Activity

From October 08, 2013 to November 06, 2013

November 06, 2013

15:36 Maybank RCAS Indonesia Development Task #3699 (Work Completed-End life cycle): Nov Roll out: Audit Log
Retested successfully. Hosseiny Elham
15:01 Maybank RCAS Indonesia Development Bug #3909 (Work Completed-End life cycle): Audit Log
Fixed and retested successfully. Hosseiny Elham
14:50 Maybank RCAS Indonesia Development Bug #3909 (Finished Development): Audit Log
Changed the header of Audit Log PDF file from "BII RCAS SYSTEM" to "BII Audit Log Report". Please retest. Ting Wei Gan
12:19 Maybank RCAS Indonesia Development Bug #3909 (Work Completed-End life cycle): Audit Log
Kindly assist to fix it.
Click on "Audit log".
Click on "Pdf".
Actual Result:
"BII RCAS SYSTEM" written as ...
Hosseiny Elham
11:18 Maybank RCAS Indonesia Development Task #3730 (Finished Development): Nov roll out: Admin User maintenance: List of user id, dormant...
Changes done:
1. Added the function of exporting to Excel or PDF for admin user search result.
2. Added extra col...
Ting Wei Gan

November 01, 2013

17:23 Maybank RCAS Indonesia Development Bug #3908 (Work Completed-End life cycle): Admin Navigation
Kindly assist to fix it .
# Click on "Maintenance "
# Click on "Create Provider"
# key in "Provider"
# Select "...
Hosseiny Elham

October 31, 2013

17:13 Maybank RCAS Indonesia Development Bug #3902 (Work Completed-End life cycle): Admin User maintenance
After double check with Lee Lee , User ID Max length is 25 characters. Hosseiny Elham
16:40 Maybank RCAS Indonesia Development Bug #3902 (Work Completed-End life cycle): Admin User maintenance
Kindly assist to fix it .
# Click on “Admin user Maintenance”
# Click on “Admin Search “
# Key in “User ID” more...
Hosseiny Elham
12:59 Maybank RCAS Indonesia Development Task #3732 (Development / Work In Progress): Nov Roll out: Token Listing - Global and Provider
Hosseiny Elham
12:56 Maybank RCAS Indonesia Development Bug #3901 (Work Completed-End life cycle): Token Listing - Global and Provider
Kindly assist to fix it.
# Click on “Token Management”
# Click on “Token Listing”
# Tick on Global radio button...
Hosseiny Elham
11:11 Maybank RCAS Indonesia Development Bug #3899 (Work Completed-End life cycle): Nov roll out: Admin User maintenance
kindly assist to solve it .
# Click on “Admin User Maintenance”
# Click on Admin Search .
# Click any User ID h...
Hosseiny Elham

October 29, 2013

14:47 Maybank RCAS ID SIT/UAT Bug #3842 (Closed - End of life cycle): Bii:UAT- Defect ID 676 Sev 3 : The pin letter back to the...
The pin letter back to the old one, still use Maybank2E & printed in 2 page.
23 Oct: Release 00029
25 Oct: Releas...
Ting Wei Gan

