September 08, 2016
- 14:48 Support #6340 (Work Completed-End life cycle): [TPMS_GL006] - Post EVENT > JPPPA Report > Fast Fact
- Email to Inteksoft on 16 Jun 16 to get feedback from user. But no reply. Issue closed .
Salam Anis,
?
Based on ... - 14:38 Support #6545 (User Acceptance Test): [TPMS_GL048] - Publication >> Email Marketing
- Tested & Passed. Page will look fine after run the script given.
Send for user testing & verification. - 14:29 Support #6560 (User Acceptance Test): [TPMS_GL052] - Promotion >> Promotion Report >> Company De...
- Tested & Passed. All value display accordingly.
Send for user testing & verification.
September 07, 2016
- 12:19 Support #6520 (Pending Prod Deployment): [TPMS_GL043] - Promotion >> Event Setup >> Product and S...
- 7 Sept 2016 12:02 PM
Dear Ayu,
Done verified on 18 August 2016.
Regards,
Azliza Husain
Application ... - 12:12 Change #6559 (Pending Customer Feedback): [TPMS_GL051] - Promotion >> Business Meeting >> Busines...
- Waiting reply from Teo.
- 12:07 Change #6427: [TPMS_GL023] - Group Management
- Hi Chee Ping,
Kindly assist on both quotation. - 12:06 Change #6427 (Documentation): [TPMS_GL023] - Group Management
- *+22 July 2016+*
Salam En. Rizal,
Below is summary on this issue:
1. TPMS module permission for view, crea... - 11:58 Support #6370 (Work Completed-End life cycle): [TPMS_GL010] - Publication >> Company Profile Writ...
- 11:28 Support #6560 (Internal Testing): [TPMS_GL052] - Promotion >> Promotion Report >> Company Detali...
- Issue:
For Promotion Report, Company Detalis - Foreign Buyer(No of Buyers By product/service, order by Foreign Buyer... - 11:01 Support #6560 (Development / Work In Progress): [TPMS_GL052] - Promotion >> Promotion Report >> ...
September 06, 2016
- 14:39 Support #6560 (Work Completed-End life cycle): [TPMS_GL052] - Promotion >> Promotion Report >> C...
- Inteksoft Case ID : TPMS/16-0052
The total of Foreign Buyer for each products / services is not correct. (refer to... - 14:08 Support #6545 (Internal Testing): [TPMS_GL048] - Publication >> Email Marketing
- Issue:
Cannot edit email marketing draft for event EXPORT ACCELERATION MISSION (EAM) IN CONJUNCTION WITH MALAYSIA IN...
September 05, 2016
- 10:17 Change #6559 (Dropped-End of life cycle): [TPMS_GL051] - Promotion >> Business Meeting >> Busines...
- Users can not proceed with business match setup cause of mandatory fields(Lunch Break Time).
Business meeting sta...
September 02, 2016
- 12:35 Support #6544 (Pending Prod Deployment): [TPMS_GL025] - Administration >> Template Manager >> Not...
- 2/9/2016 12.13pm
Dear Ayu,
Done verified.
Regards,
Azliza Husain
Application Unit
Information ... - 11:47 Support #6544 (User Acceptance Test): [TPMS_GL025] - Administration >> Template Manager >> Notifi...
- Issue tested & passed. Send for user testing & verification.
September 01, 2016
- 15:17 Support #6505 (Work Completed-End life cycle): [TPMS_GL037] - Promotion >> Event Setup >> Committee
- Migration ID: TPMS_ID0014
War File: TPMS_v043
Planed Deployment date: 29/08/2016
Actual Deployent date: 30/08/2016 - 15:16 Support #6532 (Work Completed-End life cycle): [TPMS_GL046] - MATRADE Portal >> List Of Participa...
- 15:16 Support #6532: [TPMS_GL046] - MATRADE Portal >> List Of Participant >> View Write-Up
- Migration ID: TPMS_ID0014
War File: TPMS_v043
Planed Deployment date: 29/08/2016
Actual Deployent date: 30/08/2016 - 15:15 Support #6534 (Work Completed-End life cycle): [TPMS_GL047] - Planning >> Budget >> Activity Budg...
- Migration ID: TPMS_ID0014
War File: TPMS_v043
Planed Deployment date: 29/08/2016
Actual Deployent date: 30/08/2016 - 14:53 Support #6544 (Internal Testing): [TPMS_GL025] - Administration >> Template Manager >> Notificati...
