January 02, 2015
- 16:18 Maybank - IndoChina + Future enhancement Task #4787: Email and SMS – Add Reference #
- RCAS FSD R1 ver 1.3 already sign off for this item.
- 16:17 Maybank - IndoChina + Future enhancement Task #4788: Prebind Token by Count
- RCAS FSD R1 ver 1.3 already sign off for this item.
- 16:15 Maybank - IndoChina + Future enhancement Task #5097 (Closed - End of life cycle): Timezone Editable and view
- Requirement:
1. allow to change the Timezone after submitted.
2. able to see a list of country with the timezone as... - 16:03 Maybank - IndoChina + Future enhancement Task #4573: Change Length
- requirement confirmed and FSD sign off under RCAS FSD R1 ver 1.3.
need to prepare new quotation and sow when the tim... - 15:51 Maybank - IndoChina + Future enhancement Task #4787: Email and SMS – Add Reference #
- quotation prepared b4 and cancelled. Need to prepare new quotation and sow when the delivery timeframe confirm.
- 15:49 Maybank - IndoChina + Future enhancement Task #4788: Prebind Token by Count
- quotation prepared before and has been cancelled. need to prepare new quotation and SOW but not sure the timeline, so...
- 15:48 Maybank - IndoChina + Future enhancement Task #4788: Prebind Token by Count
- enhancement requested during R2 but due to eBwork can not delivery in R2 and requested to implement it in future.
December 31, 2014
- 14:48 Maybank - IndoChina + Future enhancement Task #4788: Prebind Token by Count
- R2 already went live, is this item still on?
December 19, 2014
- 15:17 Maybank RCAS - Production (Joanne Request) - Development Task #4549: April: Joanne Request: RCAS--> Token Listing-->add Date Assigned from and Date Assign...
- pending PO to issue in Dec 2014. Since no PO, we did not release.
- 15:17 Maybank RCAS - Production (Joanne Request) - Development Task #4548: April: Joanne Request:RCAS--> Token Listing-->add Total Token
- pending PO to issue in Dec 2014. Since no PO, we did not release.
- 15:17 Maybank RCAS - Production (Joanne Request) - Development Task #4547: April: Joanne Request: Token Cover Letter
- pending PO to issue in Dec 2014. Since no PO, we did not release.
- 15:16 Maybank RCAS - Production (Joanne Request) - Development Task #4546: April: Joanne Request: Token Cover Letter - Provider
- pending PO to issue in Dec 2014. Since no PO, we did not release.
- 15:16 Maybank RCAS - Production (Joanne Request) - Development Task #4545: April: Joanne Request: Token Cover Letter Reprint
- pending PO to issue in Dec 2014. Since no PO, we did not release.
- 15:15 Maybank/Bii - RCAS - RCMS SIT/UAT support Bug #4562 (Work Completed-End life cycle): Email subject: Bii team: error while performing your r...
- released to Bank
- 15:14 Maybank RCAS Indonesia Development Task #3537: HSM - round robin
- not yet. we need them to setup the development for Penril to do the development work and testing since Penril do not ...
- 14:28 Maybank/Bii - RCAS - RCMS SIT/UAT support Bug #4562: Email subject: Bii team: error while performing your request after login rcas app
- what is the update on this?
- 14:27 Maybank RCAS Indonesia Development Task #3537: HSM - round robin
- Is this done?
December 18, 2014
- 16:38 Maybank RCAS - Production (Joanne Request) - Development Task #5080: Token Cover Letter - Timezone
- Stephanie, please get help from Wei Kuan.
- 16:34 Maybank RCAS - Production (Joanne Request) - Development Task #5080 (Closed - End of life cycle): Token Cover Letter - Timezone
- To add Timezone for those impacted module, pls refer to FSD 1.3