October 28, 2013

16:56 Maybank RCAS Indonesia Development Task #3783 (Development / Work In Progress): User Linking: webservice client
Completed:
1. Add web service client project, rcasws-client. This web service client configuration is configurable a...
Anwar Khairul
16:56 Maybank RCAS Indonesia Development Task #3732: Nov Roll out: Token Listing - Global and Provider
Hi Elham
please assist on the internal testing.
Anonymous
16:36 Maybank RCAS Indonesia Development Task #3730: Nov roll out: Admin User maintenance: List of user id, dormant id, search result list...
pls refer to FSD 1.3 for latest changes Anonymous
16:21 Maybank RCAS Indonesia Development Task #3732 (Internal Testing): Nov Roll out: Token Listing - Global and Provider
Hi Ting Wei,
Need your assistant to test this module. Because last week the server down for the whole day. So I on...
Zayani Zakaria
16:19 Maybank RCAS Indonesia Development Task #3732 (Finished Development): Nov Roll out: Token Listing - Global and Provider
Zayani Zakaria
16:18 Maybank RCAS Indonesia Development Task #3732: Nov Roll out: Token Listing - Global and Provider
Solution :
Add Radio button - Add new function based on Javascript and ajax to switch the screen between global an...
Zayani Zakaria
16:12 Maybank RCAS Indonesia Development Task #3732 (Development / Work In Progress): Nov Roll out: Token Listing - Global and Provider
Zayani Zakaria
14:04 Maybank RCAS Indonesia Development Bug #3830 (Work Completed-End life cycle): Nov Roll out: Audit Log
It has been fixed .and retested succesfully. Hosseiny Elham
12:13 Maybank RCAS ID SIT/UAT Bug #3835 (Work Completed-End life cycle): Bii:UAT- Defect ID 658 Sev 1 : Once click print system...
Once click print system display error message
Error while performing your request. Service is currently unavailable....
Ting Wei Gan
12:04 Maybank RCAS ID SIT/UAT Bug #3834 (Closed - End of life cycle): Bii:UAT- Defect ID 626 Sev 3 : Reset password through RCM...
Reset password through RCMS and choose email. Waiting for 15mins. still not receive any email.
The email address is ...
Ting Wei Gan

October 25, 2013

16:09 Maybank RCAS Indonesia Development Task #3699 (Development / Work In Progress): Nov Roll out: Audit Log
Hosseiny Elham
16:08 Maybank RCAS Indonesia Development Bug #3830 (Work Completed-End life cycle): Nov Roll out: Audit Log
Kindly assist to fix it.
# Click on Audit Log.
# Click on Search Button.
*Actual result:*
System just shows B...
Hosseiny Elham
14:57 Maybank RCAS Indonesia Development Bug #3829 (Work Completed-End life cycle): Maybank RCAS Indonesia - Login
Fixed. Hosseiny Elham
14:39 Maybank RCAS Indonesia Development Bug #3829 (Work Completed-End life cycle): Maybank RCAS Indonesia - Login
kindly assist to solve the bug ,
username: casadmin
password:
# Key in "User ID".
# Key in "Password".
# Clic...
Hosseiny Elham

October 23, 2013

13:57 RCAS ID Deployment Task #3823 (Closed - End of life cycle): RCAS ID: Prepare the RCAS ID Checklist
Please update the provide doc, update or response to rradhiah.r@maybank.com.my for any concern, missing items or high... Tan Lee Yong

October 18, 2013

17:37 Maybank RCAS Indonesia Development Task #3699: Nov Roll out: Audit Log
Elham, pls refer to fsd version 1.2 for the finalized requirement to perform the testing. Anonymous
14:31 Maybank RCAS Indonesia Development Task #3699: Nov Roll out: Audit Log
Ting wei,
May you assign to others people to test or may assign to boby to check and closed for deployment.
Man Siew Yong
14:20 Maybank RCAS ID SIT/UAT Bug #3810 (Finished Development): Global: UAT: For provider scroll bar, pls make it wider a bit.
Problem only exists in IE7. Remove the use of sexy-combo. Ting Wei Gan
11:41 Maybank RCAS Indonesia Development Task #3699 (Internal Testing): Nov Roll out: Audit Log
Added export excel and PDF function. Please test. Ting Wei Gan
11:34 Maybank RCAS Indonesia Development Task #3699 (Finished Development): Nov Roll out: Audit Log
Ting Wei Gan
11:29 Maybank RCAS ID SIT/UAT Bug #3810 (Closed - End of life cycle): Global: UAT: For provider scroll bar, pls make it wider a...
For provider scroll bar, pls make it wider a bit. refer to the defect log for the screen capture. Anonymous
09:24 Maybank RCAS Indonesia Development Task #3699 (Development / Work In Progress): Nov Roll out: Audit Log
Ting Wei Gan