- Issue:
Meeting date is not showing in No Meeting email notification.
Cause:
Meeting date in No Meeting email is ... - 10:18 Support #6544 (Development / Work In Progress): [TPMS_GL025] - Administration >> Template Manager...
August 30, 2016
- 16:14 Support #6463 (Work Completed-End life cycle): [TPMS_GL029] - Post Event >> Programmes >> Feedbac...
- 16:07 Support #6463 (User Acceptance Test): [TPMS_GL029] - Post Event >> Programmes >> Feedback - Updat...
- 30/8/2016 2:43 PM
Cik Siti Norahayu,
As of today, i have not received new report from users this issues occ... - 10:12 Support #6545 (Development / Work In Progress): [TPMS_GL048] - Publication >> Email Marketing
August 29, 2016
- 17:44 Support #6545 (Work Completed-End life cycle): [TPMS_GL048] - Publication >> Email Marketing
- Case ID : TPMS/16-0048
There is an error when click Edit Button.
please refer attachment. - 16:15 Support #6544 (Work Completed-End life cycle): [TPMS_GL025] - Administration >> Template Manager ...
- Case ID : TPMS/16-0025
Secretariat for INSP KOIMA had send email notification No Meeting to Malaysian companies wh...
August 25, 2016
- 15:15 Support #6463 (Pending Customer Feedback): [TPMS_GL029] - Post Event >> Programmes >> Feedback - ...
- I have email to Helmi to monitor on this issue. if no other issue until end of August this issue will automatically c...
- 15:10 Support #6505 (Pending Prod Deployment): [TPMS_GL037] - Promotion >> Event Setup >> Committee
- 25/08/2016 2:50 PM
Dear Ayu,
Done testing last week but forgot to send email.
Sorry for the late feedback...
August 23, 2016
- 17:47 Support #6463 (Internal Testing): [TPMS_GL029] - Post Event >> Programmes >> Feedback - Update co...
- For this issue, cannot replicate in UAT. Update has been deployed to production. Required Matrade IT member to monito...
- 17:41 Change #6427 (Pending Customer Feedback): [TPMS_GL023] - Group Management
- 16:17 Support #6370: [TPMS_GL010] - Publication >> Company Profile Write Up
- This issue can be closed since company has been able to upload images for company profile write-up up until now.
- 16:09 Support #6534 (Pending Prod Deployment): [TPMS_GL047] - Planning >> Budget >> Activity Budget All...
- 23/8/2016 2:49 PM
Dear Ayu,
Done verified.
Regards,
Azliza Husain
Application Unit
Information... - 16:08 Support #6532 (Pending Prod Deployment): [TPMS_GL046] - MATRADE Portal >> List Of Participant >> ...
- 23/8/2016 2:46 PM
Dear Ayu,
Done verified.
Regards,
Azliza Husain
Application Unit
Information T... - 16:04 Support #6534 (User Acceptance Test): [TPMS_GL047] - Planning >> Budget >> Activity Budget Alloca...
- Testing & Passed. Send for user testing & verification.
- 12:39 Support #6534 (Internal Testing): [TPMS_GL047] - Planning >> Budget >> Activity Budget Allocation
- Note: This issue only happens in Production.
Issue:
For GITEX event, received error page in Budget Activity Alloc... - 12:31 Support #6534 (Development / Work In Progress): [TPMS_GL047] - Planning >> Budget >> Activity Bud...
- 12:30 Support #6534 (Work Completed-End life cycle): [TPMS_GL047] - Planning >> Budget >> Activity Budg...
- There is an error (blue screen) when click button Activity Allocation for event GITEX 2016.
- 12:00 Support #6532 (User Acceptance Test): [TPMS_GL046] - MATRADE Portal >> List Of Participant >> Vie...
- Testing & Passed. Send for user testing & verification.
August 22, 2016
- 15:01 Support #6532 (Internal Testing): [TPMS_GL046] - MATRADE Portal >> List Of Participant >> View Wr...
- Issue:
Label mistake for programme type Export Acceleration Mission, image table is labeled as product/service inste... - 13:37 Support #6532 (Development / Work In Progress): [TPMS_GL046] - MATRADE Portal >> List Of Particip...
