November 18, 2013
- 17:01 Maybank Bii Internet Banking Phase 2 UAT Task #3948: Update MSS
- Amy is working on the BRS about this item to confirm with customer on the agree implementation approach
- 16:56 Maybank Bii Internet Banking Phase 2 UAT Task #3948 (Closed - End of life cycle): Update MSS
- In Indonesia, a lot of customer are using prepaid mobile number. Meaning, they always need to change their mobile num...
- 16:25 Task #3945 (Closed - End of life cycle): BII RIB: Forgot Password & Security Answer
- If user forgot both the password and security answer, user is required to call bank back office. Bank back office wil...
- 15:54 Task #3508 (Work Completed-End life cycle): To add 1 more item (Terminated) under the drop down l...
- Deployed to production
- 15:49 Task #3479 (User Acceptance Test): User Migration
- 15:47 Task #3483 (User Acceptance Test): Requested to remove the footer:About Us | Branches/ATM | Caree...
- 15:46 Task #3463 (User Acceptance Test): SI
- 15:45 Task #3490 (User Acceptance Test): User migration: Phone # and Email address
- 15:45 Task #3467 (User Acceptance Test): Biller Reconciliation
- 15:44 Task #3475 (User Acceptance Test): Data warehouse report
- 15:44 Task #3488 (User Acceptance Test): SKN/RTGS: add 2nd charges in MSS
- 15:44 Task #3493 (User Acceptance Test): Currency Code Create, Edit, and Details page
- 15:43 Task #3489 (User Acceptance Test): FCR: changes the MT103 message and value X & XXX
- 15:42 Task #3484 (User Acceptance Test): FTL: Change email length from 30 to 40 chars.
- 15:42 Task #3470 (User Acceptance Test): Monthly report (refer to new format)
- 15:41 RIB Phase 2 Development Task #3492 (User Acceptance Test): RIB: Bill Payment > Mobile Postpaid.
- 15:39 Task #3486 (User Acceptance Test): TAC pop up windows
November 11, 2013
- 14:13 Task #3481 (User Acceptance Test): Change Previous 1 month transaction to 3 months transaction
- 12:38 Task #3482 (User Acceptance Test): Change Default language
- 11:15 Task #3478 (User Acceptance Test): Change Password max length
- 11:14 Task #3476 (User Acceptance Test): Today's Transaction - kolom Balance
- 11:13 Task #3475 (Pending UAT Deployment): Data warehouse report
- 11:13 Task #3473 (User Acceptance Test): Requested the longer Benefinary name and message
- 11:11 RIB Phase 2 Development Task #3469 (User Acceptance Test): Exchange Rate (all items hv foreign currency involved)
- 11:11 RIB Phase 2 Development Task #3468 (User Acceptance Test): Bill payment - Oustanding payment request
- 11:11 Task #3467 (Pending UAT Deployment): Biller Reconciliation
- 11:10 Task #3462 (User Acceptance Test): Credit Card Statement Download
- 11:10 Task #3460 (User Acceptance Test): LLD report
- 11:05 Task #3496 (User Acceptance Test): To change My Plan Account (8XXXXXXXXX) flow
- 11:05 Task #3497 (User Acceptance Test): Fund Transfer > FCR
- 11:05 RIB Phase 2 Development Task #3498 (User Acceptance Test): email notification: sending to Beneficiary email if a valid em...
- 11:04 Task #3499 (User Acceptance Test): BII Credit Card : add "PAY" button
- 11:04 Task #3501 (User Acceptance Test): Interbank Online: To add "reference no"
- 11:04 Task #3506 (User Acceptance Test): Change TAC notification message
- 11:04 Task #3507 (User Acceptance Test): Change the alignment of right buttons
- 11:04 RIB Phase 2 Development Task #3510 (User Acceptance Test): Link/Unlink Account page:allow the customer select the account...
- 11:03 Maybank Bii Internet Banking Phase 2 SIT Bug #3720 (User Acceptance Test): 16.Today's Transaction - kolom Balance, why all zero?