October 16, 2013

11:45 Maybank RCAS Indonesia Development Task #3533 (Development / Work In Progress): Syncronisation between RCAS Global/MY and RCAS ID: R...
Hartanto Boby
11:42 Maybank RCAS Indonesia Development Task #3542 (Finished Development): Deployment services:
Hartanto Boby
11:37 Maybank RCAS Indonesia Development Task #3783: User Linking: webservice client
to work with Boby on task 3539 and call the api for task 3539. Anonymous
11:34 Maybank RCAS Indonesia Development Task #3783 (Closed - End of life cycle): User Linking: webservice client
Anonymous
11:05 Maybank RCAS Indonesia Development Task #3518 (Finished Development): RCAS Phase 4 - FSD and SDS
Anonymous
10:58 Maybank RCAS Indonesia Development Task #3558 (Rejected - End of life cycle): Password Expiry Notification
50% completion. Client not require this item. Anonymous
10:45 Maybank RCAS Indonesia Development Task #3541 (Work Completed-End life cycle): RCAS Functional Training preparation
Anonymous

October 14, 2013

14:37 Maybank RCAS ID SIT/UAT Bug #3670 (Closed - End of life cycle): Bii:UAT- Defect ID 157 Sev 2 : password expiry
8 Oct: User retest done Man Siew Yong
14:34 Maybank RCAS ID SIT/UAT Bug #3693 (Closed - End of life cycle): Bii:UAT- Defect ID 151 Sev 2 : Already assigned some tok...
11 OCT: Release 00022 User retest done Man Siew Yong
12:28 Maybank RCAS ID SIT/UAT Bug #3776 (Rejected - End of life cycle): Bii:UAT- Defect ID 566 Sev 2 : prebind 6 tokens. no to...
1. already prebind 6 tokens
2. click on "reissue token"
3. click on "prebind token"
4. no tokens listed out
D...
Man Siew Yong
12:26 Maybank RCAS ID SIT/UAT Bug #3775 (Closed - End of life cycle): Bii:UAT- Defect ID 565 Sev 2 : Bind Token from Pre-Bind ...
Bind Token from Pre-Bind Token listing.
Logon to IDMCD.
Already prebind / bokked 1 token for IDMCD. Token serial...
Man Siew Yong
12:24 Maybank RCAS ID SIT/UAT Bug #3774 (Closed - End of life cycle): Bii:UAT- Defect ID 564 Sev 3 : Pre-bind token / Token Re...
Man Siew Yong
12:22 Maybank RCAS ID SIT/UAT Bug #3773 (Closed - End of life cycle): Bii:UAT- Defect ID 555 Sev 1 : Unable to login to RCAS P...
Man Siew Yong
12:14 Maybank RCAS ID SIT/UAT Bug #3772 (Closed - End of life cycle): Bii:UAT- Defect ID 507 Sev 2 : There is no logout button...
10 Oct: Fixed by Anwar. Release 00022
11 Oct: User retest done
Man Siew Yong
12:11 Maybank RCAS ID SIT/UAT Bug #3771 (Closed - End of life cycle): Bii:UAT- Defect ID 501 Sev 3 : BBO users created before...
My 2 BBO users created before was not found in RCAS.
1. SUPERUSER
2. TESTING01
Pls fix and explain why.
10 Oc...
Man Siew Yong
12:06 Maybank RCAS ID SIT/UAT Bug #3770 (Closed - End of life cycle): Both: UAT-Defect ID 500 Ser 4: RCAS : Maintenance : Why ...
10 Oct: Fixed by Boby. Release 00021
11 Oct: User retest Done
Man Siew Yong
12:02 Maybank RCAS ID SIT/UAT Bug #3769 (Closed - End of life cycle): Bii:UAT- Defect ID 481 Sev 1 : Print new pin mailer pass...
Print new pin mailer password today. All blank, no password, date & time etc.
Corp ID: IDMCD
User Name: Shital
...
Man Siew Yong
11:58 Maybank RCAS ID SIT/UAT Bug #3768 (Closed - End of life cycle): Both: SIT-Defect ID 92 Ser 1: Fail - System error cannot ...
Boby : User assign a token to user which is not assign to any provider yet. Man Siew Yong
11:55 Maybank RCAS ID SIT/UAT Bug #3767 (Closed - End of life cycle): Both: UAT-Defect ID 420 Ser 3: Token Listing report.
Token Listing report.
The status is not mandatory, pls remove the symbol '*'.
Search Provider Indonesia without s...
Man Siew Yong
11:48 Maybank RCAS ID SIT/UAT Bug #3766 (Rejected - End of life cycle): Both: UAT-Defect ID 344 Ser 2: Force change password,sy...
Step to reproduce
1. login to cfo with 1st time user id
2. enter token serial no and 1st time otp
3. Fill old with...
Man Siew Yong
11:36 Maybank RCAS ID SIT/UAT Bug #3765 (Closed - End of life cycle): Bii:UAT- Defect ID 272 Sev 2 : password generated at pi...
There is 3 issues for password generated at pinmailer
1. Password not align properly inside the box
2. Date & Tim...
Man Siew Yong
10:50 Maybank RCAS ID SIT/UAT Bug #3674 (Closed - End of life cycle): UAT-Defect ID 222 Ser 2: Login in RCMS. Not prompt to cha...
9 Oct : Closed by user Man Siew Yong