- 11:42 Support #6532 (Work Completed-End life cycle): [TPMS_GL046] - MATRADE Portal >> List Of Participa...
- There is an error when click View Write-up in MATRADE portal. If programme type is Export Acceleration Mission, the w...
- 09:53 Support #6527 (Work Completed-End life cycle): [TPMS_GL045] - Planning >> Budget >> Annual Alloca...
- Migration ID: TPMS_ID0013
War File: TPMS_v042
Deployed date: 19/08/2016 - 09:52 Support #6526 (Work Completed-End life cycle): [TPMS_GL044] - Planning >> Activities List >> Add ...
- Migration ID: TPMS_ID0013
War File: TPMS_v042
Deployed date: 19/08/2016
August 19, 2016
- 16:43 Support #6526 (Pending Prod Deployment): [TPMS_GL044] - Planning >> Activities List >> Add Activi...
- 19/8/2016 4:28
Dear Ayu,
Issue tested in uat environment. Start date can select backdated date.
Thank You... - 16:12 Support #6526 (User Acceptance Test): [TPMS_GL044] - Planning >> Activities List >> Add Activity ...
- Tested & Passed. Send for user testing and verification.
- 16:00 Support #6527 (Pending Prod Deployment): [TPMS_GL045] - Planning >> Budget >> Annual Allocation
- 19/8/2016 3:07 PM
Dear Ayu,
Tested & successful.
Regards,
Rozaina Ali
IT Manager
MATRADE
Tel: +603... - 15:57 Support #6526 (Internal Testing): [TPMS_GL044] - Planning >> Activities List >> Add Activity / Ed...
- Fixed minimum end date based on start date. Please test.
- 12:03 Support #6527 (User Acceptance Test): [TPMS_GL045] - Planning >> Budget >> Annual Allocation
- Tested & Passed. Send for user testing n verification.
- 12:00 Support #6526 (Development / Work In Progress): [TPMS_GL044] - Planning >> Activities List >> Add...
- Hi Najmi,
Select start date on 2015 but end date show only 2016 on words.
- 11:43 Support #6516 (Pending Customer Feedback): [TPMS_GL042] - Promotion >> Handbook >> Print
- Cause:
If company profile upload image before Support #6373 [TPMS_GL013] - Promotion >> Handbook Printing update, th... - 11:39 Support #6526 (Internal Testing): [TPMS_GL044] - Planning >> Activities List >> Add Activity / Ed...
- Issue:
Planning module start date is limited to today and future only. Thus, preventing Matrade officer from adding ... - 11:34 Support #6527 (Internal Testing): [TPMS_GL045] - Planning >> Budget >> Annual Allocation
- Issue:
Unable to submit Budget Annual Allocation.
Cause:
Audit trail failed to get user id and disabled Budget A... - 11:30 Support #6526 (Development / Work In Progress): [TPMS_GL044] - Planning >> Activities List >> Add...
- 11:29 Support #6527 (Development / Work In Progress): [TPMS_GL045] - Planning >> Budget >> Annual Alloc...
- 10:22 Support #6527 (Work Completed-End life cycle): [TPMS_GL045] - Planning >> Budget >> Annual Alloca...
- Finance Unit were unable to submit changes made in Annual Allocation menu with error 'Failed to load resource: the se...
- 10:15 Support #6526 (Work Completed-End life cycle): [TPMS_GL044] - Planning >> Activities List >> Add ...
- Start date in planning module can not select backdated date. User can not create backdated event date in TPMS.
Be...
August 18, 2016
- 11:31 Support #6505 (User Acceptance Test): [TPMS_GL037] - Promotion >> Event Setup >> Committee
- Loading time took less than a minute.
