October 26, 2010

19:23 MPI_Banking_System_Business_Requirement_Specification_v1.0.pdf
Tan Lee Yong
19:23 MPI_Banking_System_Design_Doc.docx
Tan Lee Yong
19:23 MPI_Banking_Data_Dictionary.docx
Tan Lee Yong
19:23 Document: MPI Design Docs
Tan Lee Yong
14:07 Task #581: MPI Technical Doc: Table Glossary Document
I've done putting all the necessary tables. Need Jelson to double check on it maybe there is unused column that need ... Sarinah Darsy

October 25, 2010

18:42 Task #495 (Work Completed-End life cycle): Compile MPI Retail & SME Banking BRS
Completed the BRS. attached. Ang Wei Cheng
16:14 Task #581 (Development / Work In Progress): MPI Technical Doc: Table Glossary Document
Sarinah Darsy
16:13 Task #581: MPI Technical Doc: Table Glossary Document
Not yet included table from Jelsons' one. Sarinah Darsy
14:53 Task #581 (Work Completed-End life cycle): MPI Technical Doc: Table Glossary Document
Done the Table glossary. Danniel & Wei Cheng Please check the doc attached to check whether the description is correc... Sarinah Darsy

October 22, 2010

17:07 Task #581 (Development / Work In Progress): MPI Technical Doc: Table Glossary Document
Already get the table info from Daniell & Wei Cheng but don't get yet from jelson. Sarinah Darsy
11:50 Task #581 (Closed - End of life cycle): MPI Technical Doc: Table Glossary Document
To create table glossary document. Please get the tables from Danniell, Wei Cheng and Jelson. Tan Lee Yong
11:46 Setup_JMS_on_Weblogic.docx
Tan Lee Yong
11:46 EJB_EAR_compilation_for_WebLogic_10.docx
Tan Lee Yong
11:46 Integration_Design.pdf
Tan Lee Yong
11:46 Document: JMS Setup Document
Tan Lee Yong
11:45 Task #466 (Closed - End of life cycle): Setup JMS at Site Office Development server
Tan Lee Yong
11:44 Task #453: Install WebLogic to Site Offce Development Server and SVN Server
what is the status on this task? Tan Lee Yong
11:42 Task #485: Add more features on navigation for Maybank COSS
Is this task completed? Tan Lee Yong

October 21, 2010

15:23 Task #576 (Closed - End of life cycle): MPI BRS: Screen Flow Creation
Assist Wei Cheng to create screen flow for MPI project. Tan Lee Yong
15:18 Task #575 (Closed - End of life cycle): MPI BRS: Create Process Flow
To study, understand the business requirement doc, create process flow and pass to Wei Cheng to integrate. Tan Lee Yong

October 19, 2010

17:53 MPI_Portal_SOW_-20101019.docx
Tan Lee Yong
17:53 Document: SOW
Scope Of Work Tan Lee Yong
17:08 Task #495: Compile MPI Retail & SME Banking BRS
Get the requirement doc from the Document tab for this project under the Final Requirement doc from Hui Lee.
Compile...
Tan Lee Yong
16:53 Final_Sign_Off_BR_121010.zip
Tan Lee Yong
16:53 Document: Final Requirement Doc from Hui Lee
Tan Lee Yong
16:53 MPI_SIGN_OFF.pdf
Tan Lee Yong

October 07, 2010

10:31 Task #494 (Work Completed-End life cycle): Compile MPI Administration Module BRS
Completed BRS for MPI administration module v1:
* Navigation module
* Retail module
* Business module
* System mo...
Cheang Danniell

September 30, 2010

02:32 Task #495: Compile MPI Retail & SME Banking BRS
Please go to the Document menu to see all the given user requirement docs under MPI First Requirement Doc from Dennis Tan Lee Yong
02:32 BR_MPI_Module_2.doc
Tan Lee Yong
02:32 BR_MPI_Module_4.doc
Tan Lee Yong
02:32 BR_MPI_Module_3.doc
Tan Lee Yong
02:32 BR_MPI_Module_5.doc
Tan Lee Yong
02:32 BR_MPI_Module_1.doc
Tan Lee Yong
02:32 BR_MPI_Module_10.doc
Tan Lee Yong
02:32 Document: MPI First Requirement Doc from Dennis
Tan Lee Yong
02:32 BR_MPI_Module_8.doc
Tan Lee Yong
02:32 BR_MPI_Module_6.doc
Tan Lee Yong
02:32 BR_MPI_Module_9.doc
Tan Lee Yong
02:22 Task #495 (Closed - End of life cycle): Compile MPI Retail & SME Banking BRS
Compile the MPI Retail banking and Business Banking BRS with page flow diagrams, screen snap shots, elaboration on th... Tan Lee Yong
02:17 Task #485 (Development / Work In Progress): Add more features on navigation for Maybank COSS
Danniell requested to do a few amendments on Tue, Sep 28, 2010 at 3:14 PM:-
Hi Nazri,
There are a few amendments...
Tan Lee Yong
02:13 Task #494: Compile MPI Administration Module BRS
Danniell is compiling the document with flow diagram and Nazri is assist to create the screen shots. Tan Lee Yong
02:11 Task #494 (Closed - End of life cycle): Compile MPI Administration Module BRS
Compile MPI administration module BRS Tan Lee Yong
 