- 11:03 Maybank Bii Internet Banking Phase 2 SIT Task #3721 (User Acceptance Test): 34.Fund Transfer > FCR: Transfer to Yen Account shall not allo...
- 11:03 Maybank Bii Internet Banking Phase 2 SIT Task #3735 (User Acceptance Test): Credit Card Statement
- 10:46 Task #3479 (Pending SIT Deployment): User Migration
- 10:42 Maybank Bii Internet Banking Phase 2 SIT Bug #3719 (User Acceptance Test): 6:sent item (Send box)
- 10:40 Task #3471 (User Acceptance Test): Trf SKN/LLG List Destination Bank
November 08, 2013
- 17:04 Task #3467 (Finished Development): Biller Reconciliation
- Development done according to new requirement.
Thank you. - 12:32 Task #3462 (Finished Development): Credit Card Statement Download
- Finished the download function to call their http post.
November 07, 2013
- 17:27 Task #3463: SI
- Add one more script to update IB_NAVIGATION table.
Thank you - 17:07 Task #3463 (Finished Development): SI
- Development done for SI service and pushed to mercurial with add "common-si" project for this service.
Please refe... - 16:58 Task #3463 (Development / Work In Progress): SI
- 16:48 Task #3912 (Closed - End of life cycle): Create HTML demo for Both RIB & MSS
- Create HTML demo for Both RIB & MSS
November 04, 2013
- 14:38 Maybank BII Internet Banking Phase 3 Task #3466: FD withdrawal-change flow
- FD Withdrawal to be moved to Phase 3
- 14:37 Task #3472 (User Acceptance Test): employee account for SKN/RTGS transaction
- 14:36 Task #3474 (User Acceptance Test): Foreign Currency : Transaksi Valas - 3 charges (charges 1,2, p...
- 14:35 RIB Phase 2 Development Task #3465 (User Acceptance Test): sent item (Send box)
- 14:29 RIB Phase 2 Development Task #3500 (User Acceptance Test): M2U Receipt : Reduce font size
- 14:28 RIB Phase 2 Development Task #3502 (User Acceptance Test): User migration: To change the current migration progress by hi...
- 14:27 RIB Phase 2 Development Task #3503 (User Acceptance Test): Joint account: not allow to show in account & summary and Link...
- 14:27 RIB Phase 2 Development Task #3504 (User Acceptance Test): Loan Account:show details information
- 14:27 RIB Phase 2 Development Task #3505 (User Acceptance Test): Loan Account : Do not show Loan Account which is fully paid
- 14:26 Task #3509 (User Acceptance Test): To change the MT103 message for FCR's Mt103RECVBIC (table) Mt1...
- 14:22 Maybank Bii Internet Banking Phase 2 UAT Bug #3896 (User Acceptance Test): Fund Transfer in FCR: Session Timeout
- 14:19 Maybank Bii Internet Banking Phase 2 UAT Task #3740 (User Acceptance Test): M2U Receipt : Reduce font size
- 14:18 Maybank Bii Internet Banking Phase 2 UAT Task #3742 (User Acceptance Test): TAC Window Pop Up Look & Feel
- 14:17 Maybank Bii Internet Banking Phase 2 UAT Task #3741 (User Acceptance Test): M2U Receipt: Change dual language to single language
November 01, 2013
- 00:51 Task #3475: Data warehouse report
- Hi Chee Ping,
FYI, Please make sure to delete record in IB_RPT_LIST before generate report for particular date.
E...
October 30, 2013
- 20:04 Maybank Bii Internet Banking Phase 2 UAT Bug #3897 (User Acceptance Test): Time Deposit: Account is Closed 54 Error
- 20:02 Maybank Bii Internet Banking Phase 2 UAT Bug #3897 (Internal Testing): Time Deposit: Account is Closed 54 Error
- We do not have closed TD account both in SIT and UAT.
- 20:01 Maybank Bii Internet Banking Phase 2 UAT Bug #3897 (Finished Development): Time Deposit: Account is Closed 54 Error
- 20:00 Maybank Bii Internet Banking Phase 2 UAT Bug #3897 (Development / Work In Progress): Time Deposit: Account is Closed 54 Error
- 18:14 Maybank Bii Internet Banking Phase 2 UAT Bug #3897 (Closed - End of life cycle): Time Deposit: Account is Closed 54 Error
- Bu Anna reported in production that if one TD account is closed, customer can't see the details of other Active TD. S...