When removing name to the left when its previously on the right, the name wil... - 11:20 Support #6512: [TPMS_GL041] - Planning >>Budget >> Activity Budget Allocation
- Migration ID: TPMS_ID0012
War File: TPMS_v041
Deployed date: 17/08/2016 - 11:20 Support #6511: [TPMS_GL040] - Planning >> Budget >> Activity Budget Allocation
- Migration ID: TPMS_ID0012
War File: TPMS_v041
Deployed date: 17/08/2016 - 11:19 Support #6510: [TPMS_GL039] - Planning >> Budget >> Activity Budget Allocation
- Migration ID: TPMS_ID0012
War File: TPMS_v041
Deployed date: 17/08/2016 - 11:19 Support #6504: [TPMS_GL036] - Promotion >> Event Setup
- Migration ID: TPMS_ID0012
War File: TPMS_v041
Deployed date: 17/08/2016 - 11:18 Support #6496: [TPMS_GL035] - Post Event >> Programmes >> Feedback >> View Form (Malaysia & Foreign)
- Migration ID: TPMS_ID0011
War File: TPMS_v040
Deployed date: 10/08/2016 - 11:18 Support #6493: [TPMS_GL034] - Planning >> Export as
- Migration ID: TPMS_ID0011
War File: TPMS_v040
Deployed date: 10/08/2016 - 11:17 Support #6478: [TPMS_GL032] - Planning - Budget Report
- Migration ID: TPMS_ID0011
War File: TPMS_v040
Deployed date: 10/08/2016 - 11:17 Support #6454: [TPMS_GL026] - Error in Planning - Total sales generated
- Migration ID: TPMS_ID0011
War File: TPMS_v040
Deployed date: 10/08/2016 - 11:16 Support #6468: [TPMS_GL031] - Post Event JPPPA - Audit log is not captured / displayed
- Migration ID: TPMS_ID0010
War File: TPMS_v039
Deployed date: 01/08/2016 - 11:16 Support #6466: [TPMS_GL030] - Planning >> Add Activity
- Migration ID: TPMS_ID0010
War File: TPMS_v039
Deployed date: 01/08/2016 - 11:15 Support #6456: [TPMS_GL028] - Post Event >> Programmes >> Feedback
- Migration ID: TPMS_ID0010
War File: TPMS_v039
Deployed date: 01/08/2016 - 11:15 Support #6455: [TPMS_GL027] - Post Event >> Programmes >> Feedback - Sales record not saved.
- Migration ID: TPMS_ID0010
War File: TPMS_v039
Deployed date: 01/08/2016 - 11:14 Support #6428: [TPMS_GL024] - Company Write Up >> Public - Unable to click submit
- Migration ID: TPMS_ID0009
War File: TPMS_v038
Deployed date: 22/07/2016 - 11:14 Support #6426: [TPMS_GL022] - Company Write Up - Public
- Migration ID: TPMS_ID0009
War File: TPMS_v038
Deployed date: 22/07/2016 - 11:13 Support #6408: [TPMS_GL021] - Promotion >> New Registration (Internal & External)
- Migration ID: TPMS_ID0008
War File: TPMS_v037
Deployed date: 15/07/2016 - 11:13 Support #6403: [TPMS_GL017] - Promotion >> Business Meeting >> Foreign Buyer List >> Export as PD...
- Migration ID: TPMS_ID0008
War File: TPMS_v037
Deployed date: 15/07/2016 - 11:13 Support #6404: [TPMS_GL018] - Planning >> Report >> Planning JPPPA Report - Label of report filte...
- Migration ID: TPMS_ID0008
War File: TPMS_v037
Deployed date: 15/07/2016 - 11:13 Support #6360: [TPMS_GL008] - JPPPA Module
- Migration ID: TPMS_ID0008
War File: TPMS_v037
Deployed date: 15/07/2016 - 11:12 Support #6407: [TPMS_GL020] - Promotion
- Migration ID: TPMS_ID0007
War File: TPMS_v036
Deployed date: 13/07/2016 - 11:12 Support #6375: [TPMS_GL015] - Audit Trail for Registration Form & Company Profile Write Up
- Migration ID: TPMS_ID0007
War File: TPMS_v036
Deployed date: 13/07/2016 - 11:11 Support #6371: [TPMS_GL011] - Administration > Currency Rate
- Migration ID: TPMS_ID0006
War File: TPMS_v035
Deployed date: 04/07/2016 - 11:11 Support #6384: [TPMS_GL016] - Planning >> Activities List >> Search for Activity Name >> Edit
- Migration ID: TPMS_ID0006
War File: TPMS_v035
Deployed date: 04/07/2016 - 11:11 Support #6373: [TPMS_GL013] - Promotion >> Handbook Printing
- Migration ID: TPMS_ID0006
War File: TPMS_v035
Deployed date: 04/07/2016 - 11:10 Support #6372: [TPMS_GL012] - MATRADE Portal > List of Participants
- Migration ID: TPMS_ID0006
War File: TPMS_v035
Deployed date: 04/07/2016 - 11:10 Support #6361: [TPMS_GL009] - Promotion >> Regitration Malaysian Company (Public)
- Migration ID: TPMS_ID0005
War File: TPMS_v034
Deployed date: 21/06/2016 - 11:09 Support #6520 (User Acceptance Test): [TPMS_GL043] - Promotion >> Event Setup >> Product and Service
- Tested & Passed. Send for user testing and verify.
