry] : Unable to view or edit detai...
- +*Steps:*+
# Login as Participant user. (PUMlilyfraud@mail.com / P@$$w0rd)
# Click on INDUSTRIAL FRAUD PORTAL > MUL... - 14:59 Industry Fraud Bug #11125 (Work Completed-End life cycle): [MULE Account Enquiry] : Table header missing "Action...
- *+Steps:+*
# Login as Participant user.
# Click on INDUSTRIAL FRAUD PORTAL > MULE Account Enquiry
# Click on "Show... - 14:44 New IB SMS Solution Task #11113: [Performance Test] Perform Load Test
- JMeter Load Test
1. Concurrent users login: 30 users. Loop: 4 times. Total requests: 120
2. Tested via external n... - 14:38 Industry Fraud Bug #11124 (Work Completed-End life cycle): [Committee User Maintenance] : Unable to activate user
- Tested and passed. Successfully activate user and login.
Thank you. - 14:37 Industry Fraud Bug #11123 (Work Completed-End life cycle): [Committee User Maintenance] : Create > Missing fields
- Issue dropped.
- 14:32 Industry Fraud Bug #11124 (Internal Testing): [Committee User Maintenance] : Unable to activate user
- Hi Akmal,
This issue due to activate url configuration incorrect. I just change the url settings and restart the a... - 13:35 Industry Fraud Bug #11124 (Development / Work In Progress): [Committee User Maintenance] : Unable to activate user
- 13:35 Industry Fraud Bug #11123 (Internal Testing): [Committee User Maintenance] : Create > Missing fields
- Hi Akmal,
FSD document not updated, the field in current system is correct.
Thank you - 13:34 Industry Fraud Bug #11119 (Internal Testing): [Committee User Maintenance] : Advance search
- Hi Akmal,
Issue fixed, please try again after deployment done by today.
Thank you - 13:33 Industry Fraud Bug #11119 (Development / Work In Progress): [Committee User Maintenance] : Advance search
- 13:33 Industry Fraud Bug #11120 (Internal Testing): [Committee User Maintenance] : Create > Leave blank
- Hi Akmal,
Validation fixed, please try again after deployment done by today.
Thank you - 13:32 Industry Fraud Bug #11120 (Development / Work In Progress): [Committee User Maintenance] : Create > Leave blank
- 13:32 Industry Fraud Bug #11121 (Internal Testing): [Committee User Maintenance] : Create > Enter other than numeric t...
- Hi Akmal,
Validation fixed, please try again after deployment done by today.
Thank you - 13:31 Industry Fraud Bug #11121 (Development / Work In Progress): [Committee User Maintenance] : Create > Enter other ...
- 11:20 Industry Fraud Bug #11124 (Work Completed-End life cycle): [Committee User Maintenance] : Unable to activate user
- +*Scenario:*+
# Successfully create Committee user.
# Received notification email.
# Click on Email activation lin... - 11:13 Industry Fraud Bug #11123: [Committee User Maintenance] : Create > Missing fields
- Pls follow the system.
FSD not updated. Sorry.
- 11:04 Industry Fraud Bug #11123 (Work Completed-End life cycle): [Committee User Maintenance] : Create > Missing fields
- +*Current system:*+
* User ID
* Name
* Office No
* Mobile No
* Email
+
*Requirement in FSD:*+
* User Name
... - 10:52 Industry Fraud Bug #11122 (Work Completed-End life cycle): [Committee User Maintenance] : Create > Enter numeric...
- Scenario: Enter numeric to *Name*
Actual result:
System accept numeric at Name
Expected result:
System throw... - 10:51 Industry Fraud Bug #11121 (Work Completed-End life cycle): [Committee User Maintenance] : Create > Enter other t...
- Scenario: Enter special characters and alpahbets to *Office No* and *Mobile No*
Actual result:
Successfully cre... - 10:50 Industry Fraud Bug #11120 (Work Completed-End life cycle): [Committee User Maintenance] : Create > Leave blank
- Scenario: Leave blank to field *User ID*
Error: User Name is required
Expected: User ID is required - 10:49 Industry Fraud Bug #11119 (Work Completed-End life cycle): [Committee User Maintenance] : Advance search
- Unable to "Clear" fields User Created Date From & User Created Date To
- 10:14 Industry Fraud Bug #11118 (Work Completed-End life cycle): Mule Account Enquiry - Search Result should not be cl...
- After view details, user click "Back". The previous search result should remain.
Steps to replicate
1. Go to Mul... - 09:51 Industry Fraud Bug #11117 (Work Completed-End life cycle): Mule Account Enquiry - View Details
- Have gap in the view, see attached image
August 14, 2020
- 18:51 New IB SMS Solution Task #11114: [Performance Test] Perform Stress Test
- 27 users, 30 secs ramp-up period, and Infinite loop count, stop when hit error
Num of request before hits error:
i... - 16:08 Agrobank Soft Token 2020 Task #11115 (Closed - End of life cycle): [DEV] AgroKey Device Pairing - Maximum License Reached ...
- Dear Stephanie,
As per proposed by Mr. Tan, you may follow this error message format. I will inform Nasyran, about... - 15:38 New IB SMS Solution Task #11114 (New - Begin Life Cycle): [Performance Test] Perform Stress Test
- Dear Yaya,
Kindly help to update this task and attach the result document.