- 18:11 Maybank Bii Internet Banking Phase 2 UAT Bug #3896 (Finished Development): Fund Transfer in FCR: Session Timeout
- 18:10 Maybank Bii Internet Banking Phase 2 UAT Bug #3896: Fund Transfer in FCR: Session Timeout
- Do the ROUND HALF EVEN for all Big Decimals with the scale set to 2.
- 18:08 Maybank Bii Internet Banking Phase 2 UAT Bug #3896 (Development / Work In Progress): Fund Transfer in FCR: Session Timeout
- 18:07 Maybank Bii Internet Banking Phase 2 UAT Bug #3896 (Closed - End of life cycle): Fund Transfer in FCR: Session Timeout
- Issue reported by Pak Wahyu:
Gabby,
Session Time Out when testing FCR transaction over USD 10.000.
ScreenC...
October 25, 2013
- 17:45 Task #3475 (Development / Work In Progress): Data warehouse report
- Finished review. But those report not able to get records after run using MainReportGenerator.java. Please fix it.
October 24, 2013
- 12:15 Task #3475 (Pending Review): Data warehouse report
- Hi Chee Ping,
Added reports:
- Bill Payment
- Interbank FTT
- Interbank Fund Transfer
- Mobile Reload
- Own A...
October 23, 2013
- 12:49 Bug #3793 (User Acceptance Test): M2U History: Pagination
- 12:46 Task #3821 (User Acceptance Test): BII CC Payment: Change De102 Message Format
- 11:41 Bug #3793: M2U History: Pagination
- * Already done testing.
* The result :
- m2u history show pagination more than 1 page (file attach). - 11:15 Task #3821: BII CC Payment: Change De102 Message Format
- * Already done testing.
* The result :
1. For testing on free amount(session expired when click submit), full amo...
October 22, 2013
- 18:54 Task #3567: MSS BRS
- Thomas is reviewing it since 22nd October 2013 evening.
- 18:54 Task #3566 (Pending Customer Feedback): RIB BRS
- Thomas is reviewing it since 22nd October 2013 evening.
- 18:54 Task #3567 (Pending Customer Feedback): MSS BRS
- 18:53 Maybank Bii Internet Banking Phase 2 UAT Task #3748 (User Acceptance Test): New Requirement: Loan "PITA" Account
- 18:51 Maybank Bii Internet Banking Phase 2 UAT Task #3757 (User Acceptance Test): Mobile Postpaid & Prepaid : Change Format at Bit 37
- 18:50 Maybank Bii Internet Banking Phase 2 UAT Task #3758 (User Acceptance Test): ON/2 Error Message: To Change Label
- 18:50 Bug #3793 (Internal Testing): M2U History: Pagination
- Mas Toomy,
Kindly test this issue that has been fixed by Najmi.
Test in UAT. Username: ribuser1, password: pass... - 18:36 Task #3821 (Internal Testing): BII CC Payment: Change De102 Message Format
- Toomy, this item has been deployed to UAT because Pak Rudhi wants to test it.
At the same please assist to make su... - 18:31 Task #3821: BII CC Payment: Change De102 Message Format
- Done development and deployed to UAT, in order for Pak Rudhi to test. I never get any successful message though De102...
- 18:27 Task #3821 (Development / Work In Progress): BII CC Payment: Change De102 Message Format
- 15:00 Task #3821 (Closed - End of life cycle): BII CC Payment: Change De102 Message Format
- Need to change the De102 Message Format to Host.
Current system: De102 = Currency Code ISO+ From Account
New requ... - 14:54 Task #3467 (Development / Work In Progress): Biller Reconciliation
October 21, 2013
- 17:35 Task #3467: Biller Reconciliation
- Hi Chee Ping,
Biller reconciliation requirement has been changed to suit with Typ3 Citynet format.