- 11:03 Support #6520 (Internal Testing): [TPMS_GL043] - Promotion >> Event Setup >> Product and Service
- Issue:
Error message pop up when click Product and Service tab in Promotion > Event Setup
Cause:
Wrong committee... - 10:53 Support #6520 (Development / Work In Progress): [TPMS_GL043] - Promotion >> Event Setup >> Produc...
- 10:52 Support #6338: [TPMS_GL005] - Publication >> Email Marketing
- Migration ID: TPMS_ID0004
War File: TPMS_v033
Deployed date: 16/06/2016 - 10:52 Support #6337: [TPMS_GL004] - Post Event >> Event Report - Total Sales by Event
- Migration ID: TPMS_ID0004
War File: TPMS_v033
Deployed date: 16/06/2016 - 10:52 Support #6520 (Work Completed-End life cycle): [TPMS_GL043] - Promotion >> Event Setup >> Product...
Inteksoft Case ID : TPMS/16-0043
Pop up an error message when click Product and Service button for this event.
...- 10:51 Support #6327: [TPMS_GL003] - Post Event >> Event Report >> Total Sales by Event
- Migration ID: TPMS_ID0004
War File: TPMS_v033
Deployed date: 16/06/2016 - 10:50 Support #6307: [TPMS_GL001] - Planning >> Activity List >> Export as
- Migration ID: TPMS_ID0003
War File: TPMS_v032
Deployed date: 10/06/2016 - 10:18 Support #6504 (Work Completed-End life cycle): [TPMS_GL036] - Promotion >> Event Setup
- 10:17 Support #6506 (Work Completed-End life cycle): [TPMS_GL038] - Promotion -> Handbook printing
- 10:17 Support #6510 (Work Completed-End life cycle): [TPMS_GL039] - Planning >> Budget >> Activity Budg...
- 10:16 Support #6511 (Work Completed-End life cycle): [TPMS_GL040] - Planning >> Budget >> Activity Budg...
- 10:15 Support #6512 (Work Completed-End life cycle): [TPMS_GL041] - Planning >>Budget >> Activity Budge...
- 10:14 Support #6516 (Development / Work In Progress): [TPMS_GL042] - Promotion >> Handbook >> Print
August 17, 2016
- 17:25 Support #6516 (Work Completed-End life cycle): [TPMS_GL042] - Promotion >> Handbook >> Print
- Some image of representative did not displayed in handbook.
Please refer attachment
- 16:34 Support #6506 (Pending Prod Deployment): [TPMS_GL038] - Promotion -> Handbook printing
- 17/8/2016 4:26 PM
Ayu,
Done verified.
Regards,
Azliza Husain
Application Unit
Information Te... - 11:43 Support #6505 (Internal Testing): [TPMS_GL037] - Promotion >> Event Setup >> Committee
- Issue:
Listing name for Data Entry, Attendance Monitor, Liaison Officer not loading in Promotion Committee Setup.
...
August 16, 2016
- 11:27 Support #6512 (Pending Prod Deployment): [TPMS_GL041] - Planning >>Budget >> Activity Budget Allo...
- 16/8/2016 10:50 AM
Dear Ayu.
Done verified.
Regards,
Azliza Husain
Application Unit
Information Technol... - 11:26 Support #6510 (Pending Prod Deployment): [TPMS_GL039] - Planning >> Budget >> Activity Budget All...
- 16/8/2016 10:50 AM
Dear Ayu.
Done verified.
Regards,
Azliza Husain
Application Unit
Information Technol... - 11:20 Support #6511 (Pending Prod Deployment): [TPMS_GL040] - Planning >> Budget >> Activity Budget All...
16/8/2016 10:50 AM
Dear Ayu.
Done verified.
Regards,
Azliza Husain
Application Unit
Information ...