Thank you. - 15:37 New IB SMS Solution Task #11113 (New - Begin Life Cycle): [Performance Test] Perform Load Test
- Dear Yaya,
Understood the load test has been done. Kindly help to update this task and attach the document.
Tha... - 15:26 Agrobank Soft Token 2020 Task #11112 (Closed - End of life cycle): [INFO] Need below Information
- Dear Adit,
Please help to provide below information:
*Mobile Token:*
1. Maximum number of users that can login... - 10:14 2. Inhouse Task (Development & QA) Bug #11095 (Internal Testing): [IE] IBAM & CDB: Logo BSN does not display
- Hi Erni,
the issue has been updated. Kindly retest. - 10:13 2. Inhouse Task (Development & QA) Bug #11096 (Internal Testing): [IE] IBAM : Unable to click at "Home" & "Message Box" navigation
- Hi Erni,
the issue has been updated. Kindly retest. - 09:44 2. Inhouse Task (Development & QA) Bug #11107 (Rejected - End of life cycle): [IE] IBAM : Organization Setup > Account Management_Pr...
- Unable to replicate the issue
August 13, 2020
- 18:01 2. Inhouse Task (Development & QA) Bug #11107 (Rejected - End of life cycle): [IE] IBAM : Organization Setup > Account Management_Pr...
- Bug: CSS displayed incorrectly at this page
Path: IBAM > CBE > Organization Setup > Account Management > Edit > Co... - 10:11 KFH Projects Task #10595 (Work Completed-End life cycle): [RPP Phase 2] CMS NAD Maintenance - Authorization Mo...
- Development done.
- 09:57 KFH Projects Task #9860 (Work Completed-End life cycle): IBSCR113 RPP : Screen development
- Development done.
- 09:53 2. Inhouse Task (Development & QA) Bug #11102 (Development / Work In Progress): [IE] IBAM : Message Box_System display the 2nd Page ...
- 09:52 2. Inhouse Task (Development & QA) Bug #11087 (Internal Testing): [Mozilla Firefox] IBAM : Organization Code displayed at CDB does n...
- Hi Erni,
the double org code display at CDB has been updated. Kindly retest. - 09:50 2. Inhouse Task (Development & QA) Bug #11087 (Finished Development): [Mozilla Firefox] IBAM : Organization Code displayed at CDB do...
August 12, 2020
- 16:13 2. Inhouse Task (Development & QA) Bug #11096 (Finished Development): [IE] IBAM : Unable to click at "Home" & "Message Box" navigation
- 16:12 2. Inhouse Task (Development & QA) Bug #11095 (Finished Development): [IE] IBAM & CDB: Logo BSN does not display
- 15:33 2. Inhouse Task (Development & QA) Bug #11103 (Work Completed-End life cycle): [IE] IBAM : Message Box > BSNeBiz Subject Maintenance...
- Bug: Able to delete category without select any category
Path: IBAM > Message Box > BSNeBiz Subject Maintenance > ... - 15:12 0. CDB_Change Request Change #11003: [CR19003] : To Add New EPF Payment Type (Late Payment & Dividen)
- Chee Ping, FSD for CR_EPF Other Payment as per link. Erni with liaise with you to update on the screen required. TQ
... - 15:04 2. Inhouse Task (Development & QA) Bug #11102 (Work Completed-End life cycle): [IE] IBAM : Message Box_System display the 2nd Page a...
- Bug: System display the 2nd Page instead of 1st Page after click on BSNeBiz Subject Maintenance
Path: IBAM > Messa... - 15:00 0. CDB_Change Request Task #11101 (Work Completed-End life cycle): [CR19003] : [MOBILE ANDROID] To Add New EPF Payment ...
- New Payment type
1. Late Payment
2. Dividen
Refer log 11003.
- 15:00 0. CDB_Change Request Task #11100 (Work Completed-End life cycle): [CR19003] : [MOBILE IOS] To Add New EPF Payment Type...
- New Payment type
1. Late Payment
2. Dividen
Refer log 11003.
- 12:37 2. Inhouse Task (Development & QA) Bug #11086 (Internal Testing): [Mozilla Firefox] CDB : System does not remove the deleted file fo...
- Hi Erni,
CDB Enrollment does not remove the deleted file format has been updated. Kindly retest. - 11:29 2. Inhouse Task (Development & QA) Bug #11097 (Work Completed-End life cycle): [IE] IBAM : Message Box_Select all Checkbox button no...
- Bug : Select all checkbox button unable to select all available recipient
Path :
1) IBAM > Message Box > Send Ne... - 10:55 2. Inhouse Task (Development & QA) Bug #11096 (Work Completed-End life cycle): [IE] IBAM : Unable to click at "Home" & "Message Box...
- **Bug: "Home" & "Message Box" navigation is not function when arrow at the wording
- 10:18 2. Inhouse Task (Development & QA) Bug #11095 (Work Completed-End life cycle): [IE] IBAM & CDB: Logo BSN does not display
- Bug: System does not display BSN logo at IBAM & CDB. Refer attachment for details
Also available in: Atom