October 10, 2013

18:54 Maybank RCAS ID SIT/UAT Bug #3665 (Finished Development): Bii:UAT- Defect ID 140 Sev 4 : CR item 1 and 3
Completed for pinLetter as well. Anwar Khairul

October 08, 2013

19:52 Maybank RCAS ID SIT/UAT Bug #3665 (Development / Work In Progress): Bii:UAT- Defect ID 140 Sev 4 : CR item 1 and 3
Completed for all email. The setting value for sender and subject is configurable at upass.cfg.
Pending for pin le...
Anwar Khairul
16:40 Maybank RCAS ID SIT/UAT Bug #3631 (Closed - End of life cycle): UAT-Defect ID 115: Cosmetic issue detected in Google Chro...
05 Oct: User Closed the issue Man Siew Yong
16:39 Maybank RCAS ID SIT/UAT Bug #3650 (Closed - End of life cycle): UAT-Defect ID 56: Some HTML tags show in email body. Tag:...
Man Siew Yong
15:00 Maybank RCAS Indonesia Development Task #3730: Nov roll out: Admin User maintenance: List of user id, dormant id, search result list...
pls branch out. Anonymous
14:59 Maybank RCAS Indonesia Development Task #3732 (Work Completed-End life cycle): Nov Roll out: Token Listing - Global and Provider
'- to add new label: search Global or provider
If select Global, then the provider label will be remove, Status : As...
Anonymous
14:54 Maybank RCAS Indonesia Development Task #3699: Nov Roll out: Audit Log
New requirement. pls refer to FSD ver 1.1. Anonymous
14:53 Maybank RCAS Indonesia Development Task #3730 (Work Completed-End life cycle): Nov roll out: Admin User maintenance: List of user id...
- List of User id and system admin log - can get the list of user id by not select any search criteria.
- List of Do...
Anonymous
14:46 Maybank RCAS ID SIT/UAT Bug #3649 (Internal Testing): Nov roll out: UAT-Defect ID 55 Ser 3
Hi Man Siew, please assist to perform internal testing. We will not release this item in this Oct, we will release in... Anonymous
12:36 Maybank RCAS ID SIT/UAT Bug #3665: Bii:UAT- Defect ID 140 Sev 4 : CR item 1 and 3
pls work with Boby of the final requirement. Anonymous
 

Also available in: Atom